USDA South Building - Room 0410 Data Center Conversion Solicitation # 12314218B0010 SPECIFICATIONS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12314218B0010_Amendment___0003_dated_August_15,_2018.pdf | ||
| 12314218B0010_Amendment___0002_dated_August_08,_2018.pdf | ||
| 12314218B0010_Amendment___0001_dated_July_31,_2018.pdf | ||
| USDA_SB_Room_0410_Data_Center_Conversion_â_Sol___12314218B0010_07.13.2018.pdf | ||
| USDA_SB_Room_0410_Data_Center_Conversion_â_Sol___12314218B0010_-_DRAWINGS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
South Building - Room 0410 Data Center Conversion
Specifications Addendum #1
US Department of Agriculture Contract Number: AG-3142-C-16-0008 Deliver Order Number: AG-3142-D-17-0026 Project Number: 2017-EB-1
September 12, 2017
AECOM Project Number: 60535380
This Page Left Intentionally Blank
USDA Room 0410 September 12, 2017
Data Center Conversion Addendum #1
TABLE OF CONTENTS TOC - 1
TABLE OF CONTENTS
Division Section Title
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY
011200 MULTIPLE CONTRACT SUMMARY
012100 ALLOWANCES
012500 SUBSTITUTION PROCEDURES
013100 PROJECT MANAGEMENT AND COORDINATION
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013300 SUBMITTAL PROCEDURES
013516 ALTERATION PROJECT PROCEDURES
014000 QUALITY REQUIREMENTS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
016000 PRODUCT REQUIREMENTS
017300 EXECUTION
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 CLOSEOUT PROCEDURES
017823 OPERATION AND MAINTENANCE DATA
017839 PROJECT RECORD DOCUMENTS
017900 DEMONSTRATION AND TRAINING
019113 GENERAL COMMISSIONING REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS
024119 SELECTIVE STRUCTURE DEMOLITION
028213 ASBESTOS ABATEMENT PROCEDURES
028313 LEAD REMOVAL
028416 OTHER HAZARDOUS AND SPECIAL WASTES REMOVAL AND DISPOSAL
DIVISION 03 - CONCRETE
030130 MAINTENANCE OF CAST-IN-PLACE CONCRETE
033000 CAST-IN-PLACE CONCRETE
DIVISION 05 – METALS
055963 DETENTION ENCLOSURES
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061000 ROUGH CARPENTRY
TABLE OF CONTENTS TOC - 2
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
072100 THERMAL INSULATION
078413 PENETRATION FIRESTOPPING
079200 JOINT SEALANTS
DIVISION 08 – OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES
083113 ACCESS DOORS AND FRAMES
087100 DOOR HARDWARE
DIVISION 09 – FINISHES
092116.23 GYPSUM BOARD SHAFT WALL ASSEMBLIES
092216 NON-STRUCTURAL METAL FRAMING
092900 GYPSUM BOARD
095113 ACOUSTICAL PANEL CEILINGS
096513 RESILIENT BASE AND ACCESSORIES
096519 RESILIENT TILE FLOORING
096900 ACCESS FLOORING
099123 INTERIOR PAINTING
DIVISION 10 - SPECIALTIES
102300 HOT AISLE CONTAINMENT SYSTEM
102600 WALL AND DOOR PROTECTION
104413 FIRE PROTECTION CABINETS
104416 FIRE EXTINGUISHERS
DIVISION 21 - FIRE SUPPRESSION
211313 WET-PIPE SPRINKLER SYSTEMS
DIVISION 22 – PLUMBING
220523.12 BALL VALVES FOR PLUMBING PIPING
220523.14 CHECK VALVES FOR PLUMBING PIPING
220523.15 GATE VALVES FOR PLUMBING PIPING
220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
220719 PLUMBING PIPING INSULATION
221116 DOMESTIC WATER PIPING
221119 DOMESTIC WATER PIPING SPECIALTIES
221316 SANITARY WASTE AND VENT PIPING
221319 SANITARY WASTE PIPING SPECIALTIES
221319.13 SANITARY DRAINS
221429 SUMP PUMPS
TABLE OF CONTENTS TOC - 3
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC
230719 HVAC PIPING INSULATION
230800 COMMISSIONING OF HVAC
230923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC
230923.11 CONTROL VALVES
230923.12 CONTROL DAMPERS
232113 HYDRONIC PIPING
232116 HYDRONIC PIPING SPECIALTIES
232300 REFRIGERANT PIPING
233113 METAL DUCTS
233300 AIR DUCT ACCESSORIES
233416 CENTRIFUGAL HVAC FANS
233713.23 GRILLES
238123.12 LARGE CAPACITY (7 TONS (25 KW) AND LARGER), COMPUTER-ROOM AIR-
CONDITIONERS, FLOOR-MOUNTED UNITS
DIVISION 26 - ELECTRICAL
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
260548.16 SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
260573.13 SHORT-CIRCUIT STUDIES
260573.16 COORDINATION STUDIES
260573.19 ARC-FLASH HAZARD ANALYSIS
260800 COMMISSIONING OF ELECTRICAL SYSTEMS
260923 LIGHTING CONTROL DEVICES
262413 SWITCHBOARDS
262416 PANELBOARDS
262500 BUSWAY SYSTEM
262726 WIRING DEVICES
262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
263213.13 DIESEL EMERGENCY ENGINE GENERATORS
263353 STATIC UNINTERRUPTIBLE POWER SUPPLY
263600 TRANSFER SWITCHES
265119 LED INTERIOR LIGHTING
TABLE OF CONTENTS TOC - 4
DIVISION 27 - COMMUNICATIONS
270526 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS
270536 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
284621.11 ADDRESSABLE FIRE-ALARM SYSTEMS
END OF TABLE OF CONTENTS
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Work by Owner.
5. Owner-furnished products.
6. Access to site.
7. Coordination with occupants.
8. Work restrictions.
9. Specification and Drawing conventions.
1.3 PROJECT INFORMATION
A. Project Identification: USDA Room 0410 Data Center Conversion. USDA Project Number:
2017-EB-1.
1. Project Location: USDA South Building: 14 th & Independence Avenue Southwest, Washington DC
B. Owner: United States Department of Agriculture.
1. Owner's Representative: Gerardo Rivera. Phone: 202-720-3812.
Gerardo.rivera@dm.usda.gov.
C. Architect: AECOM Technical Services, Inc.
D. Contractor: The design bid build contractor is to be determined.
E. Project Coordinator for Multiple Contracts: Owner shall serve as Project coordinator.
F. Web-Based Project Software: Project software administered by Owner will be used for purposes of managing communication and documents during the construction stage.
SUMMARY 011000 - 2
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. The project consists of converting an existing space, approximately 1500 square feet, into a data center with auxiliary electrical spaces, and other Work indicated in the Contract
Documents.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.5 PHASED CONSTRUCTION
A. The Work shall be conducted in 1> phase.
B. Before commencing Work, submit an updated copy of Contractor's construction schedule showing the sequence, commencement and completion dates for all phases of the Work.
1.6 WORK BY OWNER
A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this
Contract with work performed by Owner.
1.7 OWNER-FURNISHED PRODUCTS
A. Owner will furnish products indicated. The Work includes receiving, unloading, handling, storing, protecting, and installing Owner-furnished products and making building services connections.
B. Owner-Furnished Products:
1. Telecom rack enclosures
2. Telecom server equipment
3. Telecom equipment cabling product and installation
1.8 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site to Work in areas indicated. Do not disturb portions of
Project site beyond areas in which the Work is indicated.
1. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
SUMMARY 011000 - 3
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.
D. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.9 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.
1.10 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of
Monday through Friday, unless otherwise indicated. Coordinate evening, weekend, and outage work times with COTR.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
SUMMARY 011000 - 4
2. Obtain Owner's written permission before proceeding with disruptive operations.
E. Restricted Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
F. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
G. Employee Screening: Comply with Owner's requirements for drug and background screening of
Contractor personnel working on Project site.
1. Maintain list of approved screened personnel with Owner's representative.
1.11 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
3. Keynoting: Materials and products are identified by reference keynotes referencing
Specification Section numbers found in this Project Manual.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
http://www.arcomnet.com/sustainable_design.aspx?topic=114 http://www.arcomnet.com/sustainable_design.aspx?topic=114
MULTIPLE CONTRACT SUMMARY 011200 - 1
SECTION 011200 - MULTIPLE CONTRACT SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes a summary of each contract, including responsibilities for coordination and temporary facilities and controls.
B. Specific requirements for Work of each contract are also indicated in individual Specification
Sections and on Drawings.
C. Related Requirements:
1. Section 011000 "Summary" for the Work covered by the Contract Documents, restrictions on use of Project site, coordination with occupants, and work restrictions.
2. Section 013100 "Project Management and Coordination" for general coordination requirements.
1.3 DEFINITIONS
A. Permanent Enclosure: As determined by Architect, the condition at which roofing is insulated and weathertight; exterior walls are insulated and weathertight; and openings are closed with permanent construction or substantial temporary closures equivalent in weather protection to permanent construction.
1.4 PROJECT COORDINATOR
A. Project coordinator shall be responsible for coordination between the General Construction
Contract and all other trades.
B. Mechanical/electrical coordinator, who shall be under the direction of Project coordinator, shall be responsible for coordination between the Plumbing Contract, HVAC Contractn and
Electrical Contract.
1. Mechanical or electrical contractor may act as the mechanical/electrical coordinator, provided they are licensed to practice as a professional engineer in the location of the project.
MULTIPLE CONTRACT SUMMARY 011200 - 2
1.5 PROJECT COORDINATOR RESPONSIBILITIES
A. Project coordinator shall perform Project coordination activities for the multiple contracts, including, but not limited to, the following:
1. Provide typical overall coordination of the Work.
2. Coordinate shared access to workspaces.
3. Coordinate product selections for compatibility.
4. Provide overall coordination of temporary facilities and controls.
5. Coordinate, schedule, and approve interruptions of permanent and temporary utilities, including those necessary to make connections for temporary services.
6. Coordinate construction and operations of the Work with work performed by each
Contract.
7. Prepare coordination drawings in collaboration with each contractor to coordinate work by more than one contract.
8. Coordinate sequencing and scheduling of the Work. Include the following:
a. Initial Coordination Meeting: At earliest possible date, arrange and conduct a meeting with contractors for sequencing and coordinating the Work; negotiate reasonable adjustments to schedules.
b. Prepare combined Contractors' Construction Schedule for entire Project. Base schedule on preliminary construction schedule. Secure time commitments for performing critical construction activities from contractors. Show activities of each contract on a separate sheet. Prepare a simplified summary sheet indicating combined construction activities of contracts.
1) Submit schedules for approval.
2) Distribute copies of approved schedules to contractors.
9. Provide photographic documentation.
10. Provide quality-assurance and quality-control services specified in Section 014000
"Quality Requirements."
11. Coordinate sequence of activities to accommodate tests and inspections, and coordinate schedule of tests and inspections.
12. Provide information necessary to adjust, move, or relocate existing utility structures affected by construction.
13. Locate existing permanent benchmarks, control points, and similar reference points, and establish permanent benchmarks on Project site.
14. Provide field surveys of in-progress construction and site work and final property survey.
15. Provide progress cleaning of common areas and coordinate progress cleaning of areas or pieces of equipment where more than one contractor has worked.
16. Coordinate cutting and patching.
17. Coordinate protection of the Work.
18. Coordinate firestopping.
19. Coordinate completion of interrelated punch list items.
20. Coordinate preparation of Project Record Documents if information from more than one contractor is to be integrated with information from other contractors to form one combined record.
21. Print and submit Record Documents if installations by more than one contractor are indicated on the same Contract Drawing or Shop Drawing.
MULTIPLE CONTRACT SUMMARY 011200 - 3
22. Collect record Specification Sections from contractors, collate Sections into numeric order, and submit complete set.
23. Coordinate preparation of operation and maintenance manuals if information from more than one contractor is to be integrated with information from other contractors to form one combined record.
B. Responsibilities of Project coordinator for temporary facilities and controls include, but are not limited to, the following:
1. Provide common-use field office for use by all personnel engaged in construction activities.
2. Provide telephone service for common-use facilities.
C. Mechanical/Electrical Coordinator: Coordination activities of mechanical/electrical coordinator include, but are not limited to, the following:
1. Schedule and sequence mechanical and electrical activities.
2. Coordinate sharing access to workspaces by mechanical and electrical contractors.
3. Coordinate integration of mechanical and electrical work into limited spaces.
4. Coordinate protection of mechanical and electrical contractors' work.
5. Coordinate cutting and patching for mechanical and electrical work.
6. Prepare mechanical and electrical coordination drawings.
7. Coordinate tests and inspections for mechanical and electrical work.
8. Coordinate mechanical and electrical temporary services and facilities.
1.6 GENERAL REQUIREMENTS OF CONTRACTS
A. Extent of Contract: Unless the Agreement contains a more specific description of the Work of each Contract, requirements indicated on Drawings and in Specification Sections determine which contract includes a specific element of Project.
1. Unless otherwise indicated, the work described in this Section for each contract shall be complete systems and assemblies, including products, components, accessories, and installation required by the Contract Documents.
2. Blocking, backing panels, sleeves, and metal fabrication supports for the work of each contract shall be the work of each contract for its own work.
3. Furnishing of access panels for the work of each contract shall be the work of each contract for its own work. Installation of access panels shall be the work of each contract for its own work.
4. Equipment pads for the work of each contract shall be the work of each contract for its own work.
5. Roof-mounted equipment curbs for the work of each contract shall be the work of each contract for its own work.
6. Painting for the work of each contract shall be the work of each contract for its own work.
7. Cutting and Patching: Provided under each contract for its own work.
8. Through-penetration firestopping for the work of each contract shall be provided by each contract for its own work.
9. Contractors' Startup Construction Schedule: Within five working days after startup horizontal bar-chart-type construction schedule submittal has been received from Project
MULTIPLE CONTRACT SUMMARY 011200 - 4
coordinator, submit a matching startup horizontal bar-chart schedule showing construction operations sequenced and coordinated with overall construction.
B. Substitutions: Each contractor shall cooperate with other contractors involved to coordinate approved substitutions with remainder of the work.
1. The General Construction Contract shall coordinate substitutions.
C. Temporary Facilities and Controls: In addition to specific responsibilities for temporary facilities and controls indicated in this Section and in Section 015000 "Temporary Facilities and
Controls," each contractor is responsible for the following:
1. Installation, operation, maintenance, and removal of each temporary facility necessary for its own normal construction activity, and costs and use charges associated with each facility, except as otherwise provided for in this Section.
2. Plug-in electric power cords and extension cords, supplementary plug-in task lighting, and special lighting necessary exclusively for its own activities.
3. Its own field office, complete with necessary furniture, utilities, and telephone service.
4. Its own storage and fabrication sheds.
5. Temporary enclosures for its own construction activities.
6. Staging and scaffolding for its own construction activities.
7. General hoisting facilities for its own construction activities, up to 2 tons.
8. Waste disposal facilities, including collection and legal disposal of its own hazardous, dangerous, unsanitary, or other harmful waste materials.
9. Progress cleaning of work areas affected by its operations on a daily basis.
10. Secure lockup of its own tools, materials, and equipment.
11. Construction aids and miscellaneous services and facilities necessary exclusively for its own construction activities.
D. Use Charges: Comply with the following:
1. Sewer Service: Include the cost for sewer service use by all parties engaged in construction activities at Project site in the General Construction Contract.
2. Water Service: Include the cost for water service, whether metered or otherwise, for water used by all entities engaged in construction activities at Project site in the General
Construction Contract.
3. Electric Power Service: Include the cost for electric power service, whether metered or otherwise, for electricity used by all entities engaged in construction activities at Project site in the General Construction Contract.
1.7 GENERAL CONSTRUCTION CONTRACT
A. Work of the General Construction Contract includes, but is not limited to, the following:
1. Remaining work not identified as work under other contracts.
2. Selective demolition.
3. Slabs-on-grade, including earthwork, subdrainage systems, and insulation.
4. Superstructure, including floor and roof construction and sprayed fire-resistive materials.
5. Exterior closure, including walls, doors, windows, and louvers.
6. Interior construction, including partitions, doors, and fittings.
MULTIPLE CONTRACT SUMMARY 011200 - 5
7. Fire-protection specialties.
8. Interior finishes, and floor and ceiling finishes.
9. Miscellaneous items, including concrete equipment bases and painting of mechanical and electrical work.
B. Temporary facilities and controls in the General Construction Contract include, but are not limited to, the following:
1. Temporary facilities and controls that are not otherwise specifically assigned to the any other contracts.
2. Sediment and erosion control.
3. Stormwater control.
4. Unpiped temporary toilet fixtures, wash facilities, and drinking water facilities, including disposable supplies.
5. Special or unusual hoisting requirements for construction activities, including hoisting loads in excess of 2 tons, hoisting material or equipment into spaces below grade, and hoisting requirements outside building enclosure.
6. Project identification and temporary signs.
7. General waste disposal facilities.
8. Pest control.
9. Temporary stairs.
10. Temporary fire-protection facilities.
11. Barricades, warning signs, and lights.
12. Site enclosure fence.
13. Security enclosure and lockup.
14. Environmental protection.
15. Maintenance and restoration of Owner's existing facilities used as temporary facilities.
1.8 PLUMBING CONTRACT
A. Work of the Plumbing Contract includes, but is not limited to, the following:
1. Domestic water distribution.
2. Sanitary waste.
3. Stormwater drainage.
4. Fire-suppression systems.
5. Plumbing connections to equipment furnished by the HVAC Contract.
B. Temporary facilities and controls in the Plumbing Contract include, but are not limited to, the following:
1. Piped sewerage and drainage.
2. Piped water service.
3. Piped temporary toilet fixtures, wash facilities, and drinking water facilities.
1.9 HVAC CONTRACT
A. Work of the HVAC Contract includes, but is not limited to, the following:
MULTIPLE CONTRACT SUMMARY 011200 - 6
1. Site hydronic distribution.
2. Energy supply, including chilled-water supply systems.
3. HVAC systems and equipment.
4. HVAC instrumentation and controls.
5. HVAC testing, adjusting, and balancing.
6. Building automation system.
1.10 ELECTRICAL CONTRACT
A. Work of the Electrical Contract includes, but is not limited to, the following:
1. Site electrical distribution.
2. Electrical service and distribution.
3. Exterior and interior lighting.
4. Communication and security.
5. Special electrical systems, including the following:
a. Uninterruptible power supply systems.
b. Packaged engine generator systems.
c. Battery power systems.
6. Electrical connections to equipment furnished by the Electrical Contract.
B. Temporary facilities and controls in the Electrical Contract include, but are not limited to, the following:
1. Electric power service and distribution.
2. Lighting, including site lighting.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011200
ALLOWANCES 012100 - 1
SECTION 012100 - ALLOWANCES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
B. Types of allowances include the following:
1. Quantity allowances.
2. Testing and inspecting allowances.
C. Related Requirements:
1. Section 014000 "Quality Requirements" for procedures governing the use of allowances for field testing by an independent testing agency.
1.3 DEFINITIONS
A. Allowance is a quantity of work or dollar amount established in lieu of additional requirements, used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order.
1.4 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work.
B. At Architect's request, obtain proposals for each allowance for use in making final selections.
Include recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by Architect from the designated supplier.
1.5 ACTION SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.
ALLOWANCES 012100 - 2
1.6 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.7 QUANTITY ALLOWANCES
A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include freight, and delivery to Project site.
B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by
Owner or selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance.
C. Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted.
1. If requested by Architect, retain and prepare unused material for storage by Owner.
Deliver unused material to Owner's storage space as directed.
1.8 TESTING AND INSPECTING ALLOWANCES
A. Testing and inspecting allowances include the cost of engaging testing agencies, actual tests and inspections, and reporting results.
B. The allowance does not include incidental labor required to assist the testing agency or costs for retesting if previous tests and inspections result in failure. The cost for incidental labor to assist the testing agency shall be included in the Contract Sum.
C. Costs of testing and inspection services not required by the Contract Documents are not included in the allowance.
D. At Project closeout, credit unused amounts remaining in the testing and inspecting allowance to
Owner by Change Order.
1.9 ADJUSTMENT OF ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.
ALLOWANCES 012100 - 3
1. Include installation costs in purchase amount only where indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.
3. Submit substantiation of a change in scope of Work, if any, claimed in Change Orders related to unit-cost allowances.
4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.
1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.
2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. Allowance No. 1: Quantity Allowance: Include 100 sq. ft. of removal of deteriorated concrete and subsequent replacement and patching, and disposal of concrete off-site, as specified in
Section 030130 "Maintenance of Cast-In-Place Concrete."
B. Allowance No. 2: Quantity Allowance: Include 40 ft. of floor joint repair, as specified in
Section 030130 "Maintenance of Cast-In-Place Concrete.
C. Allowance No. 3: Quantity Allowance: Include 200 ft. for floor crack injection repair for concrete as specified in Section 030130 "Maintenance of Cast-In-Place Concrete."
ALLOWANCES 012100 - 4
D. Allowance No. 4: Quantity Allowance: Include 1300 sq. ft. for corrosion-inhibiting treatment of existing floor slab as specified in Section 030130 "Maintenance of Cast-In-Place Concrete."
E. Allowance No. 5: Quantity Allowance: Include 500 sq. ft. for polymer sealer application to existing traffic surfaces, as specified in Section 030130 "Maintenance of Cast-in-Place
Concrete."
F. Allowance No. 6: Testing and Inspection Allowance: Include the sum of $5,000.00 for testing and inspection to be provided by the Contractor as specified in Section 030130 "Maintenance of
Cast-in-Place Concrete."
END OF SECTION 012100
SUBSTITUTION PROCEDURES 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 012100 "Allowances" for products selected under an allowance.
2. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to
Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use facsimile of form provided in Project Manual.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
SUBSTITUTION PROCEDURES 012500 - 2
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section.
Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.
h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.
j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall
Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.
Architect will notify Contractor through Construction Manager of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or
Architect's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
SUBSTITUTION PROCEDURES 012500 - 3
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
1.7 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities
Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract
Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted.
e. Requested substitution will not adversely affect Contractor's construction schedule.
http://www.arcomnet.com/sustainable_design.aspx?topic=115 http://www.arcomnet.com/sustainable_design.aspx?topic=115 http://www.arcomnet.com/sustainable_design.aspx?topic=115 http://www.arcomnet.com/sustainable_design.aspx?topic=115
SUBSTITUTION PROCEDURES 012500 - 4
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work.
h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012500
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
C. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for preparing and submitting
Contractor's construction schedule.
2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
4. Section 019113 "General Commissioning Requirements" for coordinating the Work with
Owner's Commissioning Authority.
1.3 DEFINITIONS
A. BIM: Building Information Modeling.
B. RFI: Request for Information. Request from Owner, Construction Manager, Architect, or
Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office, in web-based
Project software directory, if applicable, and in prominent location in each built facility.
Keep list current at all times.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work.
Each contractor shall coordinate its own operations with operations included in different
Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their
Work is required.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and scheduled activities of other contractors to
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.6 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop
Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings.
Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade-specific information to coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, mechanical, and electrical systems.
d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
f. Indicate required installation sequences.
g. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.
Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans: Show architectural and structural elements, and mechanical, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid that are relevant to the Work. Supplement plan drawings with section drawings where required to adequately represent the Work.
PROJECT MANAGEMENT AND COORDINATION 013100 - 4
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within plenums to accommodate layout of light fixtures and other components indicated on Drawings.
Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems relevant to the Work.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations relevant to the Work.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor-control center locations relevant to the Work.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines,…