1204T019Q023-Solicitation_GeneralInstructionsClausesProvisions.pdf

PDF 689 KB Posted

Attached to
2019 Contracting West Road Maintenance BPA Federal contract opportunity
Solicitation number
1204T019Q0023
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

This solicitation notice seeks road maintenance services for multiple national forests across Oregon. The services include grading, spot surfacing, load hauling, rolling dips, drainage cleaning, and hourly equipment rentals. The government intends to award multiple firm fixed price blanket purchase agreements to provide adequate coverage for the geographical areas. Contractors may submit offers for any or all of 13 items corresponding to districts and forests. The solicitation will be available on May 3rd and estimated effective date is July 1, 2019. Prospective awardees must register in SAM to be eligible for award.

Solicitation Packet

View the file

Other files for this federal contract opportunity

Other files attached to 2019 Contracting West Road Maintenance BPA, newest first.
File Type Posted
1204T019Q0023-Amendment2.pdf PDF
1204T019Q0023-Amendment1.pdf PDF
Attachment001-ExperienceQuestionaire.pdf PDF
Attachment002-ServiceWageDetermination.pdf PDF
Attachment005b-UMP-RoadRules.pdf PDF
Attachment006a-RRS-Items8-10-SOW.pdf PDF
Attachment005a-UMP-Items5-7-SOW_SPECS.pdf PDF
Attachment006c-RRS-Item9-SPECS.pdf PDF
Attachment007-FW-Items11-13-SOW_SPECS.pdf PDF
Attachment004-WIL-Items2-4-SOW_SPECS.pdf PDF
Attachment006d-RRS-Item10-SPECS.pdf PDF
Attachment003-SIU-Item1-SOW_SPECS.pdf PDF
Attachment006b-RRS-Item8-SPECS.pdf PDF
1204T019Q023-ReturnPacket.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NO. 3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE

DATE

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME b. TELEPHONE NUMBER (No collect calls)

8. OFFER DUE DATE/

LOCAL TIME

9. ISSUED BY

13b. RATING

14. METHOD OF SOLICITATION

CODE

15. DELIVER TO 16. ADMINISTERED BY CODE

18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/

OFFEROR

CODE

FACILITY

CODE

CODE

TELEPHONE NO.

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED

RFQ IFB RFP

SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

29. AWARD OF CONTRACT: REF. OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

10. THIS ACQUISITION IS UNRESTRICTED OR

NAICS:

SIZE STANDARD:

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

SET ASIDE: % FOR:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

8 (A)

EDWOSB

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SMALL BUSINESS

N/A SF1449: 1 of 32

1204T019Q0023

JANET PAUL, CONTRACTING OFFICER 541.750.7120

SEE BLOCK 9

2019 CONTRACTING WEST ROAD MAINTENANCE

BLANKET PURCHASE AGREEMENT (BPA)

Submit your completed Return Packet to the address in Block 9. If mailing, please identify the Solicitation Number:

1204T019Q0023 and due date on the envelope.

Continued on next page:

JANET PAUL

115310

$7.5M

05/13/2019

06/13/2019

4:00 PM PST

SIUSLAW NATIONAL FOREST

ATTN: JANET PAUL

3200 SW JEFFERSON WAY

CORVALLIS, OR 97331

(FAX: 541.750.7236)

STANDARD FORM 1449 (REV. 2/2012) BACK

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

40. PAID BY

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED

CORRECT FOR

PARTIAL FINAL

37. CHECK NUMBER

38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER

36. PAYMENT

COMPLETE PARTIAL FINAL

Note: Prospective contractors may bid on any or all of the individual 13 Bid Items, however, within each individual bid item, you must provide a Firm-Fixed Unit Price for ALL payable sub-items within that item. Unit prices shown on the individual Schedule of Items are effective and fixed from the date of award through June 30, 2020 (Base Year). Your identified annual price adjustment percentage will be applied for each subsequent Option Year, at the rate you identify herein.

Enter your unit prices on the following pages 3 - 31 of the SF-1449 Continuation Sheets (per your applicable

Bid Items as described above).

Enter your annual price adjustment percentage (%) on page 32 of the SF-1449 Continuation Sheets.

See "Response to Blanket Purchase Agreement (Request for Quotations)" for further submittal requirements.

The Government anticipates awarding 1, 2 or 3 awards per item (total number of awards to be determined).

Prospective awardees MUST be registered in the System for Award Management (SAM). If you are not, please register at the following website:

https://www.sam.gov/portal/public/SAM/

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

807(1) Equipment Rental, Excavator 1 Hour

807(2) Equipment Rental, Backhoe 1 Hour

807(3) Equipment Rental, Grader 1 Hour

807(4) Equipment Rental, Dump Truck 1 Hour

807(5) Equipment Rental, Brush Cutter 1 Hour

807(6) Equipment Rental, Roller 1 Hour

807(7) Equipment Rental, Dozer 1 Hour

811(1) Surface Maintenance: Single Lane Roads 10 MI

811(2) Surface Maintenance: Double Lane Roads 10 MI

811(3) Roller Compaction: Single Lane Roads 10 MI

811(4) Roller Compaction: Double Lane Roads 10 MI

811(5) Shoulder Maintenance: Paved Roads 10 MI

811-F1(1) Surface Maintenance:

Single Lane Sand Roads

10 MI

811-F1(2) Surface Maintenance:

Double Lane Sand Roads

10 MI

813(1) Spot Surfacing, Government Source 100 CY

813(2) Spot Surfacing, Commercial Source 100 CY

814(1) Paved Surface Cleaning: Single Lane 10 MI

814(2) Paved Surface Cleaning: Double Lane 10 MI

814-F1(1) Pothole Patching NA Ton

PER ORDER PER ORDER

814-F1(2) Skin Patching NA Ton

PER ORDER PER ORDER

832(1) Load, Haul and Place Material (Slide 5-20 CY) 1 LS

832(2) Load, Haul and Place Material (Slide 21-50 CY) 1 LS

832(3) Load, Haul and Place Material (Slide 51-100 CY) 1 LS

CONTINUATION OF 1449 SCHEDULE

SIUSLAW NATIONAL FOREST: CENTRAL COAST AND HEBO RANGER DISTRICTS (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

1 SIUSLAW NATIONAL FOREST: CENTRAL COAST AND HEBO RANGER DISTRICTS (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

834(1) Clean Ditches 10 MI

834(2) Clean Ditches and Drainage Structures 10 MI

842(1) Cutting Roadway Vegetation (10 feet from edge of roadway)

10 MI

842A(1) Cutting Roadway Vegetation (5 feet from edge of roadway)

10 MI

851(1) Logging Out 10 MI

851(2) Logging Out (Trees 10" to 24" in diameter) 10 EA

851(3) Logging Out (Trees > 24" in diameter) 10 EA

851(4) Hazard or Obstruction Removal 10 EA

861(1) Maintain Traffic Gate 1 EA

861(2) Install or Maintain Rock/Earth Barrier 10 EA

872(1) Install or Replace Single Post and Sign, Government Furnished

10 EA

872(2) Install or Replace Double Post and Sign, Government Furnished

10 EA

872(3) Install or Replace Sign, Government Furnished 10 EA

891(1) Water Supply and Watering 10 Mgal

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Central Coast and Hebo Ranger Districts

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Central Coast and Hebo Ranger Districts

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Central Coast and Hebo Ranger Districts

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Central Coast and Hebo Ranger Districts

ALL LS

BPA Call Subtotal + Applicable Mobilization Rate:

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

BPA Call Subtotal:

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

807(1) Equipment Rental, Excavator 5 Hour

807(2) Equipment Rental, Backhoe 100 Hour

807(3) Equipment Rental, Dozer 5 Hour

807(4) Equipment Rental, Grader 5 Hour

807(5) Equipment Rental, Compactor 3 Hour

807(6) Equipment Rental, Dump Truck 100 Hour

808(1) Single Flagger Operation 1 Hour

808(2) Dual Flagger Operation 1 Hour

811(1) Surface Maintenance Level 2 Roads 10 MI

811(2) Surface Maintenance Level 2 Roads with Roller Compaction

10 MI

811(3) Surface Maintenance Level 3 & 4 Roads with Roller Compaction

10 MI

813(1) Spot Surfacing, Gradation _____ 100 CY

813(2) Spot Surfacing, Gradation _____ 100 Ton

813(3) Government Furnished Spot Surfacing, Less Than 10 Miles One Way Haul

100 CY

813(4) Government Furnished Spot Surfacing, 10 - 20 Miles One Way Haul

100 CY

814(1) Pothole Patching NA Ton

PER ORDER PER ORDER

814(2) Skin Patching NA Ton

PER ORDER PER ORDER

832(1) Load, Haul, and Place Materials, Less Than 5 Miles One Way Haul

100 CY

832(2) Load, Haul, and Place Materials, 5 - 10 Miles One Way Haul

100 CY

833(1) Culvert Removal 10 EA

833(2) Water-bar Installation 10 EA

833(3) Rolling Dip Installation 10 EA

834(1) Clean and Recondition Culverts 10 MI

834(2) Clean and Recondition Culverts 10 EA

834(3) Clean Ditches 10 MI

CONTINUATION OF 1449 SCHEDULE

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

WILLAMETTE NATIONAL FOREST - SANTIAM RIVER ZONE (2 pages)

(DETROIT AND SWEET HOME RANGER DISTRICTS)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

WILLAMETTE NATIONAL FOREST - SANTIAM RIVER ZONE (2 pages)

(DETROIT AND SWEET HOME RANGER DISTRICTS)

834(4) General Road Maintenance All LS

PER ORDER PER ORDER

841(1) Hay Bail 10 EA

842(1) Vegetation Maintenance Level 2 Roads 10 MI

842(2) Vegetation Maintenance Level 3-5 Roads 10 MI

851(1) Logging Out Maintenance Level 2 Roads 10 MI

851(2) Logging Out Maintenance Level 3-5 Roads 10 MI

851(3) Danger Tree Removal 10 EA

851(4) Minimal Hazard or Obstruction Removal 10 EA

851(5) Moderate Hazard or Obstruction Removal 10 EA

861(1) Guardrail Replacement 10 LF

861(2) Guardrail Post Replacement 10 EA

861(3) Steel End Section Component and Fastener Replacement

10 EA

872(1) Install or Replace Sign 10 EA

881(5) Additional Equipment Washing 1 EA

881(6) Equipment Moving 10 MI

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Santiam River Zone

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Santiam River Zone

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Santiam River Zone

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Santiam River Zone

ALL LS

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

BPA Call Subtotal + Applicable Mobilization Rate:

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

807(1) Equipment Rental, Excavator 1 Hour

807(2) Equipment Rental, Backhoe 1 Hour

807(3) Equipment Rental, Dozer 1 Hour

807(4) Equipment Rental, Grader 1 Hour

807(5) Equipment Rental, Compactor 1 Hour

807(6) Equipment Rental, Dump Truck 1 Hour

808(1) Single Flagger Operation 1 Hour

808(2) Dual Flagger Operation 1 Hour

811(1) Surface Maintenance Level 2 Roads 10 MI

811(2) Surface Maintenance Level 2 Roads with Roller Compaction

10 MI

811(3) Surface Maintenance Level 3 & 4 Roads with Roller Compaction

10 MI

813(1) Spot Surfacing, Gradation _____ 100 CY

813(2) Spot Surfacing, Gradation _____ 100 Ton

813(3) Government Furnished Spot Surfacing, Less Than 10 Miles One Way Haul

100 CY

813(4) Government Furnished Spot Surfacing, 10 - 20 Miles One Way Haul

100 CY

814(1) Pothole Patching NA Ton

PER ORDER PER ORDER

814(2) Skin Patching NA Ton

PER ORDER PER ORDER

832(1) Load, Haul, and Place Materials, Less Than 5 Miles One Way Haul

100 CY

832(2) Load, Haul, and Place Materials, 5 - 10 Miles One Way Haul

100 CY

833(1) Culvert Removal 10 EA

833(2) Water-bar Installation 10 EA

833(3) Rolling Dip Installation 10 EA

834(1) Clean and Recondition Culverts 10 MI

834(2) Clean and Recondition Culverts 10 EA

834(3) Clean Ditches 10 MI

CONTINUATION OF 1449 SCHEDULE

WILLAMETTE NATIONAL FOREST - MCKENZIE RIVER RANGER DISTRICT (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

3 WILLAMETTE NATIONAL FOREST - MCKENZIE RIVER RANGER DISTRICT (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

834(4) General Road Maintenance All LS

PER ORDER PER ORDER

841(1) Hay Bail 10 EA

842(1) Vegetation Maintenance Level 2 Roads 10 MI

842(2) Vegetation Maintenance Level 3-5 Roads 10 MI

851(1) Logging Out Maintenance Level 2 Roads 10 MI

851(2) Logging Out Maintenance Level 3-5 Roads 10 MI

851(3) Danger Tree Removal 10 EA

851(4) Minimal Hazard or Obstruction Removal 10 EA

851(5) Moderate Hazard or Obstruction Removal 10 EA

861(1) Guardrail Replacement 10 LF

861(2) Guardrail Post Replacement 10 EA

861(3) Steel End Section Component and Fastener Replacement

10 EA

872(1) Install or Replace Sign 10 EA

881(5) Additional Equipment Washing 1 EA

881(6) Equipment Moving 10 MI

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 McKenzie River Ranger District

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 McKenzie River Ranger District

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 McKenzie River Ranger District

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 McKenzie River Ranger District

ALL LS

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

807(1) Equipment Rental, Excavator 1 Hour

807(2) Equipment Rental, Backhoe 1 Hour

807(3) Equipment Rental, Dozer 1 Hour

807(4) Equipment Rental, Grader 1 Hour

807(5) Equipment Rental, Compactor 1 Hour

807(6) Equipment Rental, Dump Truck 1 Hour

808(1) Single Flagger Operation 1 Hour

808(2) Dual Flagger Operation 1 Hour

811(1) Surface Maintenance Level 2 Roads 10 MI

811(2) Surface Maintenance Level 2 Roads with Roller Compaction

10 MI

811(3) Surface Maintenance Level 3 & 4 Roads with Roller Compaction

10 MI

813(1) Spot Surfacing, Gradation _____ 100 CY

813(2) Spot Surfacing, Gradation _____ 100 Ton

813(3) Government Furnished Spot Surfacing, Less Than 10 Miles One Way Haul

100 CY

813(4) Government Furnished Spot Surfacing, 10 - 20 Miles One Way Haul

100 CY

814(1) Pothole Patching NA Ton PER ORDER PER ORDER

814(2) Skin Patching NA Ton PER ORDER PER ORDER

832(1) Load, Haul, and Place Materials, Less Than 5 Miles One Way Haul

100 CY

832(2) Load, Haul, and Place Materials, 5 - 10 Miles One Way Haul

100 CY

833(1) Culvert Removal 10 EA

833(2) Water-bar Installation 10 EA

833(3) Rolling Dip Installation 10 EA

834(1) Clean and Recondition Culverts 10 MI

834(2) Clean and Recondition Culverts 10 EA

834(3) Clean Ditches 10 MI

834(4) General Road Maintenance All LS PER ORDER PER ORDER

CONTINUATION OF 1449 SCHEDULE

WILLAMETTE NATIONAL FOREST - MIDDLE FORK RANGER DISTRICT (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

4 WILLAMETTE NATIONAL FOREST - MIDDLE FORK RANGER DISTRICT (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

841(1) Hay Bail 10 EA

842(1) Vegetation Maintenance Level 2 Roads 10 MI

842(2) Vegetation Maintenance Level 3-5 Roads 10 MI

851(1) Logging Out Maintenance Level 2 Roads 10 MI

851(2) Logging Out Maintenance Level 3-5 Roads 10 MI

851(3) Danger Tree Removal 10 EA

851(4) Minimal Hazard or Obstruction Removal 10 EA

851(5) Moderate Hazard or Obstruction Removal 10 EA

861(1) Guardrail Replacement 10 LF

861(2) Guardrail Post Replacement 10 EA

861(3) Steel End Section Component and Fastener Replacement

10 EA

872(1) Install or Replace Sign 10 EA

881(5) Additional Equipment Washing 1 EA

881(6) Equipment Moving 10 MI

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Middle Fork Ranger District

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Middle Fork Ranger District

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Middle Fork Ranger District

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Middle Fork Ranger District

ALL LS

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

803(1) Snow Removal (Single Lane) 5.0 MI

807(1) Equipment Rental, Excavator 1.0 Hour

807(2) Equipment Rental, Backhoe 1.0 Hour

807(3) Equipment Rental, Grader 1.0 Hour

807(4) Equipment Rental, Dump Truck 1.0 Hour

807(5) Equipment Rental, Brush Cutter 1.0 Hour

807(6) Equipment Rental, Roller 1.0 Hour

807(7) Equipment Rental, Dozer 1.0 Hour

808(1) Single Flagger Operation 1.0 Hour

808(2) Dual Flagger Operation 1.0 Hour

811(1) Surface Maintenance: Single Lane Roads, Scarification Not Required.

1.0 MI

811(2) Surface Maintenance: Single Lane Roads, Scarification Required.

1.0 MI

811(3) Surface Maintenance: Double Lane Roads, Scarification Not Required.

1.0 MI

811(4) Surface Maintenance: Double Lane Roads, Scarification Required.

1.0 MI

811(5) Roller Compaction: Single Lane Roads 1.0 MI

811(6) Roller Compaction: Double Lane Roads 1.0 MI

811(7) Shoulder Maintenance: Paved Roads 1.00 MI

814(1) Pothole Patching NA Ton

PER ORDER PER ORDER

814(2) Skin Patching NA Ton

PER ORDER PER ORDER

832(1) Load, Haul, and Place Material 1 CY-MI

833(1) Culvert Removal 10 EA

833(4) Construct Water-bar 1 EA

833(5) Construct Cross Ditch 1 EA

834(1) Clean and Recondition Culverts: 24-inch Diameter and Under

1 EA

CONTINUATION OF 1449 SCHEDULE

UMPQUA NATIONAL FOREST - COTTAGE GROVE RANGER DISTRICT (3 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

5 UMPQUA NATIONAL FOREST - COTTAGE GROVE RANGER DISTRICT (3 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

834(2) Clean and Recondition Culverts: Over 24-inch Diameter through 48-inch Diameter

1 EA

834(3) Clean and Recondition Culverts: Over 48-inch Diameter

1 EA

834(4) Clean Ditches 1.00 MI

834(5) Clean Ditches and Drainage Structures 1.0 MI

834(6) General Road Maintenance All LS

PER ORDER PER ORDER

841(1) Mulching, Straw, Government Furnished 1 SQ.YD

841(2) Seeding, Grass, Government Furnished 1 SQ.YD

841(3) Straw Bale Ditch line Filters, Government Furnished

1 EA

842(1) Cutting Roadway Vegetation Low Volume Vegetation, Slash Reduction Not Required

1.0 MI

842(2) Cutting Roadway Vegetation Low Volume Vegetation, Slash Reduction Required

1.0 MI

842(3) Cutting Roadway Vegetation High Volume Vegetation, Slash Reduction Not Required

1.0 MI

842(4) Cutting Roadway Vegetation High Volume Vegetation, Slash Reduction Required

1.0 MI

851(1) Logging Out: Primary and Secondary Roads 1.0 MI

851(2) Logging Out: Other Roads 1.0 MI

851(3) Hazard or Obstruction Removal 1 EA

861(2) Maintain Traffic Gate 1 EA

861(6) Install or Maintain Rock/Earth Barrier 1 EA

872(3) Install or Replace Single Post and Sign, Government Furnished

1 EA

872(4) Install or Replace Double Post and Sign, Government Furnished

1 EA

872(5) Install or Replace Sign, Government Furnished

1 EA

872(9) Maintain Marker 1 EA

872(10) Replace Marker 1 EA

881(5) Equipment Moving 1.0 MI

891(1) Water Supply and Watering 1 MGAL

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

5 UMPQUA NATIONAL FOREST - COTTAGE GROVE RANGER DISTRICT (3 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Cottage Grove Ranger District

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Cottage Grove Ranger District

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Cottage Grove Ranger District

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Cottage Grove Ranger District

ALL LS

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

803(1) Snow Removal (Single Lane) 5.0 MI

807(1) Equipment Rental, Excavator 1.0 Hour

807(2) Equipment Rental, Backhoe 1.0 Hour

807(3) Equipment Rental, Grader 1.0 Hour

807(4) Equipment Rental, Dump Truck 1.0 Hour

807(5) Equipment Rental, Brush Cutter 1.0 Hour

807(6) Equipment Rental, Roller 1.0 Hour

807(7) Equipment Rental, Dozer 1.0 Hour

808(1) Single Flagger Operation 1.0 Hour

808(2) Dual Flagger Operation 1.0 Hour

811(1) Surface Maintenance: Single Lane Roads, Scarification Not Required.

1.0 MI

811(2) Surface Maintenance: Single Lane Roads, Scarification Required.

1.0 MI

811(3) Surface Maintenance: Double Lane Roads, Scarification Not Required.

1.0 MI

811(4) Surface Maintenance: Double Lane Roads, Scarification Required.

1.0 MI

811(5) Roller Compaction: Single Lane Roads 1.0 MI

811(6) Roller Compaction: Double Lane Roads 1.0 MI

811(7) Shoulder Maintenance: Paved Roads 1.00 MI

814(1) Pothole Patching NA Ton

PER ORDER PER ORDER

814(2) Skin Patching NA Ton

PER ORDER PER ORDER

832(1) Load, Haul, and Place Material 1 CY-MI

833(1) Culvert Removal 10 EA

833(4) Construct Water-bar 1 EA

833(5) Construct Cross Ditch 1 EA

834(1) Clean and Recondition Culverts: 24-inch Diameter and Under

1 EA

834(2) Clean and Recondition Culverts: Over 24-inch Diameter through 48-inch Diameter

1 EA

CONTINUATION OF 1449 SCHEDULE

UMPQUA NATIONAL FOREST -

DIAMOND LAKE AND NORTH UMPQUA RANGER DISTRICTS (3 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

UMPQUA NATIONAL FOREST -

DIAMOND LAKE AND NORTH UMPQUA RANGER DISTRICTS (3 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

834(3) Clean and Recondition Culverts: Over 48-inch Diameter

1 EA

834(4) Clean Ditches 1.00 MI

834(5) Clean Ditches and Drainage Structures 1.0 MI

834(6) General Road Maintenance All LS

PER ORDER PER ORDER

841(1) Mulching, Straw, Government Furnished 1 SQ.YD

841(2) Seeding, Grass, Government Furnished 1 SQ.YD

841(3) Straw Bale Ditch line Filters, Government Furnished

1 EA

842(1) Cutting Roadway Vegetation Low Volume Vegetation, Slash Reduction Not Required

1.0 MI

842(2) Cutting Roadway Vegetation Low Volume Vegetation, Slash Reduction Required

1.0 MI

842(3) Cutting Roadway Vegetation High Volume Vegetation, Slash Reduction Not Required

1.0 MI

842(4) Cutting Roadway Vegetation High Volume Vegetation, Slash Reduction Required

1.0 MI

851(1) Logging Out: Primary and Secondary Roads 1.0 MI

851(2) Logging Out: Other Roads 1.0 MI

851(3) Hazard or Obstruction Removal 1 EA

861(2) Maintain Traffic Gate 1 EA

861(6) Install or Maintain Rock/Earth Barrier 1 EA

872(3) Install or Replace Single Post and Sign, Government Furnished

1 EA

872(4) Install or Replace Double Post and Sign, Government Furnished

1 EA

872(5) Install or Replace Sign, Government Furnished

1 EA

872(9) Maintain Marker 1 EA

872(10) Replace Marker 1 EA

881(5) Equipment Moving 1.0 MI

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

UMPQUA NATIONAL FOREST -

DIAMOND LAKE AND NORTH UMPQUA RANGER DISTRICTS (3 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Diamond Lake and North Umpqua RD's

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Diamond Lake and North Umpqua RD's

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Diamond Lake and North Umpqua RD's

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Diamond Lake and North Umpqua RD's

ALL LS

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

803(1) Snow Removal (Single Lane) 5.0 MI

807(1) Equipment Rental, Excavator 1.0 Hour

807(2) Equipment Rental, Backhoe 1.0 Hour

807(3) Equipment Rental, Grader 1.0 Hour

807(4) Equipment Rental, Dump Truck 1.0 Hour

807(5) Equipment Rental, Brush Cutter 1.0 Hour

807(6) Equipment Rental, Roller 1.0 Hour

807(7) Equipment Rental, Dozer 1.0 Hour

808(1) Single Flagger Operation 1.0 Hour

808(2) Dual Flagger Operation 1.0 Hour

811(1) Surface Maintenance: Single Lane Roads, Scarification Not Required.

1.0 MI

811(2) Surface Maintenance: Single Lane Roads, Scarification Required.

1.0 MI

811(3) Surface Maintenance: Double Lane Roads, Scarification Not Required.

1.0 MI

811(4) Surface Maintenance: Double Lane Roads, Scarification Required.

1.0 MI

811(5) Roller Compaction: Single Lane Roads 1.0 MI

811(6) Roller Compaction: Double Lane Roads 1.0 MI

811(7) Shoulder Maintenance: Paved Roads 1.00 MI

814(1) Pothole Patching NA Ton

PER ORDER PER ORDER

814(2) Skin Patching NA Ton

PER ORDER PER ORDER

832(1) Load, Haul, and Place Material 1 CY-MI

833(1) Culvert Removal 10 EA

833(4) Construct Water-bar 1 EA

833(5) Construct Cross Ditch 1 EA

834(1) Clean and Recondition Culverts: 24-inch Diameter and Under

1 EA

834(2) Clean and Recondition Culverts: Over 24-inch Diameter through 48-inch Diameter

1 EA

CONTINUATION OF 1449 SCHEDULE

UMPQUA NATIONAL FOREST - TILLER RANGER DISTRICT (3 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

7 UMPQUA NATIONAL FOREST - TILLER RANGER DISTRICT (3 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

834(3) Clean and Recondition Culverts: Over 48-inch Diameter

1 EA

834(4) Clean Ditches 1.00 MI

834(5) Clean Ditches and Drainage Structures 1.0 MI

834(6) General Road Maintenance All LS

PER ORDER PER ORDER

841(1) Mulching, Straw, Government Furnished 1 SQ.YD

841(2) Seeding, Grass, Government Furnished 1 SQ.YD

841(3) Straw Bale Ditch line Filters, Government Furnished

1 EA

842(1) Cutting Roadway Vegetation Low Volume Vegetation, Slash Reduction Not Required

1.0 MI

842(2) Cutting Roadway Vegetation Low Volume Vegetation, Slash Reduction Required

1.0 MI

842(3) Cutting Roadway Vegetation High Volume Vegetation, Slash Reduction Not Required

1.0 MI

842(4) Cutting Roadway Vegetation High Volume Vegetation, Slash Reduction Required

1.0 MI

851(1) Logging Out: Primary and Secondary Roads 1.0 MI

851(2) Logging Out: Other Roads 1.0 MI

851(3) Hazard or Obstruction Removal 1 EA

861(1) Maintain one lane Cattleguard 1 EA

861(2) Maintain Traffic Gate 1 EA

861(6) Install or Maintain Rock/Earth Barrier 1 EA

872(3) Install or Replace Single Post and Sign, Government Furnished

1 EA

872(4) Install or Replace Double Post and Sign, Government Furnished

1 EA

872(8) Apply New Sign Face, Government Furnished

1 EA

872(9) Maintain Marker 1 EA

872(10) Replace Marker 1 EA

881(5) Equipment Moving 1.0 MI

2019 BPA Call Subtotal Line Item 7:

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

7 UMPQUA NATIONAL FOREST - TILLER RANGER DISTRICT (3 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Tiller Ranger District

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Tiller Ranger District

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Tiller Ranger District

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Tiller Ranger District

ALL LS

BPA Call Subtotal + Applicable Mobilization:

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23. UNIT

PRICE

24.

TOTAL

AMOUNT

640(1) Earthern Berm Repair 4 EA

807(1) Equipment Rental – Backhoe 12 Hour

807(2) Equipment Rental – Crawler Dozer 5 Hour

807(3) Equipment Rental - Dump Truck 12 Hour

811(1) Surface Maintenance Level Single Lane 20 CLRM

811(2) Surface Maintenance Level Double Lane 5 CLRM

811(3) Surface Maintenance Level Single Lane with Roller Compaction

35 CLRM

811(4) Surface Maintenance Level Double Lane with Roller Compaction

5 CLRM

813(1) Spot Surfacing, Gradation (Government Furnished Material) less than 10 miles one

1000 CY

813(2) Spot Surfacing, Gradation (Government Furnished Material) 10 - 20 miles one way

50 CY

814(1) Asphalt Surface Maintenance Pothole Patching

25 Ton

832(1) Load, Haul, and Place Material less than 10 miles one way haul

2,000 CY

832(2) Load, Haul, and Place Material 10 - 20 miles one way haul

50 CY

833(1) Culvert Replacement 60 FT

833(2) Culvert Removal 2 EA

833(3) Water-bar Installation 20 EA

833(7) Drivable Cross Ditch Installation 25 EA

834(1) Clean and Recondition Culverts 10 MI

834(2) Clean and Recondition Culverts 250 EA

834(4) Clean Ditches 35 MI

842(1) Vegetation Maintenance 70 MI

CONTINUATION OF 1449 SCHEDULE

ROGUE RIVER-SISKIYOU NF (East1) - HIGH CASCADES RANGER DISTRICT (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23. UNIT

PRICE

24.

TOTAL

AMOUNT

8 ROGUE RIVER-SISKIYOU NF (East1) - HIGH CASCADES RANGER DISTRICT (2 pages)

851(1) Logging out (ML 3-5) 20 MI

851(2) Logging out (ML 2) 15 MI

851(4) Danger Tree Removal 10 EA

851(6) Hazard or Obstruction Removal 13 EA

861(1) Maintain one- lane cattle guard 2 EA

881(5) Equipment Moving 20 MI

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000

ALL LS

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT

Price

24.

TOTAL

AMOUNT

640(1) Earthen Berm Repair 4 EA $

807(1) Equipment Rental – Backhoe 12 Hour $

807(2) Equipment Rental – Crawler Dozer 5 Hour $

807(3) Equipment Rental - Dump Truck 12 Hour $

811(1) Surface Maintenance Level Single Lane 20 CLRM $

811(2) Surface Maintenance Level Double Lane 5 CLRM $

811(3) Surface Maintenance Level Single Lane with Roller Compaction

35 CLRM $

811(4) Surface Maintenance Level Double Lane with Roller Compaction

5 CLRM $

813(1) Spot Surfacing, Gradation(Government Furnished Material) less than 10 miles one

1,000 CY $

813(2) Spot Surfacing, Gradation(Government Furnished Material) 10 - 20 miles one way

50 CY $

814(1) Asphalt Surface Maintenance Pothole Patching

25 Ton $

832(1) Load, Haul, and Place Material less than 10 miles one way haul

7,000 CY $

832(2) Load, Haul, and Place Material 10 - 20 miles one way haul

50 CY $

833(1) Culvert Replacement 60 FT $

833(2) Culvert Removal 2 EA $

833(3) Water-bar Installation 20 EA $

833(7) Drivable Cross Ditch Installation 30 EA $

834(1) Clean and Recondition Culverts 10 MI $

834(2) Clean and Recondition Culverts 250 EA $

834(4) Clean Ditches 35 MI $

842(1) Vegetation Maintenance 50 MI $

851(1) Logging out (ML 3-5) 20 MI $

851(2) Logging out (ML 2) 15 MI $

CONTINUATION OF 1449 SCHEDULE

ROGUE RIVER-SISKIYOU NF (East2) - SISKIYOU MOUNTAINS AND WILD RIVERS RANGER DISTRICTS (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT

Price

24.

TOTAL

AMOUNT

640(1) Earthen Berm Repair 4 EA $

ROGUE RIVER-SISKIYOU NF (East2) - SISKIYOU MOUNTAINS AND WILD RIVERS RANGER DISTRICTS (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

851(4) Danger Tree Removal 10 EA $

851(6) Hazard or Obstruction Removal 13 EA $

861(1) Maintain one- lane cattle guard 2 EA $

881(5) Equipment Moving 200 MI

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000

ALL LS

BPA Call Subtotal + Applicable Mobilization Rate:

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

640(1) Earthern Berm Repair 5 EA

807(1) Equipment Rental, Excavator 40 Hour

807(2) Equipment Rental, Backhoe 30 Hour

811(1) Surface Maintenance: Single Lane Roads, Scarification Not Required.

50 MI

811(2) Surface Maintenance: Single Lane Roads, Scarification Required.

30 MI

811(3) Surface Maintenance: Double Lane Roads, Scarification Not Required.

10 MI

811(4) Surface Maintenance: Double Lane Roads, Scarification Required.

10 MI

811(5) Roller Compaction: Single Lane Roads 30 MI

811(6) Roller Compaction: Double Lane Roads 10 MI

811(7) Shoulder Maintenance: Paved Roads 10 MI

813(1) Spot Surfacing, gradation (government furnished material), less than 10 miles haul

200 CY

814(2) Asphalt Surface Maintenance, Hot mix for skin patches

20 Ton PER ORDER PER ORDER

814(8) Asphalt Surface Maintenance, cold mix for pothole patching

100 SF PER ORDER PER ORDER

832(1) Load, Haul, and Place Material 1000 CY

832(4) Haul 2000 CY-MI

833(2) Remove Culvert 5 EA

833(4) Construct Water-bar 40 EA

833(5) Construct Cross Ditch 10 EA

834(1) Clean and Recondition Culverts: 24-inch Diameter and Under

100 EA

834(2) Clean and Recondition Culverts: Over 24-inch Diameter through 48-inch Diameter

100 EA

834(3) Clean and Recondition Culverts: Over 48-inch Diameter

20 EA

834(4) Clean Ditches 40 MI

834(5) Clean Ditches and Drainage Structures 20 MI

CONTINUATION OF 1449 SCHEDULE

ROGUE RIVER-SISKIYOU NF (West) - POWERS AND GOLD BEACH RANGER DISTRICTS (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY/

YEAR

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

ROGUE RIVER-SISKIYOU NF (West) -

POWERS AND GOLD BEACH RANGER DISTRICTS (2 pages)

834(6) Clean Drainage Structures 30 MI

841(1) Mulching, Straw, Government Furnished 40 SQ.YD

841(2) Seeding, Grass, Government Furnished 40 SQ.YD

841(3) Hay Bale 25 EA

842(1) Vegetation Maintenance 75 MI

851(1) Logging Out: (ML 3-5) 50 MI

851(3) Hazard or Obstruction Removal 100 EA

851(4) Treatment and Disposal of Danger Trees 50 EA

861(6) Maintain Guardrail 5 LF

872(3) Install or Replace Single Post and Sign, Government Furnished

40 EA

872(4) Install or Replace Double Post and Sign, Government Furnished

5 EA

872(5) Install or Replace Sign, Government Furnished

30 EA

881(5) Equipment Moving 200 MI

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000

ALL LS

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

807(1) Equipment Rental, Excavator 10 HR

807(2) Equipment Rental, Backhoe 10 HR

807(3) Equipment Rental, Grader 10 HR

807(4) Equipment Rental, Dump Truck 10 HR

808(1) Single Flagger Operation 5 HR

808(2) Dual Flagger Operation 5 HR

811(1) Surface Maintenance Single Lane 175 CLRM

811(2) Surface Maintenance Double Lane 56 CLRM

811(3) Surface Maintenance Single Lane with Roller Compaction

50 CLRM

811(4) Surface Maintenance Double Lane with Roller Compaction

15 CLRM

813(1) Spot Surfacing, Gradation (Government Furnished Material) less than 10 miles one way haul

20 CY

813(2) Spot Surfacing, Gradation (Government Furnished Material) 10 - 20 miles one way haul

30 CY

832(1) Load, Haul and Place Material (Less than 10 miles one way haul)

100 CY

832(2) Load, Haul and Place Material (10 - 20 miles one way haul)

100 CY

834(1) Clean and Recondition Culverts 20 EA

834(2) Clean Ditches and Drainage Structures 300 MI

834(3) General Road Maintenance All LS Per Order Per Order

842(1) Vegetation Maintenance 150 MI

CONTINUATION OF 1449 SCHEDULE

FREMONT-WINEMA NATIONAL FOREST, EAST -

BLY and LAKEVIEW RANGER DISTRICTS (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

FREMONT-WINEMA NATIONAL FOREST, EAST -

BLY and LAKEVIEW RANGER DISTRICTS (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

851(1) Logging Out ML 3-5 Roads 20 MI

851(4) Danger Tree Removal 15 EA

851(6) Hazard or Obstruction Removal 10 EA

861(1) Maintain one- lane cattle guard 4 EA

872(1) Install or Replace Single Post and Sign, Government Furnished

20 EA

872(2) Install or Replace Double Post and Sign, Government Furnished

20 EA

872(3) Install or Replace Sign, Government Furnished

20 EA

881(5) Equipment Moving 40 MI

T-891-02F Water Supply and Watering 500 MGAL

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Bly and Lakeview Ranger Districts

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Bly and Lakeview Ranger Districts

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Bly and Lakeview Ranger Districts

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Bly and Lakeview Ranger Districts

ALL LS

BPA Call Subtotal + Applicable Mobilization Rate:

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

807(1) Equipment Rental, Excavator 10 HR

807(2) Equipment Rental, Backhoe 10 HR

807(3) Equipment Rental, Grader 10 HR

807(4) Equipment Rental, Dump Truck 10 HR

808(1) Single Flagger Operation 5 HR

808(2) Dual Flagger Operation 5 HR

811(1) Surface Maintenance Single Lane 175 CLRM

811(2) Surface Maintenance Double Lane 56 CLRM

811(3) Surface Maintenance Single Lane with Roller Compaction

50 CLRM

811(4) Surface Maintenance Double Lane with Roller Compaction

15 CLRM

813(1) Spot Surfacing, Gradation (Government Furnished Material) less than 10 miles one way haul

20 CY

813(2) Spot Surfacing, Gradation (Government Furnished Material) 10 - 20 miles one way haul

30 CY

832(1) Load, Haul and Place Material (Less than 10 miles one way haul)

100 CY

832(2) Load, Haul and Place Material (10 - 20 miles one way haul)

100 CY

834(1) Clean and Recondition Culverts 20 EA

834(2) Clean Ditches and Drainage Structures 300 MI

834(3) General Road Maintenance All LS Per Order Per Order

842(1) Vegetation Maintenance 150 MI

CONTINUATION OF 1449 SCHEDULE

FREMONT-WINEMA NATIONAL FOREST, EAST -

PAISLEY and SILVER LAKE RANGER DISTRICTS (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

FREMONT-WINEMA NATIONAL FOREST, EAST -

PAISLEY and SILVER LAKE RANGER DISTRICTS (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

851(1) Logging Out ML 3-5 Roads 20 MI

851(4) Danger Tree Removal 15 EA

851(6) Hazard or Obstruction Removal 10 EA

861(1) Maintain one- lane cattle guard 4 EA

872(1) Install or Replace Single Post and Sign, Government Furnished

20 EA

872(2) Install or Replace Double Post and Sign, Government Furnished

20 EA

872(3) Install or Replace Sign, Government Furnished

20 EA

881 Equipment Moving 40 MI

T-891-02F Water Supply and Watering 500 MGAL

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Paisley and Silver Lake Ranger Districts

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Ranger Districts

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Bly and Lakeview Ranger Districts

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Bly and Lakeview Ranger Districts

ALL LS

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

807(1) Equipment Rental, Excavator 10 HR

807(2) Equipment Rental, Backhoe 10 HR

807(3) Equipment Rental, Grader 10 HR

807(4) Equipment Rental, Dump Truck 10 HR

808(1) Single Flagger Operation 5 HR

808(2) Dual Flagger Operation 5 HR

811(1) Surface Maintenance Single Lane 175 CLRM

811(2) Surface Maintenance Double Lane 56 CLRM

811(3) Surface Maintenance Single Lane with Roller Compaction

50 CLRM

811(4) Surface Maintenance Double Lane with Roller Compaction

15 CLRM

813(1) Spot Surfacing, Gradation (Government Furnished Material) less than 10 miles one way haul

20 CY

813(2) Spot Surfacing, Gradation (Government Furnished Material) 10 - 20 miles one way haul

30 CY

832(1) Load, Haul and Place Material (Less than 10 miles one way haul)

100 CY

832(2) Load, Haul and Place Material (10 - 20 miles one way haul)

100 CY

834(1) Clean and Recondition Culverts 20 EA

834(2) Clean Ditches and Drainage Structures 300 MI

834(3) General Road Maintenance All LS Per Order Per Order

842(1) Vegetation Maintenance 150 MI

851(1) Logging Out ML 3-5 Roads 20 MI

CONTINUATION OF 1449 SCHEDULE

FREMONT-WINEMA NATIONAL FOREST, WEST -

CHEMULT, CHILOQUIN and KLAMATH RANGER DISTRICTS (2 pages)

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

EST.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

TOTAL

AMOUNT

FREMONT-WINEMA NATIONAL FOREST, WEST -

CHEMULT, CHILOQUIN and KLAMATH RANGER DISTRICTS (2 pages)

PAYABLE SUB ITEM: (must quote on all payable sub-items within an item)

851(4) Danger Tree Removal 15 EA

851(6) Hazard or Obstruction Removal 10 EA

861(1) Maintain one- lane cattle guard 4 EA

872(1) Install or Replace Single Post and Sign, Government Furnished

20 EA

872(2) Install or Replace Double Post and Sign, Government Furnished

20 EA

872(3) Install or Replace Sign, Government Furnished

20 EA

881 Equipment Moving 40 MI

T-891-02F Water Supply and Watering 500 MGAL

881(1) Mobilization rate for BPA Call Subtotal amount that is: < $10,000 Chemult, Chiloquin and Klamath RD's

ALL LS

881(2) Mobilization rate for BPA Call Subtotal amount that is: > $10,000 up to $25,000 Chemult, Chiloquin and Klamath RD's

ALL LS

881(3) Mobilization rate for BPA Call Subtotal amount that is: > $25,000 up to $50,000 Chemult, Chiloquin and Klamath RD's

ALL LS

881(4) Mobilization rate for BPA Call Subtotal amount that is: > $50,000 Chemult, Chiloquin and Klamath RD's

ALL LS

CLRM-Center Line Road Mile, MI-Mile, CY-Cubic Yard, EA-Each, LS-Lump Sum, HR-Hour

Solicitation #: 1204T019Q0023 2019 CW Road Maintenance BPA

SF-1449: Page 32 of 32

Continuation of SF 1449: Schedule

All questions concerning this solicitation shall be submitted in writing to the Contracting Officer, Janet Paul, at janet.paul@usda.gov, or by mail, hand delivery or Fax to the address in block 9 of the SF-1449. The last date to submit questions is June 3, 2019. The answers to the final questions will be posted to FBO for all contractors to view on or around June 7, 2019. If you have questions after June 7, 2019, send them via email and we will determine if they necessitate an extension. No information concerning this solicitation provided in response to telephone calls or email shall be considered binding. All official answers to questions will be posted to FBO via an Amendment.

This is a Fixed Price Blanket Purchase Agreement (BPA) effective from the date of award until June 30, 2024.

NOTE: Prospective contractors may bid on any or all of the individual 13 Items, however, within each individual bid item you must provide a Firm-Fixed Unit Price for ALL payable sub-items within that Item. Unit prices shown on the individual Schedule of Items are effective and fixed from the date of award through June 30, 2020 (Base Year). Your identified annual price adjustment percentage will be applied for each subsequent Option Year, at the rate you identify below.

If you choose to not bid on a specific Item (i.e. District(s)), please enter “No Bid” on the respective Schedule of Item(s) page.

ANNUAL PRICE ADJUSTMENT

Quoters wishing to propose revised prices in successive years shall state in the spaces below the price adjustment percentages to be used by the Government to compute future year prices. For instance, a 3% price adjustment factor is shown as 3% (rather than 103% or 1.03). Note that the price adjustment percentage can be either negative or positive. The factors stated will be compounded annually. If no percentage is entered, future year prices will be the same as base year prices (per the Schedule of Items (SOI)). Offer’s price adjustment percentages(s):

Unit prices shown on SOI are effective for the Base Year: July 1, 2019 – June 30, 2020

___________% Year 1: Effective July 1, 2020 – June 30, 2021 ___________% Year 2: Effective July 1, 2021 – June 30, 2022 ___________% Year 3: Effective July 1, 2022 – June 30, 2023 ___________% Year 4: Effective July 1, 2023 – June 30, 2024

Quotes may be submitted for all or some of the Items listed in the solicitation; all Payable Sub-items under an Item must be quoted on to be considered for that Item. Quoters who are not providing pricing for an Item shall write “NO QUOTE” in the Total Item box.

Contractor DUNS Number: _______________________________

Contractor Email Address: ________________________________

General Instructions, Clauses and Provisions

ISSUANCE OF BPA CALLS

All work will be ordered by Firm-Fixed price BPA CALLS at the prices listed on the Schedule of Items. Orders may be issued orally, or by facsimile, or by electronic commerce methods.

Concurrent BPA Calls may be issued.

Any Forest Service warranted Contracting Officer, within the limits of their warrant, may award and administer a BPA Call for work covered.

The Government anticipates awarding 1, 2 or 3 awards per Item as follows:

Siuslaw National Forest o Item 1 – Central Coast and Hebo Ranger Districts

Willamette National Forest o Item 2 – Santiam River Zone (Detroit and Sweet Home Ranger Districts) o Item 3 – McKenzie River Ranger District o Item 4 – Middle Fork Ranger District

Umpqua National Forest o Item 5 – Cottage Grove Ranger District o Item 6 – Diamond Lake and North Umpqua Ranger Districts o Item 7 – Tiller Ranger District

Rogue River-Siskiyou National Forest o Item 8 (East) – High Cascades Ranger District o Item 9 (East) – Siskiyou Mountains and Wild Rivers Ranger Districts o Item 10 (West) – Gold Beach and Powers Ranger Districts

Fremont-Winema National Forest o Item 11 (East) – Bly and Lakeview Ranger Districts o Item 12 (East) – Paisley and Silver Lake Ranger Districts o Item 13 (West) – Chemult, Chiloquin and Klamath Ranger Districts

The start work date and performance time will be identified on each BPA Call. BPA Calls may be issued continuously with no time discounted for weather or fire restrictions.

Note: prospective awardees MUST be registered in the System for Award Management (SAM) to be awarded a Federal Government Contract. If you are not registered, please register at the following site: https://www.sam.gov/portal/public/SAM/

FAR 52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS (OCT 2018)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights --

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C.3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71,Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include --

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information…