J4 Project Drawings.pdf

PDF 2 MB Posted

Attached to
CUSTER GALLATIN NATIONAL FOREST - Rainbow Point Boat Ramp Construction
Solicitation number
12034320Q0027
Issued by

View the file

Other files

File Type Posted
Amendment 001 Corrected Page C-04.pdf PDF
Amendment 001.pdf PDF
J3 Project Specifications.pdf PDF
20Q0027 RFQ.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAWN

DESIGNER

STAMPS, LOGOS, AND SEALS

PROJECT NAME

DRAWING TITLE

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DRAWING SHEET NO.

DATENO.

REVISION / ISSUE

OFSHEET

United States Department of Agriculture Forest Service

1/1 3/2

0 1 3:

Z

HI

ED

EM

AN

C :\U

SE

RS

\Z

HI

ED

EM

AN

\B

OX

\01

. Z

AC

HA

RY

.H

IE

DE

MA

N W

OR

KS

PA

CE

\20

_R

AI

NB

OW

PO

IN

TR

AM

P\

RA

IN

BO

W

RA

MP

-0 8-

.D

W G;

REGION 1

NORTHERN REGION

RAINBOW POINT

BOAT RAMP

CUSTER GALLATIN

NATIONAL FOREST

HEBGEN LAKE

RANGER DISTRICT

SITE PLAN, CONTROL

POINTS, AND NOTES

01/08/2020

Z.HIEDEMAN

C.DAVIS

J.KEMPFF

C-02 2 6

EX. CONCRETE BLOCK (TYP)

(TO BE REMOVED)

HEBGEN LAKE

EX. DOCK AND 4" PILINGS

(PROTECT IN PLACE)

CP #2

CP #1

PARKING AREA

ISLAND

I

S

L

A

N

D

EX. WATER

APPURTENANCES

CONTROL POINT COORDINATES

POINT NORTHING EASTING ELEVATION

CP#1 197715.34' 1533607.35' 6542.64'

CP#2 197924.22' 1533525.85' 6540.87

BASIS OF BEARING:

All Bearings are based upon Geodetic Meridian.

EX. EDGE OF

PARKING AREA (TYP)

EX. TREE (TYP)

EX. EDGE OF

PAVEMENT (TYP)

PROPOSED

CONCRETE RAMP

SIGN (TYP)

SIGN (TYP)

RELOCATE EX. BOLLARDS AS

NECESSARY FOR NEW RAMP

LOCATION

RELOCATE EDGE OF

PARKING AREA FOR NEW

RAMP APPROACH

GEOTEXTILE: Use Class 1 Nonwoven Geotextile material complying with FP-14 Section 714.

PROJECT LOCATION: The project is located at the Rainbow Point day use area, 16 miles northwest of the town of West Yellowstone, Montana on Hebgen Lake.

DESCRIPTION OF WORK: The Contractor shall remove existing concrete ramp planks, and install new boat ramp as shown in the plans.

*Contractor may propose, at their option, alternatives to precast concrete option shown (CONTECH ARMORFLEX), such as precast boat ramp planks (Sheet C-06). Any alternative must be approved by the C.O. in writing prior to beginning work.

THE FOLLOWING NOTES APPLY UNLESS INDICATED OTHERWISE

SPECIFICATIONS: Project shall be completed in compliance with FHWA STANDARD SPECIFICATIONS FOR

CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS (FP-14) and FOREST

SERVICE SPECIAL SPECIFICATIONS.

EROSION CONTROL PLAN: Submit a soil erosion plan to the Contracting Officer at least 7 (seven) days prior to construction. Provide methods to prevent runoff from construction site from entering directly into Hebgen Lake and adjacent waterways.

BOAT RAMP PRECAST PLACEMENT PLAN: Submit a plan to the Contracting Officer for placement of precast components of the ramp at least 7 (seven) days prior to any construction activities. Precast component placement plan shall describe exactly how the Contractor plans to construct all boat ramp elements; shall include construction timing and sequencing; and shall include all anticipated dewatering activities and considerations.

TEMPORARY TRAFFIC CONTROL: The boat ramp area may be closed for construction. Submit a Temporary

Traffic Control Plan to the Contracting Officer for approval at least 30 days prior to intended use.

CONCRETE: Use Class A(AE) contrete with F'c = 4,000 PSI at 28 days and an entrained air content of 5% +/- 1%.

Chamfer all exposed edges of concrete 3/4" and fillet all acute angles 3" unless otherwise noted. Finish concrete in accordance with Section 522.16 of the Specifications. Concrete pour shall be monolithic, including thickened edge, between expansion joints.

REINFORCING STEEL: Use reinforcing steel of the deformed type conforming to AASHTO M31 (ASTM A615), Grade 60. Concrete cover shall be 2" min. except where shown. Cut and bend steel in accordance with ACI 315.

WELDING: Weld in accordance with the Structural Welding Code, AWS D1.1 with E70XX electrodes.

FOUNDATION INVESTIGATION: A subsurface foundation investigation was not completed at the site.

GENERAL NOTES

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text

( IN FEET )

AutoCAD SHX Text

SCALE

AutoCAD SHX Text

AutoCAD SHX Text S

AutoCAD SHX Text W

AutoCAD SHX Text

MV

AutoCAD SHX Text

USFS

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

DRAWN

DESIGNER

STAMPS, LOGOS, AND SEALS

PROJECT NAME

DRAWING TITLE

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DRAWING SHEET NO.

DATENO.

REVISION / ISSUE

OFSHEET

United States Department of Agriculture Forest Service

1/1 3/2

0 1 3:

Z

HI

ED

EM

AN

C :\U

SE

RS

\Z

HI

ED

EM

AN

\B

OX

\01

. Z

AC

HA

RY

.H

IE

DE

MA

N W

OR

KS

PA

CE

\20

_R

AI

NB

OW

PO

IN

TR

AM

P\

RA

IN

BO

W

RA

MP

-0 8-

.D

W G;

REGION 1

NORTHERN REGION

RAINBOW POINT

BOAT RAMP

CUSTER GALLATIN

NATIONAL FOREST

HEBGEN LAKE

RANGER DISTRICT

RAMP PLAN-VIEW AND

LONGITUDINAL

SECTIONS

01/08/2020

Z.HIEDEMAN

C.DAVIS

J.KEMPFF

C-03 3 6

F

T

R

A M

P

W

I D

T H

15 FT 15 FT

EXPANSION

JOINT

CONTRACTION

JOINT (TYP.)

A

S H

E E

T

C

G

R

O

O

V

E

A

S T

A

S T

A

LONGITUDINAL SECTION

ON RAMP CENTERLINE

(NOT TO SCALE)

15 FT 15 FT 15 FT 15 FT 40 FT

CONTRACTION

JOINT (TYP.)

CONTRACTION

JOINT (TYP.)

EXPANSION

JOINT

CONTECH ARMORFLEX 50-S

PRECAST BLOCKS

DETAILS C-05 (NOT TO SCALE)

S T

A

CLASS 1 RIPRAP IN FABRIC

LINED DITCH PER DETAILS

(SECTION 251)

F

20 FT

F

T S

L O

P E

L E

N

G

T H

F

T S

L O

P E

L E

N

G

T H

2%

EXPANSION

JOINT

EXPANSION

JOINT

LONGITUDINAL

CONTRACTION

JOINT AT

CENTERLINE

RAMP PLAN VIEW

(NOT TO SCALE)

ANCHOR TOP PER

ARMORFLEX STANDARD

DETAIL (SHEET C-05)

CONTECH ARMORFLEX 50-S PRECAST

BLOCKS OR APPROVED EQUAL

(NOT TO SCALE)

ANCHOR TOE PER

ARMORFLEX STANDARD

DETAIL (SHEET C-05)

EXISTING GROUND

AT CONTRACTORS DISCRETION, PRECAST

CONCRETE PLANKS (SHEET C-06) MAY BE

SUBSTITUTED FOR ARMORFLEX BLOCKS.

S T

A

O H

W M

O r d i n a r y

H i g h

W a t e r

M a r k

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

L

E V

A T

I O

N

F

E E

T

STATION (FEET)

Boat Ramp CL Profile

0+00 0+20 0+40 0+60 0+80 1+00 1+20 1+40 1+50

-2 .0

DRAWN

DESIGNER

STAMPS, LOGOS, AND SEALS

PROJECT NAME

DRAWING TITLE

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DRAWING SHEET NO.

DATENO.

REVISION / ISSUE

OFSHEET

United States Department of Agriculture Forest Service

1/1 3/2

0 1 3:

Z

HI

ED

EM

AN

C :\U

SE

RS

\Z

HI

ED

EM

AN

\B

OX

\01

. Z

AC

HA

RY

.H

IE

DE

MA

N W

OR

KS

PA

CE

\20

_R

AI

NB

OW

PO

IN

TR

AM

P\

RA

IN

BO

W

RA

MP

-0 8-

.D

W G;

REGION 1

NORTHERN REGION

RAINBOW POINT

BOAT RAMP

CUSTER GALLATIN

NATIONAL FOREST

HEBGEN LAKE

RANGER DISTRICT

PROFILE VIEW AND

SECTIONAL DETAILS

01/08/2020

Z.HIEDEMAN

C.DAVIS

J.KEMPFF

C-04 4 6

PROPOSED

CL GRADE

EXISTING CL GRADE

(SURVEYED)

S

E L

B E

G I N

B

S

E L

E N

D

R

A M

P

EXISTING CL GRADE

(PROJECTED)

2 FT

S

E L

G B

S

E L

E N

D

C

A S

T I N

P

L A

C E

B E

G

R M

O R

F L

E X

SECTION A: TYPICAL RAMP CROSS-SECTION

(NOT TO SCALE)

2 FT20 FT

H 1"=10'

V 1"=2.5'

F

T

F

T

FILL SLOPE AT 2H:1V

(TYP BOTH SIDES)

8"

GROOVED SURFACE

POURED CONCRETE RAMP

THICKENED EDGE PER

DETAIL THIS SHEET.

SITE-SPECIFIC GEOTEXTILE

CONTINUOUS UNDER RIPRAP

(TYP BOTH SIDES)

CLASS 1 RIPRAP

(PROTECT RAMP EDGES

AND SURFACE DURING

PLACEMENT)

GRADE, SMOOTH, AND COMPACT APPROVED

BEDDING MATERIAL IN ACCORDANCE WITH

SECTION 209

EXPANSION JOINT DETAIL

(NOT TO SCALE)

" EXPANSION JOINT FILLER.

EXTEND JOINT FILLER FROM BOTTOM

OF SLAB TO WITHIN

" OF FINISHED

SLAB SURFACE.

" x 18" DOWELS

AT 12" SPACING

4" 2"

1"

EXPANSION CAP

REBAR

LUBRICATE PORTION OF DOWEL IN

THIS SLAB TO PREVENT BOND

BETWEEN CONCRETE AND STEEL

SEALANT & BOND BREAKER

" RADIUS ALL CORNERS

THICKENED EDGE DETAIL

(NOT TO SCALE)

4"

8"

18"6"

3"-4"

2 FT

GRADE 60 #4 @ 12" MAX EACH DIRECTION

PROVIDE 18" STAGGERED SPLICE

GRADE 60 #4 @ 12" MAX EACH DIRECTION

PROVIDE 18" STAGGERED SPLICE

RAMP SURFACE GROOVE DETAIL

(NOT TO SCALE)

RAMP SURFACE

TRACTION / DRAINAGE GROOVE,

1" x 1" V PATTERN

Y

P

90 TYP.

1' TYP.

6"

S

E L

B E

G

R

P

R A

P

F L

A N

K

A

R M

O R

S

E L

O H

W M

CHAMFER

EDGE

" TYP.

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

L E

V A

T I O

N

F

E E

T

STATION (FEET)

0+00 0+20 0+40 0+60 0+80 1+00 1+20 1+40 1+50

-2 .0

ARMORFLEX

CONCRETE MATTRESS

BOAT RAMP CONCRETE

PER DETAILS SHEET C-04

ARMORFLEX

CONCRETE MATTRESS

CLASS 1 RIPRAP

PROPOSED

CL GRADE

EXISTING CL GRADE

(SURVEYED)

S

E L

B E

G

B

S

E L

E N

D

R

A M

P

EXISTING CL GRADE

(PROJECTED)

S

E L

G B

S

E L

HIGHEST RECORDED WATER

SURFACES (2010-2019)

HIGH MARCH 1, MARCH 15,

APRIL 1 & APRIL 15

HIGH MAY 15

PREDICTED WATER SURFACES

(2020)

HIGH MAY 1

HIGH JUNE 1 & JUNE 15

(OHWM)

NOTES:

1. WATER SURFACES AT RAMP SITE WERE ESTIMATED USING RESERVOIR FOREBAY

ELEVATIONS REPORTED BY THE USBR ON 11/27/2019 AT THE FOLLOWING WEBSITE:

https://www.usbr.gov/gp/hydromet/hydromet_arcread.html

2. FOREBAY WATER SURFACE ELEVATIONS WERE CONVERTED TO SURVEYED RAMP SITE

ELEVATIONS USING THE FOLLOWING CONVERSION:

SURVEYED WS ELEVATION ON 10/8/19 OF 6536.2 = USBR ELEVATION ON 10/8/19 OF 6531.6

HISTORIC WATER SURFACE ELEVATIONS ALONG

NEW BOAT RAMP CENTERLINE

H 1"=10'

V 1"=2.5'

CAST-IN-PLACE ARMORFLEX

PREDICTED MARCH 1

PREDICTED MARCH 15

PREDICTED APRIL 1

PREDICTED APRIL 15

PREDICTED MAY 1

PREDICTED MAY 15

DRAWN

DESIGNER

STAMPS, LOGOS, AND SEALS

PROJECT NAME

DRAWING TITLE

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DRAWING SHEET NO.

DATENO.

REVISION / ISSUE

OFSHEET

United States Department of Agriculture Forest Service

1/1 3/2

0 1 3:

Z

HI

ED

EM

AN

C :\U

SE

RS

\Z

HI

ED

EM

AN

\B

OX

\01

. Z

AC

HA

RY

.H

IE

DE

MA

N W

OR

KS

PA

CE

\20

_R

AI

NB

OW

PO

IN

TR

AM

P\

RA

IN

BO

W

RA

MP

-0 8-

.D

W G;

REGION 1

NORTHERN REGION

RAINBOW POINT

BOAT RAMP

CUSTER GALLATIN

NATIONAL FOREST

HEBGEN LAKE

RANGER DISTRICT

HISTORIC AND PREDICTED

LAKE LEVELS, AND

PRECAST STANDARD

DETAILS

01/08/2020

Z.HIEDEMAN

C.DAVIS

J.KEMPFF

C-05 5 6

ARMORFLEX

CONCRETE MATTRESS

SITE SPECIFIC GEOTEXTILE

(TURN ENDS UP)

SITE SPECIFIC GEOTEXTILE

(TURN ENDS UP)

TOP TERMINATION

(NOT TO SCALE)

TOE TERMINATION

(NOT TO SCALE)

FLANK TERMINATION

(NOT TO SCALE)

ARMORFLEX INSTALLATION DETAILS

3'

2'

REBAR

PER DETAILS SHEET C-04

6" APPROVED BEDDING

MATERIAL SECTION 209

APPROVED NATIVE

SUBGRADE (SLOPE

AS REQ'D BY LOCAL

CONDITIONS)

APPROVED NATIVE

SUBGRADE (SLOPE

AS REQ'D BY LOCAL

CONDITIONS)

6" DEPTH APPROVED BEDDING

MATERIAL SECTION 209

6" DEPTH APPROVED BEDDING

MATERIAL SECTION 209

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

DRAWN

DESIGNER

STAMPS, LOGOS, AND SEALS

PROJECT NAME

DRAWING TITLE

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DRAWING SHEET NO.

DATENO.

REVISION / ISSUE

OFSHEET

United States Department of Agriculture Forest Service

1/1 3/2

0 1 3:

Z

HI

ED

EM

AN

C :\U

SE

RS

\Z

HI

ED

EM

AN

\B

OX

\01

. Z

AC

HA

RY

.H

IE

DE

MA

N W

OR

KS

PA

CE

\20

_R

AI

NB

OW

PO

IN

TR

AM

P\

RA

IN

BO

W

RA

MP

-0 8-

.D

W G;

REGION 1

NORTHERN REGION

RAINBOW POINT

BOAT RAMP

CUSTER GALLATIN

NATIONAL FOREST

HEBGEN LAKE

RANGER DISTRICT

ALTERNATE

PRECAST PANEL

DETAILS AND

INSTALLATION

01/08/2020

Z.HIEDEMAN

C.DAVIS

J.KEMPFF

C-06 6 6

PRECAST PANEL INSTALLATION DETAILS

#5 REBAR PER MANUFACTURER

(MIN. 6 PER PLANK)

2" CLEAR

TWISTED CONNECTOR BAR ASSEMBLY

" X 2" X 20" GALVANIZED FLAT BARS

w/

" HOLES

ROUGH TEXTURE SURFACE

" DIAM. HOLES

(2 HOLES / BAR)

PROVIDE GALVANIZED

BOLTS, NUTS, WASHERS

1"

14" OR PER MANUFACTURER

1.5"

#5 REBAR PER MANUFACTURER

(MIN. 6 PER PLANK)

2" CLEAR

PRECAST PANEL SECTION @ CONNECTOR BAR

(NOT TO SCALE)

PRECAST PANEL PLAN VIEW

(NOT TO SCALE)

10' OR PER MANUFACTURER

20' RAMP WIDTH

2.5'5'2.5'

CONNECTION SPACING PER

PRECAST PANEL MANUFACTURER

MIN. 4 CONNECTIONS TO RAMP (TYP.)

CONNECTION SPACING (TYP.)

OR PER PRECAST PANEL MANUFACTURER

MIN. 4 CONNECTIONS TO RAMP (TYP.)

TWISTED CONNECTOR BAR ASSEMBLY

" X 2" X (LENGTH AS NEEDED PER

PRECAST PANEL MANUFACTURER)

GALVANIZED FLAT BARS w/

" HOLES

M

I N

#4 REBAR

DOUBLE ROW

AT EYE BOLTS

EYE BOLTS

(DOWNHILL

EDGE OF

RAMP ONLY)

NOTE: EYE BOLTS ARE

" X 20"

CAST, HOT-DIPPED GALVANIZED STEEL

WITH 3" WASHER SECURED BY TWO BOLTS

EMBEDDED IN CONCRETE

PLAN VIEW OF DOWNHILL EDGE OF CAST-IN-PLACE

RAMP SHOWING EYE BOLT ASSEMBLY

(NOT TO SCALE)

SECTION B: THICKENED DOWNHILL CAST-IN-PLACE

EDGE DETAIL FOR PRECAST OPTION

(NOT TO SCALE)

#4 REBAR DOUBLE ROW

AT EYE BOLTS

EYE BOLT

(DOWNHILL EDGE

OF RAMP ONLY)

#4 REBAR @ 12" MIN.

LAP 18"

CONTINUOUS #4 REBAR

THROUGH THICKENED EDGE

MIN. 3" CLEAR ALL DIRECTIONS

4,000 PSI CONCRETE (TYP.)

PRECAST PANEL FLANK AND TOE

TERMINATION DETAIL

(NOT TO SCALE)

PRECAST BOAT

RAMP PLANK

CLASS 1 RIPRAP

2' X 2' CROSS SECTION

6" DEPTH APPROVED

BEDDING MATERIAL

SITE SPECIFIC GEOTEXTILE

CONTINUOUS UNDER PRECAST PLANKS

AND RIPRAP (TURN ENDS UP)

FILL SLOPE AT 2H:1V

(TYP BOTH SIDES)

NATURAL LAKE

BOTTOM AT TOE

3" GALV. WASHER BOLT

BOTH SITES

EMBED EYE BOLT IN

CONCRETE

(DOWNHILL EDGE

OF RAMP ONLY)

NOTE ON PRECAST ALTERNATIVE: Contractor may propose, at their option, alternatives to precast concrete option shown (CONTECH ARMORFLEX), such as precast boat ramp planks (Sheet C-06). Any alternative must be approved by the C.O. in writing prior to beginning work. Submit engineered precast concrete plans and cut sheets for approval prior to ordering materials.

B

THIS SHEET

AutoCAD SHX Text

30 IN.

AutoCAD SHX Text

20 FT. RAMP WIDTH

AutoCAD SHX Text

60 IN.

AutoCAD SHX Text

30 IN.

AutoCAD SHX Text

30 IN.

AutoCAD SHX Text

60 IN.

AutoCAD SHX Text

30 IN.

AutoCAD SHX Text

CL RAMP

AutoCAD SHX Text

18 IN.

AutoCAD SHX Text

24 IN.

AutoCAD SHX Text

8 IN.

AutoCAD SHX Text

3-4 IN.

AutoCAD SHX Text

4 IN.

AutoCAD SHX Text

4 IN.

AutoCAD SHX Text F

AutoCAD SHX Text O

AutoCAD SHX Text R

AutoCAD SHX Text E

AutoCAD SHX Text S

AutoCAD SHX Text T

AutoCAD SHX Text S

AutoCAD SHX Text E

AutoCAD SHX Text R

AutoCAD SHX Text V

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text P

AutoCAD SHX Text A

AutoCAD SHX Text R

AutoCAD SHX Text T

AutoCAD SHX Text M

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text T

AutoCAD SHX Text O

AutoCAD SHX Text F

AutoCAD SHX Text A

AutoCAD SHX Text G

AutoCAD SHX Text R

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text U

AutoCAD SHX Text L

AutoCAD SHX Text T

AutoCAD SHX Text U

AutoCAD SHX Text R

Sheets and Views
RainbowRamp12-08-19-C-01 TITLE
PLOT
RainbowRamp12-08-19-C-02 SITE PLAN AND CONTROL
OLE1
RainbowRamp12-08-19-C-03 DTLS AND SECTIONS
OLE1
RainbowRamp12-08-19-C-04 RAMP PROFILE AND X-SECT
OLE1
RainbowRamp12-08-19-C-05 WATER LEVELS
OLE1
RainbowRamp12-08-19-C-06 PRECAST ALT.