This document is a Stormwater Pollution Prevention Plan (SWPPP) template completed by the Harford County Department of Public Works for the Taylor Creek Stream Restoration project located at 555 Joppa Farm Road in Joppa, Maryland. The project involves the restoration of approximately 3,550 linear feet of main stem stream channel and tributaries within a 69.33-acre property, with a maximum of 6.15 acres expected to be disturbed during construction. The restoration effort supports the County's Total Maximum Daily Load (TMDL) goals by reducing sediment and nutrient loads from streambanks, reducing hydrograph peaks, restoring floodplain connectivity, and enhancing riparian buffer zones. Construction is estimated to commence on August 24, 2026, and conclude on February 26, 2027, with stabilization measures scheduled for March 1, 2027. The project discharges stormwater into Taylor Creek, which is listed as an impaired waterway with documented pollutants including nutrients, polychlorinated biphenyls (PCBs), and sediments within the Gunpowder River Watershed. Harford County Department of Public Works, represented by Danielle Hankins, serves as the operator, while contractor information is to be identified following competitive selection.
The SWPPP outlines comprehensive pollution prevention and stormwater management standards including dewatering practices utilizing filter bags, turbidity monitoring using an Oakton T100WL meter, and outlet protection measures. Pollutant-generating activities identified include grading, dewatering, equipment fueling and maintenance, and materials hauling, with controls including silt fence, super silt fence, double-walled fuel storage tanks, spill kits, and designated staging areas located outside the 100-year floodplain. Inspections are required every seven calendar days and within 24 hours of precipitation events exceeding 0.25 inches, with daily turbidity monitoring conducted by a third-party contractor. The plan designates Mike Davies, Chief Construction Inspector for Environmental Inspections, as responsible for site inspections and corrective actions, while authorized non-stormwater discharges include landscape irrigation, dust control water, and construction dewatering water. No chemical treatment additives or concrete washout operations are anticipated at the site, and all hazardous materials storage, spill prevention procedures, and emergency contact protocols comply with applicable Maryland Department of the Environment regulations and Harford County Hazardous Materials Law requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stormwater Pollution Prevention Plan (SWPPP) Taylor Creek Stream Restoration
Construction Stormwater Pollution Prevention Plan Template The Maryland Department of the Environment (MDE) requires construction operators to develop a Stormwater Pollution Prevention Plan (SWPPP) prior to submitting a Notice of Intent (NOI) for Construction General Permit (20-CP) coverage (Refer to Part III.F of the permit). To assist with developing a SWPPP that meets the minimum requirements of the General Permit for Stormwater Associated with Construction Activity, the Maryland Department of the Environment has provided this template.
This template is customizable to your specific project and site.
Once MDE has approved coverage for your project under the 20-CP, include your NOI, your authorization, and a copy of the 20-CP as attachments to the SWPPP.
For more information on the Tier II Checklist, the NOI in ePermits or Cationic Chemical Treatment, please navigate to our website located here:
https://mde.maryland.gov/programs/water/wwp/Pages/gp_construction.aspx
Instructions for Using the SWPPP Template Each section of the SWPPP Template includes instructions and space for your project and site information. Read the instructions for each section before you complete that section. The blue text indicates what information is to be included.
The SWPPP Template is an editable document file. You may add tables or additional text and/or delete unneeded or inapplicable fields. The information provided in each section may vary in length.
The following items may help you better prepare for completing the SWPPP:
● Make sure you read the General Permit thoroughly before you begin preparation of your SWPPP. By doing so, you are ensuring that you have a working understanding of the permit’s underlying requirements.
● Remember to complete the SWPPP prior to submitting your Notice of Intent (NOI) for permit coverage when required.
● If there is more than one construction operator or individual/entity that will be responsible for separate phases or parts of the construction for your project, consider coordinating the development of your SWPPP with the other operators or individuals/entities.
While MDE has made every effort to ensure the accuracy of all instructions contained in the SWPPP Template, it is ultimately the permit that determines the obligations of regulated construction stormwater discharges. In the event of a conflict between the SWPPP Template and any corresponding provision of the 20-CP, you must abide by the requirements in the permit. MDE welcomes feedback on the SWPPP Template. Future revisions of this document will consider all feedback.
For Construction Activities At:
555 Joppa Farm Road
Joppa, MD 21085
SWPPP Prepared For:
Harford County Department of Public Works Danielle Hankins
212 S. Bond Street Bel Air, MD 21014
410-638-3217 ext. 1176 dhankins@harfordcountymd.gov
SWPPP Prepared By:
Rebecca Oaks
212 S. Bond Street Bel Air, MD 21014
410-638-3217 ext. 1176 roaks@harfordcountymd.gov
SWPPP Preparation Date:
03/19/2026
Estimated Project Dates
Project Start Date: 08/24/2026
Project Completion Date: 02/26/2027
A SWPPP is required for your site in the following situations (Part III.F.1 of the Permit). Indicate which of these conditions apply at your site:
☒ My project is within a common plan of development and I am sharing liability between and among operators on the same site. This SWPPP clarifies Harford County’s and the Contractor’s areas of responsibility.
☐ I plan to use Chemical Additives or Polymers for Sediment Control.
☒ I have the potential for any of the non-stormwater discharges prohibited in permit Part I.D (also listed below). This may include any of these.
1. Wastewater from the Concrete Washout. (permit Part III.A.3.d).
2. Wastewater from washout and cleanout of stucco, paint, form release oils, curing compounds, and other construction materials. (permit Part III.A.3.d)
3. Fuels, oils, or other pollutants used in vehicle and equipment operation and maintenance (permit Parts III.A.3.a and III.A.3.c.iii).
4. Soaps or solvents, or detergents used in vehicle and equipment washing or external building washdown (permit Part III.A.3.b);
5. Toxic or hazardous substances from a spill or other release (also see permit Part III.A.3.c iv, III.A.3.f. and VI.J) (whether the site is known to be contaminated by PCBs, PFAS, mercury, lead, or other metals, or any other source of toxic industrial pollution); and
6. Water contaminated by toxic or hazardous substances from sites managed under Maryland's Voluntary Cleanup Program (VCP) or Land Restoration Program (LRP).
☐ I plan on implementing controls associated with the activities requiring pollution prevention measures, referenced in Part III.A.3 of the permit.
☐ None of the above, I am voluntarily creating a SWPPP for my construction activity.
Contents SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES (Part III.F.2.a of the permit)
1.1 Operator(s) / Subcontractor(s)
1.2 Stormwater Team (Part III.F.2.b of the permit)
SECTION 2: NATURE OF CONSTRUCTION ACTIVITIES (Part III.F.2.c of the permit)
2.1 Project/Site Information
2.2 Discharge Information
2.3 Description of the Construction Activities (Part III.F.2.c.i - v of the permit) 0
2.4 Sequence and Estimated Dates of Construction Activities (Part III.F.2.c.vi of the permit)
2.5 Authorized Non-Stormwater Discharges (Part III.F.2.e of the permit)
SECTION 3: DEWATERING AND USE OF CHEMICAL TREATMENT (Part III.F.2.c of the permit)
3.1 Dewatering Practices
3.2 Chemical Treatment
SECTION 4: POLLUTION PREVENTION STANDARDS (Part III.A.3 of the Permit)
4.1 Potential Sources of Pollution
4.2 Spill Prevention and Response
4.3 Fueling and Maintenance of Equipment or Vehicles (Part III.A.3.a in the Permit)
4.4 Washing of Equipment and Vehicles (Part III.A.3.b in the Permit)
4.5 Storage, Handling, and Disposal
SECTION 5: INSPECTION, MAINTENANCE, AND CORRECTIVE ACTION
5.1 Inspection Personnel and Procedures (Part III.C of the Permit)
5.2 Corrective Action (Part III.D of the Permit)
SECTION 6: TRAINING (Part III.E of the Permit)
SECTION 7: EROSION AND SEDIMENT CONTROLS (Part III.F.f.i)
7.1 Stream Protection Zone (Natural Buffers or Equivalent Sediment Controls) (Part III.F.f.ii)
7.2 Perimeter Controls (Part III.F.f.ii) .............................. Error! Bookmark not defined.
7.3 Sediment Track-Out (Part III.F.f.ii) ........................... Error! Bookmark not defined.
7.4 Site Stabilization .......................................................... Error! Bookmark not defined.
7.5 Stockpiled Sediment or Soil ..................................... Error! Bookmark not defined.
7.6 Minimize Dust ............................................................... Error! Bookmark not defined.
7.7 Minimize Steep Slope Disturbances ...................... Error! Bookmark not defined.
7.8 Topsoil ............................................................................ Error! Bookmark not defined.
7.9 Soil Compaction ......................................................... Error! Bookmark not defined.
7.10 Storm Drain Inlets .................................................... Error! Bookmark not defined.
7.11 Compliance with Other Requirements ............ Error! Bookmark not defined.
SECTION 8: CERTIFICATION AND NOTIFICATION
SECTION 9: Appendices
9.1 Amendment Log
9.2 Site Maps (Part III.F.2.d of the permit)
9.3 Sample Subcontractor Certifications/Agreements
9.4 Cationic Chemical Treatment Approval Form
9.5 Grading and Stabilization Activities Log
9.6 Rainfall Log
9.6 SWPPP Training Log
SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES (Part III.F.2.a of the permit)
1.1 Operator(s) / Subcontractor(s)
Operator(s):
Danielle Hankins 212 S. Bond Street Bel Air, MD 21014 410-638-3217 ext. 1176 dhankins@harfordcountymd.gov
Control of plans and specifications
Contractor (TBD)
Contact information will be added after selection and the SWPPP will be amended
Control of daily site construction activities NOI inspections Daily dewatering inspections Turbidity monitoring
Emergency 24-Hour Contact:
Danielle Hankins
443-862-5367
Contractor – contact information to be updated upon selection
Instructions – Identify the operator(s) who are responsible for construction activities at the site.
Indicate respective responsibilities, where appropriate.
Remember to include the project’s 24-hour emergency contact.
List subcontractors expected to work on-site.
Notify subcontractors of stormwater requirements applicable to their work.
Consider using Subcontractor Agreements. (See Appendix 9.3) List any amendments to this SWPPP in Appendix 9.1.
1.2 Stormwater Team (Part III.F.2.b of the permit)
Stormwater Team
Name and/or position, and contact Responsibilities
I Have Read the 20-CP and Understand the Applicable
Requirements
Harford County DPW Danielle Hankins
443-862-5367 dhankins@harfordcountymd.gov
Operator ☒ Yes
Date: 03/19/2026
RK&K
Rebecca Oaks, Project Manager
410-462-9275 roaks@rkk.com
SWPPP Development
☒ Yes
Date: 03/19/2026
Contractor information to be amended upon selection.
Operator Daily site work
Sitewide NOI inspections Turbidity monitoring
☐ Yes
Date: Click here to enter a date.
[Insert or delete rows as necessary.]
Instructions – Identify the project’s stormwater team.
Identify everyone by name or position.
Describe everyone’s responsibilities.
Indicate which members are responsible for inspections.
At a minimum, the stormwater team is comprised of individuals who are responsible for:
Overseeing the development of the SWPPP Any later modifications to the SWPPP Compliance with the permit requirements (i.e., installing and maintaining stormwater controls, conducting site inspections, and taking corrective actions where required)
Each member of the stormwater team must have ready access to either an electronic or a paper copy of the 20-CP and the SWPPP.
SECTION 2: NATURE OF CONSTRUCTION ACTIVITIES (Part III.F.2.c of the permit)
2.1 Project/Site Information
Project Name and Address
Project/Site Name: Taylor Creek Stream Restoration
Project Street/Location: site entrance near 555 Joppa Farm Road
City: Joppa
State: MD
ZIP Code: 21085
County or Similar Subdivision: Harford County
Business days and hours for the project: Monday-Friday 7am-4pm
Project Latitude/Longitude
Latitude: 39. 414700 º N (decimal degrees)
Longitude: - 76. 354653 º W (decimal degrees)
Latitude/longitude data source: Google Maps
☒ Map ☐ GPS ☐ Other (please specify): __________________________________________
Additional Project Information
Are you requesting permit coverage as a state or federal entity? ☐ Yes ☒ No
Have you received an assigned MDE SF number for the Erosion and Sediment Control Plan?
☐ Yes ☒ No
If yes, please provide the assigned number: N/A
Instructions – Provide basic site information.
Provide the nearest cross street if a physical address is unavailable.
The Latitude and Longitude Coordinates must be in Decimal Degrees.
2.2 Discharge Information
Does your project/site discharge stormwater into a Municipal Separate Storm Sewer System (MS4)?
☐ Yes ☒ No
Are there any waters of this State within 50 feet of your project’s earth disturbances?
☒ Yes ☐ No
Provide the Watershed Basin Code below. If your project discharges to more than one watershed, please provide all basin codes.
Gunpowder River Watershed 02-13-08-01
[Include additional rows or delete as necessary.]
Instructions – Include information relating to your site’s discharge.
List all the stormwater points of discharge from your site.
Identify each point of discharge with a unique 3-digit ID (e.g., 001, 002).
For each unique point of discharge listed, specify the name of the receiving water of this State that the stormwater directly discharges.
You may have multiple points of discharge to the same receiving water.
Specify whether any waters of this State that you discharge to are listed as impaired.
List the pollutants causing the impairment.
Identify any completed Total Maximum Daily Loads (TMDL) for any of the waters of this State that you discharge to.
List the pollutants for which there is a TMDL.
Indicate whether any water of this State that you discharge to is designated as a Tier II.
MDE SWPPP Template
Outf all ID
Name of receiving water
Is the receiving water impaired (on the
CWA
303(d) list)?
List the pollutants that are causing the impairment
Is there a completed
TMDL for this receiving waterbody
Is this receiving water designate d as a Tier
II?
Filter bags at multiple locations
Taylor Creek ☒ Yes ☐ No Nutrients, PCBs, Sediments
☒ Yes ☐ No ☐ Yes ☒ No
2.3 Description of the Construction Activities (Part III.F.2.c.i - v of the permit)
General Description of Project Provide a general description of the nature of your construction activities. For any demolition, include the dates of past renovations:
The project includes restoration of approximately 3,550 linear feet of main stem stream and its tributaries. The project will support the County’s TMDL goals by reducing sediment and nutrient loads coming from the streambanks, reduce hydrograph peaks, restore floodplain connectivity, enhance the riparian buffer, and reduce the potential for concentrated flow to impair the site.
Size of Construction Site Size of Property: 69.33 acres Total Acreage Expected to be Disturbed by Construction Activities: 6.15 acres Maximum Acreage Expected to be Disturbed at Any One Time: 1 acre. Stream channel disturbance is limited to what can be permanently stabilized within one working day.
[Repeat as necessary for individual project phases.]
Type of Construction Site (check all that apply):
☐ Single-Family Residential ☐ Multi-Family Residential ☐ Commercial ☐ Industrial
☐ Institutional ☐ Highway or Road ☐ Utility ☒ Other: Stream Restoration
Instructions – Provide a general description of the construction activities at your site.
Indicate the size of the property (in acres), the total acreage to be disturbed by the construction activities, and the maximum acreage expected to be disturbed at any one time.
Indicate the type of construction site. Include any demolition activities, and if the predevelopment land use was for agriculture.
Provide a list and description of all pollutant-generating activities.
Examples: paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations
Indicate for each activity the type of pollutant that will be generated with potential to be discharged in stormwater from your site.
Examples: sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels
Describe the construction support activities covered by this permit.
Examples: concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas
Will there be demolition of any structure built or renovated before January 1, 1980?
☐ Yes ☒ No If yes, do any of the structures being demolished have at least 10,000 square feet of floor space? ☐ Yes ☐ No ☒ N/A
Pollutant-Generating Activities (Part III.F.c.vii) ― List and describe all pollutant-generating activities. Indicate for each activity the type of pollutant that will be generated. Consider where potential spills and leaks could occur, and any known hazardous or toxic substances, such as PCBs or asbestos, which will be disturbed during construction.
Pollutant-Generating Activity (e.g., paving operations; concrete, paint, and stucco washout and waste disposal; solid waste storage and disposal; and dewatering operations)
Grading, dewatering, equipment fueling and/or maintenance
Pollutants or Pollutant Constituents
(e.g., sediment, fertilizers, pesticides, paints, caulks, sealants, fluorescent light ballasts, contaminated substrates, solvents, fuels)
Grading Sediment Dewatering Sediment Equipment fueling/maintenance Fuels, oils, lubricants, etc.
Construction Support Activities (only provide if applicable) Describe any construction support activities for the project (e.g., concrete or asphalt batch plants, equipment staging yards, material storage areas, excavated material disposal areas, borrow areas) Stockpile areas, staging areas, excavated material disposal areas
Contact information for construction support activity:
Name TO BE FILLED AFTER CONTRACTOR SELECTION Telephone number Email Address [Repeat as necessary.]
2.4 Sequence and Estimated Dates of Construction Activities (Part III.F.2.c.vi of the permit)
Phase I
Stream channel construction activities
Estimated Start Date of Construction Activities for this Phase
08/24/2026
Estimated End Date of Construction Activities for this Phase
02/26/2027
Estimated Date(s) of Application of Stabilization Measures for Areas of the Site Required to be Stabilized
03/01/2027
Estimated Date(s) when Stormwater Controls will be Removed
02/26/2027
Instructions – Describe the intended construction sequence and duration of major activities.
For each portion or phase of the construction site, include the following:
Commencement and duration of construction activities, including clearing and grubbing, mass grading, demolition activities, site preparation (i.e., excavating, cutting and filling), final grading, and creation of soil and vegetation stockpiles requiring stabilization
Temporary or permanent cessation of construction activities Temporary or final stabilization of areas of exposed soil Removal of temporary stormwater controls and construction equipment or vehicles, and cessation of any pollutant-generating activities
2.5 Authorized Non-Stormwater Discharges (Part III.F.2.e of the permit)
List of Authorized Non-Stormwater Discharges Present at the Site
Type of Authorized Non-Stormwater Discharge You are required to identify the locations of these authorized non-stormwater discharges on your site map.
Present at the construction site?
Discharges from emergency fire-fighting activities ☐ Yes ☒ No
Landscape irrigation; ☐ Yes ☒ No
Waters used to wash vehicles and equipment ☐ Yes ☒ No
Water used to control dust ☐ Yes ☒ No
Potable water including uncontaminated water line flushing (requires separate “HT” permit)
☐ Yes ☒ No
External building washdown (soaps/solvents are not used, and external surfaces do not contain hazardous substances)
☐ Yes ☒ No
Pavement wash waters ☐ Yes ☒ No
Uncontaminated air conditioning or compressor condensate ☐ Yes ☒ No
Uncontaminated, non-turbid discharges of ground water or spring water ☐ Yes ☒ No
Construction dewatering water ☒ Yes ☐ No
Instructions - Identify all authorized sources of non-stormwater discharges.
a. Discharges from emergency fire-fighting activities;
b. Landscape irrigation;
c. Water used to wash vehicles and equipment, if there is no discharge of soaps, solvents, or detergents used for such purposes;
d. Water used to control dust;
e. External building washdown, provided soaps, solvents, and detergents are not used, and external surfaces do not contain hazardous substances (as defined in Appendix A) (e.g., paint or caulk containing polychlorinated biphenyls (PCBs));
f. Pavement wash waters – if spills or leaks of toxic or hazardous substances have not occurred (unless all spill material has been removed) and where soaps, solvents, and detergents are not used. You are prohibited from directing pavement wash waters directly into any Waters of this State, storm drain inlet, or stormwater conveyance, unless the conveyance is connected to a sediment basin, sediment trap, or similarly effective control;
g. Uncontaminated air conditioning or compressor condensate;
h. Uncontaminated, non-turbid discharges of ground water or spring water;
i. Foundation or footing drains where flows are not contaminated with process materials such as solvents or contaminated ground water; and
j. Construction dewatering water discharged in accordance with Part III.A.4.
SECTION 3: DEWATERING AND USE OF CHEMICAL TREATMENT (Part III.F.2.c of the permit)
3.1 Dewatering Practices
General Filter bags will be used at the site to filter stream water that is not captured by the clear water diversion or pump-around practice. They will be installed in accordance with the approved ESC plans. Filter bags will be regularly inspected to ensure no rips or punctures in the bag and that the connections remain watertight.
Specific Dewatering Practices
Filter bag
Description: Geotextile bag through which sediment laden water is filtered
Installation Upon project start
Maintenance Requirements
Monitor bags for rips, tears, or punctures and replace bag if damaged. Ensure the dewatering hose connection to the bag is watertight. Dewater to stabilized area or suitable base per approved plans.
Outlet protection
Description: Velocity dissipator and/or outlet protection (riprap or sandbags)
Installation Upon project start
Maintenance Requirements
Outlet protection practices will be monitored to ensure that flow from the stream diversion pipe/clean water pump-around is not causing channel erosion and/or creating turbidity greater than the allowable threshold.
Turbidity Meter and Procedures
Meter: Oakton T100WL
Calibration: Calibration verification occurs prior to every use. If the calibration is more than 2% off the sample vials, a full calibration will be conducted. Procedures are outlined in the instruction manual that accompanies the meter in the carrying case. All calibration will be in accordance with manufacturer’s instructions.
Sampling: Sampling will occur at every discharge point during dewatering. A sample will be collected in a clean vessel and the sample vial will be filled to the 4/5 position. After filling, the
Instructions – Describe any dewatering practices Include a description of all dewatering practices that are installed and maintained at the construction site.
Excavations Trenches Foundations Vaults or other similar points of accumulation cap will be tightly secured. Before measuring, the sample vial should be gently shaken to produce a uniform sample. Wait until all the bubbles have disappeared and wipe the vial surface with a soft cloth to ensure the surface is dry, clean, and free of smudges. Apply 1-2 drops of silicon oil to the surface and wipe with a soft cloth to obtain an even distribution.
Place the meter on a level flat surface and insert the vial into the meter for reading.
Reporting and compliance: Turbidity sampling will be conducted by a third-party contractor.
Information will be recorded on the turbidity monitoring sheets provided by MDE in the “Turbidity Reporting” section of the SWPPP binder. If the NTU’s are above the acceptable threshold, the contractor will stop pumping and begin corrective measures. Corrective measures will be documented.
3.2 Chemical Treatment
Will this site use treatment chemicals? ☐ YES ☒ NO
SECTION 4: POLLUTION PREVENTION STANDARDS (Part III.A.3 of the Permit)
4.1 Potential Sources of Pollution
Instructions - If you are using treatment chemicals at your site, provide details in the tables below Complete the tables with all applicable requested information.
Attach copies of applicable manufacturer’s specifications regarding the use of your specific treatment chemicals and/or chemical treatment systems.
Refer to the Maryland List of Pre-Approved Flocculants available on MDE’s website.
Receive approval from the Department prior to the use of Cationic Chemicals.
Construction Site Pollutants You must consider where potential spills and leaks could occur that contribute pollutants to stormwater discharges, and any known hazardous or toxic substances, such as PCBs and asbestos that will be disturbed or removed during construction.
Pollutant-Generating Activity Pollutants or Pollutant
Constituents (that could be discharged if exposed to stormwater)
Location on Site (or reference SWPPP site map where this is shown)
Excavation and grading Sediment All areas inside LOD
Equipment refueling and maintenance
Fuels, oils, lubricants Stockpile/staging areas 100 feet from the 100-year floodplain
Dewatering operations Sediments, fuels Multiple areas within LOD
Materials hauling Sediments, fuels Active work areas, stockpile/staging areas, construction entrances
[Include additional rows as necessary.]
4.2 Spill Prevention and Response
Instructions – Describe all pollutant generating activities Identify and describe all pollutant-generating activities at your site
Paving operations Concrete Paint Stucco washout and waste disposal Solid waste storage and disposal
For each pollutant generating activity, include an inventory of pollutants or pollutant constituents associated with that activity that may be exposed to rainfall or snowmelt.
Sediment Fertilizers and/or pesticides Paints Solvents Fuels
Spill prevention and response procedures (see Part I.D.5 and Part III.A.3.c.iv of the permit). You must include the following:
o Procedures for expeditiously stopping, containing, and cleaning up spills, leaks, and other releases. Identify the name or position of the employee(s) responsible for detection and response of spills or leaks; and o Procedures for notification of appropriate facility personnel, emergency response agencies, and regulatory agencies where a leak, spill, or other release containing a hazardous substance or oil in an amount equal to or in excess of a reportable quantity consistent with Part III.A.3.f. and established under either 40 CFR 110, 40 CFR 117, or 40 CFR 302, occurs during a 24-hour period (see Part III.A.3.f). Contact information must be in locations that are readily accessible and available to all employees. You may also reference the existence of Spill Prevention Control and Countermeasure (SPCC) plans developed for the construction activity under Part 311 of the CWA, or spill control programs otherwise required by an NPDES permit for the construction activity, provided that you keep a copy of that other plan on site.
Responsible Personnel
Danielle Hankins, Operator
In the event of a spill, staff will follow the procedures listed below:
1. Identify the material, the source, and approximate quantity
2. Attend to any individuals who are injured and contact 911 for further assistance if necessary
3. Evaluate the potential for fires, explosions, etc.
4. If possible, stop the release to prevent the situation from worsening
5. Contain the spill using pads, berms, ditches, etc.
6. Evaluate if the situation is an immediate threat to the life or health of fellow employees
7. If the material has a Reportable Quantity (RQ) Requirement and the spill was in excess of the RQ amount, contact Emergency Response Agencies
8. Prevent other humans or vehicles from exposure by sectioning off the area, posting a sign, or having someone guard the area.
9. Organize those individuals trained for spill cleanup and review the situation with them. Identify any hazards they may encounter, and ensure they are using proper personal protective equipment (PPE). Ensure they follow proper cleanup, decontamination, and disposal procedures.
Dispose of contaminated absorbents and other supplies properly and decontaminate any equipment used in the cleanup process.
In the event of a discharge resulting from a spill of hazardous substances or oil from a construction site, where the release is an amount equal to or in excess of a reporting quantity, you must notify the National Response Center (NRC) at 1-800-424-8802 as soon as you have knowledge of the discharge. This is in accordance with the requirements of 40 CFR 110, 40 CFR Part 117, and 40 CFR Part 302. Reportable quantities which occur during a 24-hour period are established under 40 CFR 110, 40 CFR Part 117, or 40 CFR Part 302.
• You must notify Maryland Department of the Environment (MDE) as soon as you have knowledge of the discharge o Between 8AM and 5PM at 410-537-3510 o All other hours at 866-633-4686
• You must also, within seven (7) calendar days of knowledge of the release, provide a description of the release, the circumstances leading to the release, and the date of the release to MDE’s compliance program.
• In accordance with Harford County’s Hazardous Materials Law Article 1, Section 146: Any release of a hazardous material into the environment or a release that has the potential to enter the environment must be reported to 911 immediately. 911 Dispatchers are trained to respond based on each situation.
o Within 14 calendar days, after a release which requires notification, the responsible person shall provide a written follow-up emergency notice or notices (if more information becomes available) to the Harford County Division of Emergency Operations (HCDEO). Information will include:
Actions taken to respond to and contain the release.
Any known or anticipated acute or chronic health risks associated with the release.
Advice regarding medical attention necessary for exposed individuals, where appropriate.
Actions to be taken to mitigate potential future incidents
Actions taken in accordance with the requirements of the HCDEO
4.3 Fueling and Maintenance of Equipment or Vehicles (Part III.A.3.a in the Permit)
Fueling will take place away from floodplains. Spill kits will be available on-site to clean any leaks or spills.
Specific Pollution Prevention Practices
Spill kit
Description: A spill kit will be stored on-site in proximity to fueling operations
Installation Upon project start
Maintenance Requirements
Locate tanks outside of the 100-year floodplain. Monitor tanks and machinery for leaks or spills. Deploy spill kit as needed if a leak or spill occurs.
[Repeat as needed.]
Instructions – Describe fueling and maintenance practices Describe equipment/vehicle fueling and maintenance practices that will be implemented to eliminate the discharge of spilled or leaked chemicals
Secondary containment Spill berms Decks Spill containment pallets Spill kits
4.4 Washing of Equipment and Vehicles (Part III.A.3.b in the Permit)
No washing practices are expected to occur on-site.
4.5 Storage, Handling, and Disposal
4.5.1 Building Products (Part III.A.3.c.i in the Permit)
Instructions – Describe washing practices Describe equipment/vehicle washing practices that will be used to minimize the discharge of pollutants from equipment and vehicle washing, wheel wash water, and other types of wash waters
Locate activities away from waters of this State and stormwater inlets or conveyances Direct wash waters to a sediment basin or sediment trap Use filtration devices filter bags or sand filters Use other effective controls
Describe how you will prevent the discharge of soaps, detergents, or solvents Plastic sheeting Temporary roofs Other method of design to prevent the discharge of pollutants from these areas
Instructions – Describe storage, handling, and disposal of building products, materials, and wastes
Asphalt sealants, copper flashing, roofing materials, adhesives, concrete admixtures, gravel and mulch stockpiles
Pesticides, herbicides, insecticides, fertilizers, and landscape materials Diesel fuel, oil, hydraulic fluids, other petroleum products, and other chemicals Hazardous or toxic waste, paints, solvents, petroleum-based products, wood preservatives, additives, curing compounds, acids Construction and Domestic Waste, packaging materials, scrap construction materials, masonry products, timber, pipe and electrical cuttings, plastics, styrofoam, concrete, and other trash or building materials
Sanitary waste Describe used applicator and container washing
Paint, Concrete or Other Materials Describe pollution prevention for the use of fertilizers Describe any additional pollution prevention practices
Building materials will be stored in the stockpile/staging areas before being installed in the stream channel or stormwater facilities. All areas will be contained by silt/super silt fence.
Silt fence
Description: woven geotextile filtering fence with wooden stakes
Installation Upon project start
Maintenance Requirements
Ensure there are no rips or punctures in the geotextile material. Ensure fence remains entrenched. Repair/replace damaged sections immediately.
Super silt fence
Description: woven geotextile fence with chain-link fence and posts
Installation Upon project start
Maintenance Requirements
Ensure there are no rips or punctures in the geotextile material. Ensure fence remains entrenched. Repair/replace damaged sections immediately.
4.5.2 Pesticides, Herbicides, Insecticides, Fertilizers, and Landscape Materials (Part III.A.3.c.ii in the Permit)
Fertilizer, herbicide, insecticide, and landscape materials will be covered and stored in a manner to prevent contact with stormwater. Landscape material will be stored on site during the planting phase of the project in the stockpile areas if necessary.
4.5.3 Diesel Fuel, Oil, Hydraulic Fluids, Other Petroleum Products, and Other Chemicals (Part III.A.3.c.iii in the Permit)
Provide a general description of storage, handling and disposal of diesel fuel, oil, hydraulic fluids, other petroleum products, and other chemicals
Fuel tank
Description: Double-walled fuel storage tank
Installation Upon project start
Maintenance Requirements
Ensure tank shows no signs of damage or corrosion. Tank should be highly visible and protected with a barrier to prevent machinery collisions.
4.5.4 Hazardous or Toxic Waste (Part III.A.3.c.iv in the Permit)
No hazardous or toxic waste will be present on site.
4.5.5 Construction and Domestic Waste (Part III.A.3.c.v in the Permit)
Domestic waste associated with construction employees will be collected and removed from the site on a regular basis.
Very little construction waste will be generated with this project due to it being a restoration.
Construction waste such as grading spoils will be stored in the stockpile area and hauled off-site for disposal.
Trash bags
Description: trash bags
Installation Upon project start
Maintenance Requirements
Ensure trash is removed from site at regular intervals and disposed of properly.
Ensure bags do not have any significant rips or tears.
4.5.6 Sanitary Waste (Part III.A.3.c.vi in the Permit)
Job site toilet will be located on-site.
Porta-potty
Description: job site toilet(s)
Installation Upon project start
Maintenance Requirements
Job toilet will be located on stable, flat ground to prevent tipping. Toilet shall be located outside of 100-year floodplain. Check for leaks and ensure regular emptying occurs.
4.5.7 Washing of Applicators and Containers used for Paint, Concrete or Other Materials (Part III.A.3.d in the Permit)
No concrete washout will occur on site.
4.5.8 Fertilizers (Part III.A.3.e in the Permit)
Fertilizers and landscape materials will be covered and stored in a manner to prevent contact with stormwater. Landscape material will be stored on-site during the planting phase of the project in the stockpile areas if necessary.
4.5.9 Releases in Excess of Reportable Quantities. (Part III.A.3.f in the Permit) Discharges of hazardous substances and oil resulting from on-site spills are not authorized by this permit. (Part I.D.5). In the event of a discharge resulting from a spill of hazardous substances or oil from a construction site (Parts III.A.3.c.iii and Part III.A.3.c.iv), where the release is an amount equal to or in excess of a reporting quantity established under either 40 CFR Part 110, 40 CFR Part 117, or 40 CFR Part 302, occurring during a 24 hour period:
i. You shall notify the National Response Center (NRC) as soon as you have knowledge of the discharge in accordance with the requirements of 40 CFR Part 110, 40 CFR Part 117, and 40 CFR Part 302;
• 1-800-424-8802 or
• 202-267-2675 (in the Washington, DC metropolitan area)
ii. You shall notify the Maryland Department of the Environment as soon as you have knowledge of the discharge;
• Between 8AM and 5PM at 410-537-3510
• All other hours at (866) 633-4686 You must also, within seven (7) calendar days of knowledge of the release, provide a description of the release, the circumstances leading to the release, and the date of the release to the Department’s compliance program. Local requirements may necessitate additional reporting of spills or discharges to local emergency response, public health, or drinking water supply agencies. No condition of this general permit shall release the permittee from any responsibility or requirements under other environmental statutes or regulations.
SECTION 5: INSPECTION, MAINTENANCE, AND CORRECTIVE ACTION
5.1 Inspection Personnel and Procedures (Part III.C of the Permit)
Personnel Responsible for Inspections
Name Mike Davies
Certificate of attendance for a Responsible Personnel Training Program X Yes ☐ No ☐ N/A
4/29/2016
Has the Approval Authority waived the Certificate of Training requirement?
☐ Yes ☐ No X N/A
Inspection Schedule
Standard Frequency:
☐ Every 7 calendar days and within 24 hours of a 0.25” rain or the occurrence of runoff from snowmelt sufficient to cause a discharge ☐ Every 4 business days
☒ Daily turbidity monitoring
Increased Frequency (if applicable):
For areas of sites discharging to waters designated as Tier II.
☐ Every 4 calendar days and within 24 hours of a 0.25” rain
Rain Gauge Location (if applicable)
On-site rain gauge, if provided by contractor. Otherwise, Joppatowne Station weather station.
20-CP inspections and turbidity sampling requirements are to be satisfied by the selected contractor. Harford County grading permit inspections to be conducted by the Environmental Inspections Division.
Instructions – Describe inspection procedures Personnel Responsible Inspection schedule Record daily rainfall (See Appendix VI)
Inspection Report Forms
Standard MDE inspection forms will be used.
5.2 Corrective Action (Part III.D of the Permit)
Corrective action is dictated by the severity of the violation. Items or violations that have not resulted in sediment leaving the site are issues a minor maintenance order. If these items are not completed by the next scheduled inspection (two weeks typically), they will be escalated to a correction notice. If the correction notice is not address in the outlined time frame, a stop work order will be issues.
In a situation where large quantities of sediment are observed leaving the site due to negligence or contractors are working out of sequence/ purview of the plans, an immediate stop work order will be issues.
Personnel Responsible for Corrective Actions
Name and Title: Mike Davies, Chief Construction Inspector - Environmental Telephone number: 410-638-3217 ext. 2434 Email: mtdavies@harfordcountymd.gov Area of site responsible for: Entire Site
Corrective Action Forms
Insert a copy of any correction action forms to be used
Instructions – Describe correction action Describe the procedures for taking corrective action in compliance
SECTION 6: TRAINING (Part III.E of the Permit)
Documentation for Completion of Training
Name Describe Training Completion date Mike Davies Responsible Personnel
Training 4/29/2016
Instructions – Describe training The following personnel, at a minimum, must receive training, and therefore should be listed individually in the table below:
Personnel who are responsible for the design, installation, maintenance, and repair of stormwater controls
Personnel responsible for the application and storage of treatment chemicals Personnel who are responsible for conducting inspections Personnel who are responsible for taking corrective actions Personnel who are responsible for spill response
Personnel must be trained to understand the following if related to the scope of their job duties:
The permit deadlines associated with installation, maintenance, and removal of stormwater controls and with stabilization;
The location of all stormwater controls on the site required by this permit, and how they are to be maintained;
The proper procedures to follow with respect to the permit’s pollution prevention requirements; and
When and how to conduct inspections, record applicable findings, and take corrective actions.
Document all training.
SECTION 7: EROSION AND SEDIMENT CONTROLS (Part III.F.f.i)
Please refer to the approved erosion and sediment control plan.
General Instructions – Describe the erosion and sediment controls This section is included for your use. However, you may refer to your approved E&SC rather than list everything in this plan. Focus on areas not addressed by the E&SC.
Describe any applicable stormwater control design specifications
Include references to any manufacturer specifications and/or erosion and sediment control manuals/ordinances relied upon
Describe any routine stormwater control maintenance specifications.
Describe the projected schedule for stormwater control installation/implementation.
SECTION 8: CERTIFICATION AND NOTIFICATION
I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I have no personal knowledge that the information submitted is other than true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.
Name and Title: Danielle Hankins Administration
Signature and Date:
[Repeat as needed for multiple construction operators at the site.]
Instructions – Certification statement The following certification statement must be signed and dated by a person who meets the requirements.
This certification must be re-signed in the event of a SWPPP Modification.
SECTION 9: Appendices
9.1 Amendment Log
Use the table below to record any SWPPP Amendments.
No. Description of the Amendment Date of Amendment
Amendment Prepared by
[Name(s) and Title]
9.2 Site Maps (Part III.F.2.d of the permit)
Instructions – Attach site maps For most projects, a series of site maps is necessary and recommended.
The first should show the undeveloped site and its current features.
An additional map or maps should be created to show the developed site or, for more complicated sites, show the major phases of development.
Site maps must include the following features:
Boundaries of the property;
Locations where earth-disturbing activities will occur, noting any phasing of construction activities and any demolition activities;
Approximate slopes before and after major grading activities;
Note areas of steep slopes Locations where sediment, soil, or other construction materials will be stockpiled;
Locations of any crossings of waters of this State;
Designated points where vehicles will exit onto paved roads;
Locations of structures and other impervious surfaces upon completion of construction; and Locations of on-site and off-site construction support activity areas covered by this permit.
Locations of all waters of this State, including wetlands, on your site and within one mile downstream of the site’s discharge point.
Indicate which waterbodies are listed as impaired Indicate which are identified as Tier II waters
Areas of federally listed critical habitat for endangered or threatened species within the site and/or at discharge locations.
Type and extent of pre-construction cover on the site
Examples: vegetative cover, forest, pasture, pavement, structures Drainage pattern(s) of stormwater and authorized non-stormwater before and after major grading activities.
Stormwater and authorized non-stormwater discharge locations, including:
Locations where stormwater and/or authorized non-stormwater will be discharged to storm drain inlets; and
Locations where stormwater or allowable non-stormwater will be discharged to waters of this State (including wetlands).
Locations of all potential pollutant-generating activities.
Locations of stormwater controls, including natural buffer areas and any shared controls utilized to comply with the permit.
Locations where polymers, flocculants, or other treatment chemicals will be used and stored.
Insert Site Maps
EXAMPLES:
9.3 Sample Subcontractor Certifications/Agreements
You may use the sample below as a template to record any subcontractor agreements.
SUBCONTRACTOR CERTIFICATION
STORMWATER POLLUTION PREVENTION PLAN
Project Number:
Project Title:
Operator(s):
As a subcontractor, you are required to comply with the Stormwater Pollution Prevention Plan (SWPPP) for any work that you perform on-site. Any person or group who violates any condition of the SWPPP may be subject to substantial penalties or loss of contract. You are encouraged to advise each of your employees working on this project of the requirements of the SWPPP. A copy of the SWPPP is available for your review at the office trailer.
Each subcontractor engaged in activities at the construction site that could impact stormwater must be identified and sign the following certification statement:
I certify under the penalty of law that I have read and understand the terms and conditions of the SWPPP for the above designated project and agree to follow the practices described in the
SWPPP.
This certification is hereby signed in reference to the above-named project:
Company:
Address:
Telephone Number:
Type of construction service to be provided:
Signature:
Title:
Date:
9.4 Cationic Chemical Treatment Approval Form
Use the form found on the construction website for approval for the use of Cationic Chemical Additives: https://mde.maryland.gov/programs/water/wwp/Pages/gp_construction.aspx
When submitting for the approval of Cationic Chemical Additives, the form must be accompanied with the information contained in section 4.12 of the SWPPP. The approval authority may request additional information.
Remember that final approval from the appropriate authority must be received prior to the use of Cationic Chemical Additives.
9.5 Grading and Stabilization Activities Log
Use the table below to record any grading/stabilization activities.
Date Grading Activity Initiated
Description of Grading Activity Description of
Stabilization Measure and Location
Date Grading Activity Ceased (Temporary or Permanent)
Date When Stabilization Measures Initiated
Date Date ☐ Temporary ☐ Permanent
Date
Date Date ☐ Temporary ☐ Permanent
Date
Date Date ☐ Temporary ☐ Permanent
Date
Date Date ☐ Temporary ☐ Permanent
Date
9.6 Rainfall Log
Use the table below to record the rainfall gauge readings at the beginning and end of each workday.
Month/Year Month/Year Month/Year
Day Start time End time Day Start time End time Day Start time End time
1 1 1
2 2 2
3 3 3
4 4 4
5 5 5
6 6 6
7 7 7
8 8 8
9 9 9
10 10 10
11 11 11
12 12 12
13 13 13
14 14 14
15 15 15
16 16 16
17 17 17
18 18 18
19 19 19
20 20 20
21 21 21
22 22 22
23 23 23
24 24 24
Month/Year Month/Year Month/Year
Day Start time End time Day Start time End time Day Start time End time
25 25 25
26 26 26
27 27 27
28 28 28
29 29 29
30 30 30
31 31 31
9.6 SWPPP Training Log
You may use the sample below as a template to record specific personnel training.
Stormwater Pollution Prevention Training Log
Project Name:
Project Location:
Instructor’s Name(s):
Instructor’s Title(s):
Course Location Date Course Length (hours)
Stormwater Training Topic: (check as appropriate)
☐ Sediment and Erosion Controls ☐ Emergency Procedures
☐ Stabilization Controls ☐ Inspections/Corrective Actions
☐ Pollution Prevention Measures ☐ Other: ________________________
Specific Training Objective:
Attendee Roster:
No. Name of Attendee Company
(attach additional pages as necessary)
| SECTION 1: CONTACT INFORMATION/RESPONSIBLE PARTIES (Part III.F.2.a of the permit) |
| 1.1 Operator(s) / Subcontractor(s) |
| 1.2 Stormwater Team (Part III.F.2.b of the permit) |
| SECTION 2: NATURE OF CONSTRUCTION ACTIVITIES (Part III.F.2.c of the permit) |
| 2.1 Project/Site Information |
| 2.2 Discharge Information |
| 2.3 Description of the Construction Activities (Part III.F.2.c.i - v of the permit) |
| 2.4 Sequence and Estimated Dates of Construction Activities (Part III.F.2.c.vi of the permit) |
| 2.5 Authorized Non-Stormwater Discharges (Part III.F.2.e of the permit) |
| SECTION 3: DEWATERING AND USE OF CHEMICAL TREATMENT (Part III.F.2.c of the permit) |
| 3.1 Dewatering Practices |
| 3.2 Chemical Treatment |
| SECTION 4: POLLUTION PREVENTION STANDARDS (Part III.A.3 of the Permit) |
| 4.1 Potential Sources of Pollution |
| 4.2 Spill Prevention and Response |
| 4.3 Fueling and Maintenance of Equipment or Vehicles (Part III.A.3.a in the Permit) |
| 4.4 Washing of Equipment and Vehicles (Part III.A.3.b in the Permit) |
| 4.5 Storage, Handling, and Disposal |
| SECTION 5: INSPECTION, MAINTENANCE, AND CORRECTIVE ACTION |
| 5.1 Inspection Personnel and Procedures (Part III.C of the Permit) |
| 5.2 Corrective Action (Part III.D of the Permit) |
| SECTION 6: TRAINING (Part III.E of the Permit) |
| SECTION 7: EROSION AND SEDIMENT CONTROLS (Part III.F.f.i) |
| Please refer to the approved erosion and sediment control plan. |
| SECTION 8: CERTIFICATION AND NOTIFICATION |
| SECTION 9: Appendices |
| 9.1 Amendment Log |
| 9.2 Site Maps (Part III.F.2.d of the permit) |
| 9.3 Sample Subcontractor Certifications/Agreements |
| 9.4 Cationic Chemical Treatment Approval Form |
| 9.5 Grading and Stabilization Activities Log |
| 9.6 Rainfall Log |
| 9.6 SWPPP Training Log |