Attachment_III_-_Option_1_-_SOW_with_photos.pdf
PDF 1 MB Posted
- Attached to
- Electrical Upgrade in Building 13 Federal contract opportunity
- Solicitation number
- 1232SDS18JC06
About this file
Attachment III - Option 1 SOW w/Photos
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF-30_Amendment_03.pdf | ||
| SF-30_Amendment_02.pdf | ||
| Amendment_1.pdf | ||
| Solicitation_-_1232SDS18JC06.pdf | ||
| Attachment_V_-_Payment_and_Performance_Bond_Forms.pdf | ||
| Attachment_IV_-_DBA_Wage_Rates.pdf | ||
| Attachment_II_-_Drawings_for_base.pdf | ||
| Attachment_I_-_Specifications_for_base.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
B13 ELECTRICAL UPGRADE
Option 1 600 AMP MDP Replacement
HONEY BEE BREEDING, GENETICS &
PHYSIOLOGY RESEARCH
BATON ROUGE LA
Date: 5/3/2018
STATEMENT OF WORK
Construction
1. Intent of option is to replace 600 AMP MDP panel on Building 11 and replace conduit and conductors from Building 11 to Building 13 400 AMP panel being replaced in base bid.
a. Provide and install new 600 amp I line Panel Board NEMA 3R with 3 each 225 amp circuit breakers, 1 each 200 amp breaker, 2 each 60 amp breakers, to replace existing 600 AMP MDP. Pictures of existing MDP attached.
b. Provide and install new properly sized conduit and properly sized 400 amp feeder to Building 13. Estimate of 160 feet 3 inch conduit and 1280 feet 3/0 conductors. Contractor to verify all dimensions, sizes, etc. before bidding.
c. Remove and properly dispose of existing conductors to Building 13.
d. Project intent is to disconnect, label and reconnect other existing circuits to the new panel board.
e. Properly repair all trenching, asphalt, concrete, etc. as needed disturbed by construction.
f. Government will assist in location of utilities, but contractor is responsible for protection of utilities at all time and for repair if damaged.
2. General Notes A thru D of sheet E100, B13 Electrical Upgrade, apply to this option.
3. All work to be per specifications in B13 Electrical Upgrade drawings and specs.
4. All work to be per State, Local and Federal guidelines, and per applicable UFGS specifications.
These can be found listed on the Whole Building Design Guide Construction Criteria Base UFGS page at : https://www.wbdg.org/ccb/browse_cat.php?c=3
5. Exercise of this option increases period of performance by 60 days.
https://www.wbdg.org/ccb/browse_cat.php?c=3
600 AMP MDP Picture 1
600 AMP MDP Picture 2
600 AMP MDP Picture 3
B11 MDP and B13 Panels (Inside/Interior) Location Map
| United States Department of Agriculture |
| Agricultural Research Service |
| HONEY BEE BREEDING, GENETICS & PHYSIOLOGY RESEARCH |
| BATON ROUGE LA |
File details come from the government source that posted it.