J3 Project Specifications.pdf

PDF 2 MB Posted

Attached to
CUSTER GALLATIN NATIONAL FOREST - Rainbow Point Boat Ramp Construction
Solicitation number
12034320Q0027
Issued by

View the file

Other files

File Type Posted
Amendment 001 Corrected Page C-04.pdf PDF
Amendment 001.pdf PDF
J4 Project Drawings.pdf PDF
20Q0027 RFQ.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents Preface

101 - Terms¸ Format¸ and Definitions

101.01 Meaning of Terms

101.03 Abbreviations

101.04 Definitions

102 - Bid¸ Award¸ and Execution of Contract

Delete Section 102

103 - Scope of Work

Delete Subsections 103.02, 103.03, 103.04, 103.05. ............................... Error! Bookmark not defined.

104 - Control of Work

Delete Subsections 104.01, 104.02, 104.04

104.06 Use of Roads by Contractor

106 - Acceptance of Work

106.01 Conformity with Contract Requirements

106.02 Visual Inspection

107 - Legal Relations and Responsibility to the Public

Delete Subsection 107.05

108 - Prosecution and Progress

Delete Section 108

109 - Measurement and Payment

Delete Subsections 109.06, 109.07, 109.08, 109.09

109.01 Measurement of Work

109.02 Measurement Terms and Definitions

153 - Contractor Quality Control

153.04 (2) (a) Submittal Log

155 - Schedules for Construction Contracts

Delete Section 155

156 - Public Traffic

Section 156. – PUBLIC TRAFFIC

157 - Soil Erosion and Sediment Control

157.04 General

204 - Excavation and Embankment

Section 204. — EXCAVATION AND EMBANKMENT

208 - Structure Excavation and Backfill for Selected Major Structures

208.07 Dewatering

302 - Minor Crushed Aggregate ............................................................. Error! Bookmark not defined.

302.04 Placing Crushed Aggregate. ..................................................... Error! Bookmark not defined.

552 - Structural Concrete

Section 552. – STRUCTURAL CONCRETE

552.01 Description

552.02 Material

552.03 Construction Requirements

552.08 Delivery

552.18 Loads on New Concrete Structures

622 - Rental Equipment

622.01 Description

703 - Aggregate

703.05 Subbase, Base, Surface Course, and Screened Aggregate

Preface Preface_wo_12_06_2019

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest

System Roads.

101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016

Add the following paragraph to Subsection 101.01:

101.01 Meaning of Terms.

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_National_11_9_2016

Add the following to Subsection 101.03:

101.03 Abbreviations.

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations

AFPA — American Forest and Paper Association

FSAR — Forest Service Acquisition Regulations

MSHA — Mine Safety and Health Administration

NESC — National Electrical Safety Code

WCLIB — West Coast Lumber Inspection Bureau

(f) Miscellaneous unit abbreviations.

MP — milepost location ppm — parts per million volume

STA station location

101.04_National_9_5_2018

Make the following changes to Subsection 101.04:

101.04 Definitions.

Delete these definitions and replace the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line

(including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2)

Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of

Agriculture.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road

Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.

Utilization Standards —

The minimum size and percent soundness of trees described in Public Works contract specifications or

Timber Sale and IRTC contract provisions to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016

Delete Section 102 in its entirety.

Delete Section 102.

103 - Scope of Work

103.01 Intent of Contract. Delete this subsection and replace with the following:

Rainbow Point Boat Ramp

The intent of the contract is to remove an existing concrete boat ramp and replace it with a new boat ramp. This project is located within the Rainbow Point Day Use Area 16 mile

Northwest of West Yellowstone, Montana, in the Custer Gallatin National Forest. The project is located in Section 24, T. 12 S., R. 4 E., Gallatin County, Montana.

This project includes removing and disposing an existing concrete boat ramp, structural excavation, roadway embankment, backfilling, hauling and placing aggregate base, compacting, constructing a new concrete boat ramp, and riprap placement. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

Delete the remaining subsections in this Section.

104 - Control of Work 104.00_National_11_9_2016

Delete Subsections 104.01, 104.02, and 104.04.

Delete Subsections 104.01, 104.02, 104.04.

104.06_National_11_9_2016

Add the following to Subsection 104.06:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road

Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material

105.02 Material Sources

Under (c) Contractor-located sources add the following:

Prior to use of any materials, the Contractor shall provide to the CO a State certification that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

106 - Acceptance of Work 106.01_National_7_18_2017

Delete Subsection 106.01 and replace with the following:

106.01 Conformity with Contract Requirements.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project.

When the Government tests work, copies of test reports are furnished to the Contractor upon request.

Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive.

The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work;

providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

1. Sampling method;

2. Number of samples;

3. Sample transport;

4. Test procedures;

5. Testing laboratories;

6. Reporting;

7. Estimated time and costs; and

8. Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the

Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

1. Have the work accepted at a reduced price; or

2. Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.02_National_11_9_2016

Delete Subsection 106.02 and replace with the following:

106.02 Visual Inspection.

Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.

107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017

107.02 Protection and Restoration of Property and Landscape.

Add the following:

Work within the wetted perimeter of Hebgen Lake will be allowed only as specified in the approved permits.

Delete Subsection 107.05.

Delete Subsection 107.05.

108 - Prosecution and Progress 108.00_National_11_9_2016

Delete Section 108 in its entirety.

Delete Section 108.

109 - Measurement and Payment 109.00_National_11_9_2016

Delete Subsections 109.06, 109.07, 109.08, and 109.09:

Delete Subsections 109.06, 109.07, 109.08, 109.09.

109.01_National_2_22_2019

Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:

109.01 Measurement of Work.

Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement

Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.

Table 109-1

Decimal Accuracy of Quantities for Final Payment

Pay Item Level of Precision

Linear Foot 1

Exception--Timber, Steel, and concrete Piles 0.1

Station 0.1

Mile 0.01

Square Foot 0.1

Square Yard 0.1

Each 1

Acre 0.01

Gallon 1

M-Gals. 0.1

Cubic Yard 1

Exception--Structure Excavation; Sheathing

Materials; Bedding, Bed Course, and Backfill

Materials; Gabions;

0.1

Exception--Concrete; Masonry 0.01

Pound 1

Ton 0.1

Exception--Calcium Chloride;

Sodium Chloride; Hydrated Lime;

Bituminous Materials; Pavements;

Bed Course Materials

0.01

Hour 0.1

MFBM 0.01

Station Yard 1

Cubic Yard Mile 1

Ton Mile 1

109.02_National_11_9_2016

Add the following sentence to Subsection 109.02(b):

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

151 - Mobilization

Delete Section 151 in its entirety and replace with the following.

Description

151.01. This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.

Construction Requirements

151.02. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.

Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.

Notify the CO in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.

Use methods of cleaning and locations for cleaning approved by the CO.

For work at a commercial washing facility, use an approved facility.

New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or

Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party.

Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest

Service is available at each Forest Service office.

Aquatic:

Wash the outside and inside of equipment that will come in contact with waterbodies, such as streams, lakes, wetlands, and ditches with one of the following approved methods:

1. Wash debris, mud, sediments, organisms, plant material and fragments from all equipment that will enter water feature. Allow equipment to thoroughly air dry (inside and out) for a minimum of 48 hrs

2. Wash equipment with heated water (>140° F) for a minimum of ten minutes and until all mud, sediments, organisms, plant material and fragments are removed from equipment.

Allow equipment to thoroughly air dry for a minimum of two hours, or until no visible moisture exits.

3. Wash equipment with a minimum of 5% Quaternary ammonium solution (Quat128

Sparquat256) for a minimum of ten minutes and until all mud, sediments, organisms, plant material and fragments are removed from equipment. Allow equipment to thoroughly air dry for a minimum of two hours, or until no visible moisture exits.

Only equipment inspected by the Forest Service will be allowed to operate within the project. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in.

Equipment will be considered free of debris, mud, sediments, organisms, plant material and fragments when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.

Measurement

151.03 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.

Measure mobilization according to Subsection 109.02.

Payment

151.04. The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule.

Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Progress payments for mobilization lump sum will be paid as follows:

(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5

Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.

Include all costs associated with the initial cleaning of equipment in the unit bid price for

Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.

152 – Construction Survey and Staking

Delete Section 152 in its entirety and replace with the following.

The Forest Service will provide construction survey and staking. Contractor shall provide 14-day notice before beginning work.

153 - Contractor Quality Control 153.10_Regional_5_31_2018

Add the following Subsection:

153.04 (2) (a) Submittal Log At a minimum the contractor shall provide project submittals as shown on the Submittal Log below.

Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.

Submittal Log

Log No.

Indirect payment to Pay

Item(s) Description of Submittal Type of

Submittal

Requirement found in

Specification No.

/Drawings

Additional Specification References

1 151 Weed Free Material Source Certification

Material Certification

FSSS 105.02 (c)

2 151 Hazardous Spill Plan Plan 107.10

3 151 Contractor Quality Control Plan Plan 153.03

4 151 Traffic Control Plan Plan FSSS 156 Drawings

5 151 Dewatering Plan Plan FSSS 157.04 Drawings

6 157 Soil Erosion and Pollution Control Plan

Plan FSSS 157.04 Drawings

7 552 Concrete Mix Design Mix Design 552.03 106, Drawings

8 552 Concrete Testing Test Results 552.19 106, Drawings

9 553 Reinforcing Steel and Wire Rope Material Certification

709.01 553, Drawings

10 553A Precast Concrete Structures Shop Drawing FSSS 553A.04 106, 552, 553, 11 553A Precast Concrete Structures: Testing Test Results FSSS 553A.02 106, 554, 562

12 553A Precast Concrete Structures: Design Design Calculations

FSSS 553A.04 106, 554, 562

13 622 Equipment Rental Equipment Approval

FSSS 622.02

14 714 Geotextile Geotextile Certification

714 106, Drawings

155 - Schedules for Construction Contracts 155.00_National_11_9_2016

Delete Section 155 in its entirety.

Delete Section 155.

156 - Public Traffic 156.00_National_2_5_2019

Delete Section 156 in its entirety and replace with the following:

Section 156. – PUBLIC TRAFFIC Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Permanent Traffic Control 633

Traffic Signing and Marking Material 718

Temporary plastic fence 710.11

Construction Requirements

156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section. Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 15 minutes at any one time followed by an open period of no less than 30 minutes. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection

106.07(b).

Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM

7100-15. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the

National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. The Contractor will be allowed to close the Rainbow Point Boat Launch in the immediate vicinity of the project to public traffic during construction. Provide at least 14 days advance written notice to the CO prior to any road closure period, to allow public notice of the closure period by the Forest Service.

Private residences use the southern portion of the parking area to access their homes and driveways. All adjacent property owners must always be able to access their property. Delays up to 15 minutes are permitted.

Develop a construction sign plan (temporary traffic control plan) identifying the type and location of all advanced warning signs necessary to safely restrict or pass public traffic. Install construction signs conforming to the Manual on Uniform Traffic Control Devices (MUTCD) prior to proceeding with any construction work. Furnish, maintain and remove all barricades and signs required for construction signing and trail closures.

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See

Subsection 109.05.

157 - Soil Erosion and Sediment Control

157.02 Materials

Add the following:

Provide bales, wattles, logs and rolls from a certified noxious weed free source.

Delete Subsection 157.03.

Delete Subsection 157.03.

Delete Subsection 157.04 and replace with the following:

157.04 General.

Thirty (30) days prior to the start of construction, submit a written plan according to subsection 104.03 with all necessary permits that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control without approval.

When erosion control measures are not functioning as intended, take corrective action to eliminate or minimize pollutants in storm water discharges from the project.

Reflect in the Erosion Control Plan special concerns and measures necessary to protect resources and government improvements. Include:

(a) The construction activities and sequence of implementation relating to specific erosion control measures.

(b) The location and type of permanent controls to be implemented during construction.

(c) The location and type of temporary controls to be implemented during construction.

(d) For work within the lake a detailed dewatering / precast plank placement plan.

(e) For work adjacent to the lake without water describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery.

(f) Description of the monitoring plan.

Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.

157.05 Controls and Limitations on Work.

Add the following to the second paragraph:

Temporary erosion control measures will be in place throughout and at the end of each day’s operation.

Earthwork operations may be temporarily suspended if significant rainfall is forecasted.

203 - Removal of Structures and Obstructions

203.01 Work.

Delete and replace with the following:

This work consists of disposing of clearing slash, salvaging, removing and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.

203.05 Disposing of Material.

(a) Remove from project Add the following:

All materials designated for removal become the property of the Contractor and are to be disposed of by removing off of Forest Service Lands in accordance with all local, state and federal requirements.

(b) Burn. Delete this subsection

(c) Bury. Delete this subsection

204 - Excavation and Embankment 204.00_Forest_5_21_2019

Section 204.11 — Compaction

Delete the contents of this Subsection and replace with the following:

Compact all embankments and roadbed materials using the following method:

1) Method 1. Moisten or dry the aggregate to a uniform moisture content suitable for compaction.

Operate a vibratory steel-wheeled roller having a minimum weight of 5 ton, equipped with amplitude and frequency controls, over the full width of each layer until visual displacement ceases, making not fewer than three complete passes.

208 - Structure Excavation and Backfill for Selected Major

Structures 208.07_National_11_8_2016

Add the following to Subsection 208.07:

208.07 Dewatering.

Construct diversions according to Subsection 157.10 Diversions. Submit dewatering plans according to

Subsection 104.03.

552 - Structural Concrete 552.00_Regional_4_18_2019

Section 552. – STRUCTURAL CONCRETE

552.01 Description.

Delete the first paragraph of Subsection 552.01 and replace with the following:

This work consists of furnishing, placing, finishing, and curing concrete to be cast-in-place in bridges, culverts, and other structures; furnishing precast concrete elements by forming, placing reinforcing steel, placing and finishing concrete, curing, and transporting members; and materials testing and implementing quality control procedures. When specified, work also includes installation of furnished precast concrete elements, including performing all necessary grouting, welding or other connections;

and repairs or finishing associated with transport and the removal of lifting devices.

552.02 Material.

Add the following references to Subsection 552.02:

Dowel bars 709.01(f)

Falsework and forms 562

Hook bolts 709.01(e)

Mortar cement 701.02(b)

Reinforcing steel 554

Structural steel 717.01

552.03 Construction Requirements.

Delete Table 552-1 and its footnotes and replace with the following table and footnotes:

Table 552-1

Composition of Concrete

Class of

Concrete

Minimum Compressive

Strength

@ 28-Days, f’c, psi (MPa)

Maximum Water/

Cementitious

Material Ratio

Coarse Aggregate Size

Number AASHTO M

43 (1)

A 4500 (31.0) 0.45 5, 56, 57

A(AE) (5) 4500 (31.0) 0.45 5, 56, 57

C 4500 (31.0) 0.45 7, 78

C(AE) 4500 (31.0) 0.45 7, 78

D(AE) (2) 5000 (34.5) 0.40 5, 56, 57

P (Precast, Prestressed) (3) (4) (5)

See plans – 6,7,67,68,78

P(AE) (3) (4) (5) See plans – 6,7,67,68,78

S (Seal) – 0.54 5, 56, 57

(1)

(2) (1) Meet the processing requirements of AASHTO M 43, Table 1 – Standard Sizes of Processed Aggregate.

(3) (2) The maximum water-soluble chloride ion (Cl-) content is 0.15 percent by mass of cement. Determine the water-soluble chloride ion content of concrete made with mix ingredients at an age between 28 and

48 days according to ASTM C1218. Submit test results with the concrete mix design for approval.

(4) (3) The maximum water-soluble chloride ion (Cl-) content is 0.06 percent by mass of cement. Determine the water-soluble chloride ion content of concrete made with mix ingredients at an age between 28 and

48 days according to ASTM C1218. Submit test results with the concrete mix design for approval.

(5) (4) Use Class P (AE) concrete in the entire depth of the top flange of all multi-beam bridge girders. In lieu of this, Class P (AE) concrete may be used for fabrication of the entire girder and throughout the entire depth of prestressed slabs. In all cases, furnish concrete meeting the 28 day specified minimum concrete strength requirements for the prestressed members as shown on the plans, unless otherwise specified.

(6) (5) Use Class A (AE) or Class P (AE) concrete for precast elements to be used as substructure elements, such as footings or foundations. Use Class P (AE) concrete for fabrication of precast elements to be used in a precast (non-prestressed) superstructure element, including slabs, girders, and box culverts where traffic will be in contact with the horizontal top surface. In all cases, furnish concrete meeting the 28 day specified minimum concrete strength requirements for the precast or prestressed members as shown on the plans, unless otherwise specified.

(7)

Delete the second and third paragraph of Subsection 552.03 and replace with the following:

Submit written concrete mix designs on FHWA Form 1608, 552 Structural Concrete Mix Design

Submittal, or other format that is professional in appearance and provides all of the required information in subsections (a) through (z) of this section, 552.03. Allow at least 30 calendar days for approval before production.

Add the following Subsection 552.03 under the list of items to be included in the mix design submittal:

(z) Evaluation of potential aggregate reactivity

552.08 Delivery.

Delete the last sentence of the first paragraph of Subsection 552.08(a) with the following:

Do not exceed 130 total revolutions at mixing speed, including both initial mixing and remixing. Do not exceed 300 total revolutions, including both mixing and agitating speed.

Delete table 552-4 and its footnotes and replace with the following table and footnotes:

Table 552-4 Concrete Remixing and Discharge Time Limits

Cement Type (1) Admixtures Remixing Time Limit

(hour)

Discharge Time Limit

(hour)

Type I, IA, II, IIA, V, or approved blended hydraulic cement

None 0.75 1.00

Type I, IA, II, IIA, V, or approved blended hydraulic cement

ASTM

C494, Type B, D, or G(2)

1.25 1.50

Type I, IA, II, IIA, V, or approved blended hydraulic cement

Hydration stabilizer

3.00

Approved design discharge time limit,

3.50 maximum

Type III None 0.50 0.75

Type III

ASTM

C494, Type B, D, or G(2)

1.00 1.25

(1) AASHTO M 85 or AASHTO M 240 as applicable.

(2) ASTM C494 defines Type B as a retarding admixture, Type D as a Water-reducing and retarding admixture, and Type G as a Water-reducing, high range, and retarding admixture.

552.18 Loads on New Concrete Structures.

Add the following paragraph to Subsection 552.18:

Do not allow public traffic on the bridge until approaches, curbs, and bridge rail are completed and in-place. Erect barricades at each end of bridge spans when road approaches allow vehicles to drive directly onto the structure.

Delete Subsections 552.20, 552.21, and 552.22 and replace with the following:

552.20 Precast Elements. Precast concrete elements and members considered structural in nature shall meet the following specifications of this section.

(a) Certification and/or Quality Assurance of Precast Manufacturing Plant. Furnish precast concrete members using a plant with one of the following certifications, appropriate to the type of member being fabricated:

(1) Precast/Prestressed Concrete Institute (PCI)

(a) Bridge 1, Precast Bridge Products (no prestressed reinforcing).

(b) Commercial 1, Precast Concrete Products (no prestressed reinforcing).

(2) National Precast Concrete Association (NPCA)

(3) American Concrete Pipe Association (ACPA)

When available, submit a copy of the transmittal letter of the latest PCI, NPCA, or ACPA inspection and certification with the shop drawings.

In lieu of the above certification, the Contractor shall retain a professional engineer to provide quality assurance for the work by inspecting and certifying in writing the concrete members are constructed in accordance with the contract specifications and FSSS Section 552 and shall include information including but not limited to the following:

(a) Shop drawings review.

(b) Concrete member dimensions.

(c) Concrete mix design.

(d) Aggregate sources, moisture contents, test results.

(e) Steel reinforcing placement.

(f) Concrete curing and strength test results.

(g) Concrete material certifications.

(h) Placement mixing, delivery and sampling.

(i) Properly calibrated production and test equipment

(j) Proper records keeping including; personnel qualifications and training records, material sources, quality control testing results for the aggregate and concrete, pre-pour and post-pour inspection reports, batching records, disposition of failing products, and shipping.

Material sources shall be on the State’s approved supplier list or approved in writing by the CO.

Furnish the certification or supplemental information above to the CO prior to shipment of materials and installation at the job site.

Perform all sampling, testing, and inspection necessary to ensure quality control of the component materials and the concrete. Sample and test for quality control and acceptance testing in accordance with the AASHTO or ASTM test methods prescribed in Section 552.

Maintain adequate records of all inspections and tests. Keep records that indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and the nature of any corrective action taken.

(b) Precast Manufacturing Plant (i.e. Casting Yard). The precasting of concrete structural members may be done at a casting yard of an industry-certified plant or a casting yard of the Contractor’s choice with the appropriate certifications discussed above.

(c) Tolerances. Place and consolidate concrete so that shrinkage cracks are not produced in the member.

Verify that the prefabricated elements will fit-up and align properly before shipping from the precast facility. Assembling each superstructure and substructure composed of prefabricated elements in the yard prior to shipping the elements to the project site is a suitable way to perform such verification. If assembled in the yard, use blocking to simulate the support of the elements and the spacing between the elements. Verify all elements are constructed in compliance with all plan requirements. Dry fit all connections in the fabrication yard prior to installation of the elements at the bridge site.

Fabricate precast concrete foundation units straight and true size and shape with exposed edges and corners precise and true so each finished unit complies with the following dimension tolerances as well as position tolerances for cast in items:

(1) Length shall not vary by more than ¾ inch.

(2) Height/Width shall not vary from that shown in the design by more than ¼ inch.

(3) Local smoothness shall be no more than ¼ inch in 10 feet for any surface, except when finishing or form liners are called out or accepted as part of the submittal

(4) Position of inserts for structural connections shall not vary from that shown in the shop drawings by more than ½ inch.

(5) Placement of non-prestressed reinforcement shall comply with Section 554

Reinforcing Steel.

(d) Submittals. Submit four (4) sets of shop drawings to the CO for approval according to subsection 104.03, a minimum of 21 days before fabrication of the precast member(s). In lieu of hard copy shop drawing submittals, electronic submittals are acceptable. Show all details necessary for fabrication, including the following:

(1) Details and location of all lifting holes, inserts, hardware, devices, and any additional reinforcing required for lifting. Include supporting calculations and lifting procedures.

(2) Describe the method of curing, handling, storing, and transporting the elements.

(3) Concrete mix design for all precast elements.

(e) Quality Assurance.

(1) Permanently mark each element with date of fabrication, supplier identification and module identification. Stamp markings in fresh concrete.

(2) Prevent cracking or damage of precast components during handling and storage.

(3) Replace or repair defective or broken precast concrete deck and concrete deck overhang elements according to section 106. Requests to repair defective or broken elements are subject to the following;

(a) Obtain approval before performing concrete repairs.

(b) Concrete repair work must re-establish the module’s structural integrity, durability, and aesthetics to the satisfaction of the CO.

(c) Describe the cause of damage and the corrective action taken to eliminate future damage.

(d) An updated CPM schedule showing the effects of repair work on project completion must be submitted.

(4) Elements will be rejected if they do not conform to the contract documents, and for the following reasons:

(a) Full-depth cracking of concrete and concrete breakage that is not repairable.

(b) Cracks that extend to the nearest reinforcement plane, or fine surface cracks that do not extend to the nearest reinforcement plane but are numerous or extensive.

(c) Camber that does not meet the requirements of the plans or fabrication drawings.

(d) Honeycombed texture.

(e) Dimensions exceeding the allowable tolerances.

(f) Damage during fabrication, transportation, erection, or construction.

(5) Document all test results for structural concrete. Show in the quality control files at least the following information:

(a) Element identification.

(b) Date and time of fabrication concrete pour.

(c) Concrete cylinder test results.

(d) Concrete mix design and the batch print out.

(e) Form-stripping date.

(f) Location and number of blockouts and lifting inserts.

(g) Temperature, moisture, and duration of curing period.

(h) Approved repair procedures.

(f) Handling, storing, and transporting.

(1) Damage/Cracking. Prevent cracking or damage of prefabricated elements and modules during handling, storing, and transporting.

(2) Precast Element Sizes. Finalize the size of precast elements with consideration for shipping restrictions, equipment availability, and site constraints. Show the final element sizes on the assembly plan.

(3) Lifting Devices. The design and detail of the lifting devices is the responsibility of the contractor. Use lifting devices in a manner that does not cause damage, cracking, or torsional forces. Place the lifting devices in locations that are not visible once the prefabricated element is placed, or within recessed pockets that can be patched after installation.

(4) Safety. The Contractor is responsible for the safety and stability of prefabricated elements during all stages of handling, transportation, and construction.

(5) Handling and Storing. Store the precast units in a horizontal and upright position, supported at their designated bearing points. Follow Chapter 5 of the PCI Design

Handbook for handling and erection bracing requirements.

Lift the precast elements so that the angle between the top surface of the precast element and the lifting line is not less than 60 degrees when measured from the top surface of the precast elements to the lifting line. If two cranes are used, then the lifting lines shall be vertical. Lift the modules at the designated points. The Contractor is responsible for handling stresses in the modules. Choose the locations of the lifting points so that the anticipated flexural tensile stress induced in the top of the structural concrete for the assumed support locations is not greater than the allowable stress.

Select smooth and well compacted storage areas to prevent damage due to differential settlement. Support precast elements during storage to prevent cracking or creep induced deformation (sagging). Check precast elements at least once per month to ensure that creep‐induced deformation does not occur.

Protect the elements from freezing temperatures for 5 days after casting or until precast concrete attains design compressive strength. Do not remove thermal protection for any length of time before the units attain the specified compressive strength when the surrounding air temperature is below 20 °F (‐6 °C).

Before transporting precast concrete members, provide written certification that the members were fabricated and visually inspected in conformance with 552 and meet minimum quality requirements.

(6) Additional Reinforcement. Provide additional reinforcement, as needed, to meet the requirements of handling, transporting, and erecting precast members.

(7) Requirements Prior to Shipping. Do not ship precast concrete members until concrete cylinder tests, manufactured from the same concrete and cured under the same conditions as the members, indicate that the concrete in each member has attained the minimum required design strength and is at least 7 days old.

(g) Installation.

(1) Install members without damage to structural capacity, shape, or finish. Replace or repair damaged members.

(2) Install members level and plumb without exceeding the following allowable tolerances:

(a) Plan Location from Design Datum: Plus or Minus ½ in. (±13mm).

(b) Top Elevation from Nominal Top Elevation: Plus or Minus 3/8 in. (±6mm).

(c) Maximum Plumb Variation over the Lesser of Height of Structure or 100 ft (30m): 1

in. (25 mm).

(d) Plumb in Any 10 ft (3 m) of Element Height: ¼ in. (6mm).

(e) Maximum Jog in Alignment of Matching Edges: ¼ in. (6mm).

552.21 Acceptance.

See Table 552-9 for sampling, testing, and acceptance requirements and the quality characteristic category.

Reinforcing steel, anchor devices, elastomeric bearings, and material for concrete and grout will be evaluated under Subsection 106.03. Furnish production certifications for hydraulic cement, reinforcing steel, and any other cementitious materials.

Cast in place concrete mixture’s slump, air content, density, and temperature will be evaluated under Subsections 106.02 and 106.04.

Concrete compressive strength will be evaluated under Subsection 106.05. The lower specification limit is the minimum required compressive strength at 28 days (f’c) specified in the contract. Remove and replace concrete represented by cylinders having a compressive strength less than 90 percent of the minimum 28-day strength (f’c).

Concrete for precast concrete members will be evaluated under Subsections 106.02, 106.03, and 106.04.

Construction of all precast concrete members and concrete structures (including batching, placing, finishing, and curing concrete) will be evaluated under Subsections 106.02 and 106.04.

Reinforcing steel will be evaluated under Section 554.

Falsework and forms will be evaluated under Section 562.

Measurement

552.22 Measure the Section 552 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

When measuring structural concrete by the cubic yard (cubic meter), measure in the structure.

Do not measure reinforcing steel, concrete, anchorages, plates, nuts, and other material contained within or attached to the unit for precast concrete structural members.

Payment

552.23 The accepted quantities will be paid at the contract price per unit of measurement for the Section

552 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this

Section. See Subsection 109.05

553A – Precast Concrete Structures Description

553A.01 Work. This work consists of designing, fabricating, and installing precast concrete boat ramp plank sections AS SHOWN ON THE DRAWINGS. The precast concrete plank sections shall be contractor designed units to the overall dimensions shown on the drawings. The contractor’s design shall be submitted for approval (see section 553A.04 below). The work also includes steel connections for linking the plank sections together, hardware, shop drawings, and other incidentals as required.

Materials

553A.02 Requirements. Provide materials that meet the requirements specified in the following subsections:

Reinforcing Steel ……………………………………………… 709.01

Sealants, Fillers, Seals, & Sleeves ……………………… 712.01

Structural Concrete …………………………………………… 552

Structural Steel ………………………………………………… 717.01

Provide precast concrete members of the size, shape, strength, air content, and finish that are SHOWN

ON THE DRAWINGS. Precast concrete members must be manufactured by a plant with the following certifications:

Precast/Prestressed Concrete Institute (PCI)

Commercial 1, Precast Concrete Products (no prestressed reinforcing)

National Precast Concrete Association (NPCA)

• Precast

Submit a copy of the transmittal letter of the latest PCI or NPCA inspection/certification with the shop drawings. Certification of the above shall be received by the CO prior to shipment and installation at the job site.

Perform all sampling, testing, and inspection necessary to ensure quality control of the component materials and the concrete. Sample and test for quality control and acceptance testing in accordance with the AASHTO or ASTM test methods prescribed in Section 552.

Maintain adequate records of all inspections and tests. Keep records that indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and the nature of any corrective action taken.

Construction

553A.03 Shop Drawings. Submit ONE set of precast concrete boat ramp plank shop drawings to the

Contracting Officer at least 7 days in advance of the start of fabrication to allow time for review and correction of any changes and approval by the CO.

This is the start of the file's text. The full file is on GovTribe.