1232SD18B0001_Amd_0002.pdf

PDF 95 KB Posted

Attached to
Greenhouse Upgrades Federal contract opportunity
Solicitation number
1232SD18R0003
Issued by
Department of Agriculture Agricultural Research Service Central Program Planning Coordination and Support

About this file

1232SD18B0001 Amd 0002

View the file

Other files for this federal contract opportunity

Other files attached to Greenhouse Upgrades, newest first.
File Type Posted
1232SD18B0001_Amd_0005.pdf PDF
1232SD18B0001_Amd_0004.pdf PDF
1232SD18B0001_Amd_0003.pdf PDF
Calculation_of_Self_Performed_Work.xlsx XLSX spreadsheet
Pre-bid_sign_in_sheet.PDF PDF
Asbestos_Report_16-02-02015.PDF PDF
Pre_Bid_Agenda.pdf PDF
1232SD18B0001_Amd_0001.pdf PDF
Wage_Determination_NE180058_02-02-2018__NE58.pdf PDF
Calculation_of_Self_Performed_Work.xlsx XLSX spreadsheet
ars371.pdf PDF
Drawings.pdf PDF
Contractor_Certification_Regarding_EMR.pdf PDF
Greenhouse_Upgrade_Phase_II_SOW.pdf PDF
1232SD18B0001.pdf PDF
RFI_FORM.pdf PDF
ars372.pdf PDF
Specifications.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1232SD18B0001

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

LINCOLN NE 68583-0937

ARS-NPA-5440-02

UNIVERSITY OF NEBRASKA

251 FILLEY HALL/FOOD INDUSTRY COMPL

USDA-ARS-PA

USDA ARS GRAIN FORAGE & BIOENERGY R

ARS-WBSC-0330-05-T

Peoria IL 61604 1815 N University St ARS WBSC Contracting, Acquisition, ARS WBSC Contracting, Acquisition, 02/23/20180002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/23/2018

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to provide the agenda and sign in sheet for the pre-bid site visit.

Also provided in this amendment is a partial list of answers to question presented for clarification.

Q1.The scope of work states that the period of performance is 120 calendar days. In the condition that alternates 1 or 2 are awarded, will there be additional days added to the duration of the overall project, or is all work awarded to be completed in 120 calendar days?

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

JEFFERY A. RIDENOUR

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

1232SD18B0001/0002

A1. The period of performance for the all work whether or not alternates have been awarded shall be 180 calendar days.

Q2. The specifications state that there are liquidated damages incurred for not completing the project prior to the established deadline, but there is no monetary value placed on the liquidated damages that we can find. Could you please advise as to what these costs are, if there are any?

A2. No liquated damages shall be accessed for this project.

Q3. As discussed at the site visit, there was to be an asbestos report provided to establish the information needed to accurately price out abatement work that was not provided with the original contract documents. Could you please provide this asbestos survey?

A3. The government will provide the asbestos survey. See attached document

Q.4 Is there a required proprietary controls contractor for the location? Other USDA sites we have worked at have required a specific Digital

Controls contractor to perform work on the system so that the system is operated and maintained by a single system as most control systems are proprietary or specific to the location.

A4. The existing controls are pneumatic and electronic. There is not a proprietary control system at this site.

Q5. Specification section 23 64 26 on Steam

Piping seems to be a bit vague. It does not specify the schedule of steel pipe to be used for the steam piping work, this section seems to deal more with water piping than steam piping. Typical steam piping is schedule 40 and steam condensate return is schedule 80, but none of this information is listed in the specifications.

There is also no specification on the steam traps. Could you provide more information on the steam piping requirements, or make sure the steam piping specification is the correct specification to reference steam piping as applicable to this

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

1232SD18B0001/0002

project specifically.

A5. Steam piping shall be carbon steel, ASTM A53

Grade B, Seamless or Electric Resistance Welded, Schedule 40. Steam Condensate piping shall be carbon steel, ASTM A53 Grade B, Seamless or

Electric Resistance Welded, Schedule 80. Steam traps shall be Float & Thermostatic Steam Traps, Minimum 150 lbs/hr @ ¼ psi differential.

Q6. Specification 23 00 00 2.10.1 e. is this pertaining to the whole line of ductwork that is labeled O/A? Or was it pertaining to all the duct outside? Please clarify if this is the whole line or just the outside portion.

A6. Part e is for ductwork located outside.

Q7. Where is Temp-power coming to be supplied to keep power on while replacing transformer. Also, new transformer location does not meet electrical code.

A7. Contractor to provide temporary power. The new pad-mounted transformer shall meet the recommended minimum clearances as recommended by the transformer manufacturer and the NEC. The contractor shall modify/extend the existing pad as required to meet the minimum clearances.

All terms and conditions remain unchanged.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)