09-383804 Hot Mix Asphalt (Type A)_ Culvert Work_ and Minor Concrete.pdf
PDF 988 KB Posted
- Solicitation number
- 09-383804
- Issued by
- Kern County, Los Angeles City, California
About this file
Contract Summary
This is a Notice to Bidders and Special Provisions document issued by the California Department of Transportation (Caltrans) for Contract No. 09-383804, a highway construction project located in Inyo County near Lone Pine on State Route 395. The work encompasses hot mix asphalt (Type A), culvert replacement, and minor concrete construction extending from Locust Street to 0.2 miles north of Pangborn Lane. The project includes 92 line items with significant quantities: 14,300 tons of hot mix asphalt, 850 linear feet of culvert removal, 562 linear feet of alternative pipe culvert installation, 190 cubic yards of concrete removal, and approximately 212 cubic yards of minor concrete placement for curbs, sidewalks, and ramps. Contractors must submit electronically sealed bids by 2:00 p.m. on Thursday, October 22, 2026, with the estimated project cost of $7,600,000. Work must be completed within 90 working days. The contractor must hold either a Class A license or a C-12 Class C license as the majority work classification.
The contract requires bidders to provide security equal to at least 10 percent of their bid and comply with prevailing wage requirements as determined by the California Department of Industrial Relations. An SBE (Small Business Enterprise) participation goal of 5 percent is established; no DVBE goal is set, though DVBE participation is encouraged. Bidders may pursue optional small business or non-small business preferences with specific certification and commitment requirements. The project is subject to multiple environmental and safety requirements, including water pollution control programs, treated wood waste management, and the designation of an on-site safety representative with specific Cal/OSHA certifications and qualifications. Special provisions address traffic control restrictions during designated holidays and special days in 2026 and 2027, parking and staging locations, local material sourcing requirements with comprehensive sampling protocols, and submittal requirements for environmental product declarations for hot mix asphalt and concrete materials exceeding specified thresholds. Prompt payment requirements mandate subcontractor payment within 7 days of contractor receipt of progress payments.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids open Thursday, October 22, 2026
Dated September 14, 2026
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
NOTICE TO BIDDERS
AND
SPECIAL PROVISIONS
FOR CONSTRUCTION ON STATE HIGHWAY IN INYO COUNTY AT AND NEAR
LONE PINE FROM LOCUST STREET TO 0.2 MILE NORTH OF PANGBORN
LANE
In District 09 On Route 395
Under
Bid book dated September 14, 2026 Standard Specifications dated 2025
Project plans approved April 6, 2026 Standard Plans dated 2025
Identified by
Contract No. 09-383804
09-Iny-395-57.9/R59.0
Project ID 0919000070
SPECIAL NOTICES
See sections 2 and 3 for contractors' registration requirements.
The Department advises bidders that potential claim records must be submitted by the contractor using the Department's Internet potential claim system.
See section 2 for submittal requirements for DVBE quotes and Non–Small Business
Subcontractor Preference.
For work plan for local material from (1) a noncommercial source or (2) a source not regulated under California jurisdiction, see section 6-1.03B(2).
See section 7-1.02K(3) for the requirements for electronic submittal of certified payroll records using LCPtracker Pro.
The flagging and temporary traffic control requirements have been revised. See sections 7-
1.03, 7-1.04, and 12.
See sections 2-1.11 and 2-1.33B for in-use off-road diesel-fueled vehicle requirements regarding Certificate of Reported Compliance submittals.
See section 14-11.14 for changes to the management of treated wood waste.
See sections 1-1.06, 1-1.07B, 2-1.23, 2-1.24, 2-1.33B(3), 5-1.13D, and 5-1.13F for “Small
Business Enterprise Participation Goal Requirement” and “Small Business and Non-Small Business Subcontractor Preferences.”
See section 6-1.08 for the requirements for environmental product declarations for hot mix asphalt and concrete materials and products.
Contract No. 09-383804 i
TABLE OF CONTENTS
NOTICE TO BIDDERS
BID ITEM LIST
SPECIAL PROVISIONS
ORGANIZATION
DIVISION I GENERAL PROVISIONS
1 GENERAL
2 BIDDING
5 CONTROL OF WORK
6 CONTROL OF MATERIALS
7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
8 PROSECUTION AND PROGRESS
9 PAYMENT
DIVISION II GENERAL CONSTRUCTION
10 GENERAL
12 TEMPORARY TRAFFIC CONTROL
13 WATER POLLUTION CONTROL
14 ENVIRONMENTAL STEWARDSHIP
15 EXISTING FACILITIES
DIVISION V SURFACINGS AND PAVEMENTS
36 GENERAL
39 ASPHALT CONCRETE
DIVISION VI STRUCTURES
49 PILING
55 STEEL STRUCTURES
56 OVERHEAD SIGN STRUCTURES, STANDARDS, AND POLES
DIVISION VII DRAINAGE FACILITIES
61 GENERAL
DIVISION VIII MISCELLANEOUS CONSTRUCTION
73 CONCRETE CURBS AND SIDEWALKS
78 INCIDENTAL CONSTRUCTION
DIVISION IX TRAFFIC CONTROL DEVICES
82 SIGNS AND MARKERS
83 RAILINGS AND BARRIERS
84 MARKINGS
DIVISION X ELECTRICAL WORK
86 GENERAL
87 ELECTRICAL SYSTEMS
ii
STANDARD PLANS LIST
The standard plan sheets applicable to this Contract include those listed below. The applicable revised standard plans (RSPs) listed below are included in the project plans.
RSP A3A Abbreviations (Sheet 1 of 3)
RSP A3B Abbreviations (Sheet 2 of 3)
RSP A3C Abbreviations (Sheet 3 of 3)
A10A Legend - Lines and Symbols (Sheet 1 of 5)
A10B Legend - Lines and Symbols (Sheet 2 of 5)
A10C Legend - Lines and Symbols (Sheet 3 of 5)
A10D Legend - Lines and Symbols (Sheet 4 of 5)
A10E Legend - Lines and Symbols (Sheet 5 of 5)
A20A Pavement Markers and Traffic Lines - Typical Details
A20B Pavement Markers and Traffic Lines - Typical Details
A20D Pavement Markers and Traffic Lines - Typical Details
A24A Pavement Markings - Arrows
A24B Pavement Markings - Arrows and Symbols
A24C Pavement Markings - Symbols and Numerals
A24D Pavement Markings - Words
A24F Pavement Markings - Crosswalks
A24G Pavement Markings - Yield Lines, Limit Lines, and Wrong Way Details
A40B Shoulder Rumble Strip Details - Ground-In Indentations
A40E Rumble Strip Placement at Freeway Exit Ramps, Freeway Entrance Ramps, and Intersections
A40F Rumble Strip Placement at Intersections with Left Turn Pockets, Railroad Crossings, Private Roads, and Major Driveways
A40H Rumble Strip Placement with Gaps for Bicycles
A40L Rumble Strip Placement for Class 2 Bicycle Lane and Class 4 Bikeway
A62A Excavation and Backfill - Miscellaneous Details
A62F Excavation and Backfill - Metal and Plastic Culverts
A73A Object Markers
A73B Markers
A73C Delineators, Channelizers and Barricades
A77L2 Midwest Guardrail System - Standard Railing Section (Steel Post with Notched Wood or Notched Recycled Plastic Block)
A77M1 Midwest Guardrail System - Standard Hardware
A77N2 Midwest Guardrail System - Steel Post and Block Details iii
A77N3 Midwest Guardrail System - Typical Line Post Embedment and Hinge Point Offset Details
A77N4 Midwest Guardrail System - Typical Height Measurement, Dike Positioning, and Delineation Details
A77R3 Midwest Guardrail System - Typical Layouts for Roadside Fixed Objects
RSP A77S1 Midwest Guardrail System - End Anchor Assembly (Type SFT - M)
A77S3 Metal Railing Anchor Cable and Anchor Plate Details
A85 Chain Link Fence
A85A Chain Link Fence Details
A85B Chain Link Fence Details
A87A Curbs and Driveways
RSP A88A Curb Ramp Details
P70 Hot Mix Asphalt Paving (Longitudinal Tapered Notched Wedge Joint)
P74 Pavement Edge Treatments
P75 Pavement Edge Treatments - Overlays
D72B CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D72C CIP Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D72F CIP Drainage Inlet Notes
D72G CIP Drainage Inlet Tables
D73B Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D73C Precast Drainage Inlets - Types G1, G2, G3, G4, G5 and G6
D73F Precast Drainage Inlet Notes
D73G Precast Drainage Inlet Tables
D74 Drainage Inlet Details
D77A Grate Details No. 1
D77B Grate Details No. 2
D88 Construction Loads on Culverts
D94A Metal and Plastic Flared End Sections
D97A Corrugated Metal Pipe Coupling Details No. 1 - Annular Coupling Band, Bar and Strap, and Angle Connections
D97C Corrugated Metal Pipe Coupling Details No. 3 - Helical and Universal Couplers
D97D Corrugated Metal Pipe Coupling Details No. 4 - Hugger Coupling Bands
D97E Corrugated Metal Pipe Coupling Details No. 5 - Standard Joint
D97I Corrugated Polyvinyl Chloride Pipe with Smooth Interior - Standard and Positive Joints
H1 Landscape and Erosion Control Symbols
T1A Temporary Crash Cushion - Sand Filled (Unidirectional)
T1A1 Temporary Crash Cushion - Sand Filled (Unidirectional) iv
T1B Temporary Crash Cushion - Sand Filled (Bidirectional)
T2 Temporary Crash Cushion - Sand Filled (Shoulder Installations)
RSP T3A Temporary Railing (Type K)
T3B Temporary Railing (Type K)
T3C Temporary Barrier System (Cross Bolt)
T3D Temporary Barrier System (Cross Bolt)
T3E Temporary Barrier System (Cross Bolt)
T3F Temporary Barrier System (Cal F-23)
T3F2 Temporary Barrier System (Cal F-23)
T3G Temporary Barrier System (Staking or Anchoring)
T3G2 Temporary Barrier System (Staking or Anchoring)
T9 Traffic Control System Tables for Lane and Ramp Closures
RSP T11 Traffic Control System for Lane Closure on Multilane Conventional Highways
T11A Traffic Control System for Changeable Lane Closure on Multilane Conventional Highways and Expressways
RSP T12 Traffic Control System for Half Road Closure on Multilane Conventional Highways and Expressways
T19 Traffic Control System - Construction Work Zone Speed Limit Reduction on Conventional Highways
T20 Traffic Control System - Construction Work Zone Speed Limit Reduction Details
T21 Traffic Control System - Construction Work Zone Speed Limit Reduction Twenty- Four Hours a Day 7 Days a Week (24/7)
T30 Temporary Pedestrian Access Routes - Typical Sidewalk Closure and Pedestrian Detour
T32 Temporary Pedestrian Access Routes - Typical Sidewalk/Crosswalk Closure and Pedestrian Detour
T56 Temporary Water Pollution Control Details (Temporary Fiber Roll)
T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)
T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)
B7-11 Utility Details
RS1 Roadside Signs - Typical Installation Details No. 1
RS2 Roadside Signs - Wood Post - Typical Installation Details No. 2
RS4 Roadside Signs - Typical Installation Details No. 4
RS5 Roadside Sign-PSST Post-Typical Installation Details No. 1
RS6 Roadside Sign-PSST Post-Typical Installation Details No. 2
S89 Roadside Sign - Formed Single Sheet Aluminum Panel
S93 Framing Details for Framed Single Sheet Aluminum Signs, Rectangular Shape v
S94 Roadside Framed Single Sheet Aluminum Signs, Rectangular Shape
S95 Roadside Single Sheet Aluminum Signs, Diamond Shape
ES-1A Electrical Systems (Legend)
ES-1B Electrical Systems (Legend)
ES-1C Electrical Systems (Legend)
ES-2A Electrical Systems (Service Equipment)
ES-2E Electrical Systems (Service Equipment Enclosure and Typical Wiring Diagram, Type III - B Series)
ES-5C Electrical Systems (Accessible Pedestrian Signal and Push Button Assemblies)
ES-6B Electrical Systems (Electrolier Anchorage and Grouting for Type 15 and Type 21, Barrier Rail Mounted)
ES-7C Electrical Systems (Signal and Lighting Standard, Case 1 Signal Mast Arm Loading, Wind Velocity = 100 mph and Signal Mast Arm Lengths 15' to 30')
ES-7F Electrical Systems (Signal and Lighting Standard, Case 4 Signal Mast Arm Loading, Wind Velocity = 100 mph and Signal Mast Arm Lengths 25' to 45')
ES-7M Electrical Systems (Signal and Lighting Standard, Details No. 1)
ES-7N Electrical Systems (Signal and Lighting Standard, Details No. 2)
RSP ES-7O Electrical Systems (Signal and Lighting Standard, Details No. 3)
ES-8A Electrical Systems (Non-Traffic Pull Box)
ES-11 Electrical Systems (Foundation Installations)
ES-13A Electrical Systems (Splice Insulation Methods Details)
ES-13B Electrical Systems (Kinking and Banding Detail)
CANCELED STANDARD PLANS LIST
The 2025 standard plan sheets listed below are canceled and not applicable to this contract.
Plan No.
Date
Canceled Plan No.
Date Canceled
Plan No.
Date
Canceled
P8 04-20-26
NOTICE TO BIDDERS
Bids open Thursday, October 22, 2026
Dated September 14, 2026
General work description: Hot mix asphalt (Type A), culvert work, and minor concrete.
The Department will receive electronically sealed bids for the following work: CONSTRUCTION ON
STATE HIGHWAY IN INYO COUNTY AT AND NEAR LONE PINE FROM LOCUST STREET TO 0.2
MILE NORTH OF PANGBORN LANE.
District-County-Route-Post Mile: 09-Iny-395-57.9/R59.0
Contract No. 09-383804
The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: C-12.
The Department establishes no DVBE Contract goal but encourages bidders to obtain DVBE participation.
The SBE Contract goal is 5 percent.
Bids must be on a unit price basis.
Complete the work within 90 working days.
The estimated cost of the project is $7,600,000.
The Department will receive bids until 2:00 p.m. on the bid open date via Bid Express website. Bids received after this time will not be accepted. For more information refer to the Electronic Bidding Guide at the Office Engineer's website.
The Department will open and publicly read the bids through webcast/teleconference services immediately after the specified closing time.
For bid results go to:
https://ppmoe.dot.ca.gov/cc
Select Electronic Bidding under the Bidding tab.
District office addresses are provided in the Standard Specifications.
Present bidders' inquiries to the Department and view the Department's responses at:
https://ppmoe.dot.ca.gov/cc?id=cc_bidinquiries
Questions about alleged patent ambiguity of the plans, specifications, or estimate must be asked before bid opening. After bid opening, the Department does not consider these questions as bid protests.
Submit your bid with bidder's security equal to at least 10 percent of the bid.
Under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq., the Department gives preference to certified small businesses and non–small businesses who commit to 25 percent certified small business participation.
Under Pub Cont Code § 6107, the Department gives preference to a "California company," as defined, for bid comparison purposes over a nonresident contractor from any state that gives or requires a preference to be given to contractors from that state on its public entity construction contracts.
Prevailing wages are required on this Contract. The Director of the California Department of Industrial Relations determines the general prevailing wage rates. Obtain the wage rates at the DIR website, http://www.dir.ca.gov, or from the Department's District 6 Labor Compliance Office.
The Department has made available Notices of Suspension and Proposed Debarment from the Federal Highway Administration. For a copy of the notices, go to https://www.dir.ca.gov/dlse/debar.html.
Additional information is provided in the Excluded Parties List System at https://sam.gov/content/home.
Caltrans and the Construction Industry are committed to making partnering the way we do business. For more information, go to https://dot.ca.gov/programs/construction/partnering.
Department of Transportation
BID ITEM LIST
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0001 070030 LEAD COMPLIANCE PLAN LS LUMP SUM
0002 090100 TIME-RELATED OVERHEAD (WDAY) WDAY 90
0003 120090 CONSTRUCTION AREA SIGNS LS LUMP SUM
0004 120100 TRAFFIC CONTROL SYSTEM LS LUMP SUM
0005 120103 STATIONARY IMPACT ATTENUATOR VEHICLE DAY 10
0006 120110 FLASHING ARROW SIGN EA 2
0007 120149 TEMPORARY PAVEMENT MARKING (PAINT) SQFT 210
0008 120159 TEMPORARY TRAFFIC STRIPE (PAINT) LF 44,500
0009 120165 CHANNELIZER (SURFACE MOUNTED) EA 68
0010 120205 PORTABLE FLASHING BEACONS (EA) EA 2
0011 120207 PORTABLE RADAR SPEED FEEDBACK SIGN
SYSTEM
DAY 80
0012 124000 TEMPORARY PEDESTRIAN ACCESS ROUTE LS LUMP SUM
0013 128652 PORTABLE CHANGEABLE MESSAGE SIGN (LS) LS LUMP SUM
0014 129152 TEMPORARY RADAR SPEED FEEDBACK SIGN
SYSTEM
EA 2
0015 130100 JOB SITE MANAGEMENT LS LUMP SUM
0016 130201 WATER POLLUTION CONTROL PROGRAM LS LUMP SUM
0017 130620 TEMPORARY DRAINAGE INLET PROTECTION EA 5
0018 130640 TEMPORARY FIBER ROLL LF 250
0019 130900 TEMPORARY CONCRETE WASHOUT LS LUMP SUM
0020 131103 WATER QUALITY SAMPLING AND ANALYSIS DAY EA 2
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0021 131104 WATER QUALITY MONITORING REPORT EA 1
0022 131201 TEMPORARY CREEK DIVERSION SYSTEMS LS LUMP SUM
0023 141120 TREATED WOOD WASTE LB 2,450
0024 146007 INVASIVE SPECIES CONTROL LS LUMP SUM
0025 190101 ROADWAY EXCAVATION CY 230
0026 190185 SHOULDER BACKING TON 220
0027 194001 DITCH EXCAVATION CY 8
0028 200002 ROADSIDE CLEARING LS LUMP SUM
0029 208600 (F) - 3" PLASTIC PIPE (SCHEDULE 40) (SUPPLY
LINE)
LF 24
0030 210212 DRY SEED (SQFT) SQFT 57
0031 210610 COMPOST (CY) CY 0.4
0032 260203 CLASS 2 AGGREGATE BASE (CY) CY 310
0033 390132 HOT MIX ASPHALT (TYPE A) TON 14,300
0034 390136 MINOR HOT MIX ASPHALT TON 28
0035 394060 DATA CORE LS LUMP SUM
0036 397005 TACK COAT TON 39
0037 398200 COLD PLANE ASPHALT CONCRETE PAVEMENT SQYD 67,200
0038 510094 (F) - STRUCTURAL CONCRETE, DRAINAGE
INLET
CY 18
0039 610108 18" ALTERNATIVE PIPE CULVERT LF 52
0040 610112 24" ALTERNATIVE PIPE CULVERT LF 510
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0041 039555 STRESS REDUCING SLAB CY 38
0042 665012 12" CORRUGATED STEEL PIPE (.079" THICK) LF 150
0043 665023 24" CORRUGATED STEEL PIPE (.079" THICK) LF 10
0044 667014 28" X 20" CORRUGATED STEEL PIPE ARCH (.109"
THICK)
LF 110
0045 705311 18" ALTERNATIVE FLARED END SECTION EA 2
0046 705315 24" ALTERNATIVE FLARED END SECTION EA 2
0047 705407 28" X 20" STEEL FLARED END PIPE ARCH
SECTION
EA 1
0048 710120 REMOVE DRAINAGE FACILITY (EA) EA 7
0049 710132 REMOVE CULVERT (LF) LF 850
0050 710152 REMOVE HEADWALL EA 1
0051 730020 MINOR CONCRETE (CURB) (CY) CY 69
0052 730070 DETECTABLE WARNING SURFACE SQFT 120
0053 731502 MINOR CONCRETE (MISCELLANEOUS
CONSTRUCTION)
CY 1
0054 731516 MINOR CONCRETE (DRIVEWAY) CY 45
0055 731521 MINOR CONCRETE (SIDEWALK) CY 77
0056 731623 MINOR CONCRETE (CURB RAMP) CY 20
0057 731850 REMOVE CONCRETE (CURB, GUTTER, AND
SIDEWALK) (CY)
CY 190
0058 733000 PRE/POST CONSTRUCTION SURVEYS EA 8
0059 750001 (F) - MISCELLANEOUS IRON AND STEEL LB 1,505
0060 750010 MANHOLE FRAME AND COVER EA 5
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0061 780258 ADJUST MANHOLE FRAME AND COVER
(UTILITY)
EA 1
0062 780433 PAINT CURB (2-COAT) SQFT 360
0063 016204 FLAGPOLE SLEEVE EA 3
0064 800310 CHAIN LINK FENCE (TYPE CL-3.5) LF 250
0065 803020 REMOVE FENCE LF 280
0066 810130 REMOVE DELINEATOR EA 30
0067 810180 DELINEATOR (CLASS 2) EA 30
0068 810190 GUARD RAILING DELINEATOR EA 4
0069 820110 MILEPOST MARKER EA 1
0070 820112 MARKER (CULVERT) EA 12
0071 820250 REMOVE ROADSIDE SIGN EA 32
0072 820510 RESET ROADSIDE SIGN (ONE POST) EA 3
0073 037364 ROADSIDE SIGN (TURNABLE METAL POST) EA 1
0074 820750 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.063"-UNFRAMED)
SQFT 340
0075 820760 FURNISH SINGLE SHEET ALUMINUM SIGN
(0.080"-UNFRAMED)
SQFT 150
0076 820840 ROADSIDE SIGN - ONE POST EA 34
0077 820860 INSTALL SIGN (STRAP AND SADDLE BRACKET
METHOD)
EA 12
0078 820900 INSTALL ROADSIDE SIGN PANEL ON EXISTING
POST
EA 3
0079 832006 MIDWEST GUARDRAIL SYSTEM (STEEL POST) LF 150
0080 839580 END ANCHOR ASSEMBLY (TYPE SFT-M) EA 1
Item No.
Item Code Item Description Unit of Measure Estimated Quantity
0081 015299 ALTERNATIVE IN-LINE TERMINAL TL-3 EA 1
0082 839760 SALVAGE GUARDRAIL (STEEL POST) LF 120
0083 846051 12" RUMBLE STRIP (ASPHALT CONCRETE
PAVEMENT)
STA 39
0084 847128 6" METHYL METHACRYLATE PAINT TRAFFIC
STRIPE
LF 34,300
0085 847136 6" METHYL METHACRYLATE PAINT TRAFFIC
STRIPE (BROKEN 17-7)
LF 3,790
0086 847138 6" METHYL METHACRYLATE PAINT TRAFFIC
STRIPE (BROKEN 36-12)
LF 10,100
0087 847140 6" METHYL METHACRYLATE PAINT TRAFFIC
STRIPE (BROKEN 8-4)
LF 600
0088 847142 8" METHYL METHACRYLATE PAINT TRAFFIC
STRIPE
LF 1,230
0089 847148 METHYL METHACRYLATE PAINT TRAFFIC
STRIPE CROSSWALK AND PAVEMENT MARKING
SQFT 1,590
0090 870009 MAINTAINING EXISTING TRAFFIC MANAGEMENT
SYSTEM ELEMENTS DURING CONSTRUCTION
LS LUMP SUM
0091 037568 RECTANGULAR RAPID FLASHING BEACON
SYSTEMS
LS LUMP SUM
0092 999990 MOBILIZATION LS LUMP SUM
SPECIAL PROVISIONS
ORGANIZATION
Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.
Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.
Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.
DIVISION I GENERAL PROVISIONS
1 GENERAL
Add to section 1-1.01:
Bid Items and Applicable Sections
Item code
Item description Applicable section
039555 STRESS REDUCING SLAB 61
016204 FLAGPOLE SLEEVE 78
037364 ROADSIDE SIGN (TURNABLE METAL POST) 82
015299 ALTERNATIVE IN-LINE TERMINAL TL-3 83
037568 RECTANGULAR RAPID FLASHING BEACON SYSTEMS 87
Add to the table in the 1st paragraph of section 1-1.06:
SBE Small Business Enterprise
Add to section 1-1.07B:
small business enterprise: Small business or small business for the purpose of public works, as certified by the Department of General Services, Office of Small Business and DVBE Services, and as defined in Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.
2 BIDDING
Add between the 1st and 2nd paragraphs of section 2-1.06B:
The Department makes the following supplemental project information available:
Supplemental Project Information
Means Description Included in the Information Handout 1. California Department of Fish and Wildlife Notification
No. EPIMS-INY-60408-R6
2. Lahontan Regional Water Quality Control Board WDID No. 6B142508003
3. 401 Permit Application
4. LADWP Right of Entry
5. Existing Traffic Management System Element Locations
6. Smoothness Profile Data Reference Points
7. Final Report - Utilization of Small Business Enterprises
Available as specified in the Standard Specifications
1. Digital Terrain Model in XML
2. Design alignments in XML
3. Existing Smoothness Profile Data Files in PPF format
Replace section 2-1.23 with:
2-1.23 SMALL BUSINESS ENTERPRISE PARTICIPATION GOAL REQUIREMENT
2-1.23A General
Section 2-1.23 applies if an SBE participation goal requirement is shown on the Notice to Bidders.
The SBE participation goal requirement is in addition to any DVBE goal shown on the Notice to Bidders and the DVBE requirements in section 2-1.22.
Make work available to SBEs and select work parts consistent with the available SBEs, including subcontractors, suppliers, service providers, and truckers.
Meet the SBE participation goal requirement shown on the Notice to Bidders. A bid that demonstrates an SBE participation commitment less than the SBE participation goal requirement is nonresponsive.
Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
The Department of General Services determines whether an SBE was certified on the bid opening date.
The Department of Transportation confirms an SBE’s certification status.
2-1.23B SBE Submittals
Submit SBE information under section 2-1.33.
For the SBE participation goal requirement, submit the following:
1. Completed Small Business Enterprise – Commitment form. Failure to submit the completed form by 4 p.m. on the 4th business day after bid opening may result in a nonresponsive bid.
2. Copy of the quote for each SBE shown on the Small Business Enterprise – Commitment form that describes the type and dollar amount of work shown on the form. Quotes are not required for work that will be completed by SBE prime bidders. Failure to submit a copy of the quote for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.
3. Completed Small Business Enterprise – Confirmation form from each SBE listed on the Commitment form. The form for each SBE is required to establish that the SBE will be participating in the Contract for the type and dollar amount of work shown on the form. Failure to submit completed Confirmation forms for each SBE listed on the Commitment form by 4 p.m. on the 4th business day after bid opening may result in disallowance of the SBE’s participation.
4. If an SBE is participating as a joint venture partner, submit a copy of the joint venture agreement.
The Department may contact you and SBEs to clarify quotes and supporting documentation.
If you elect, at time of bid, to pursue the optional small business or non-small business preference, see section 2-1.24 for the requirements arising from your request for the preference. SBE participation listed to meet the SBE participation goal requirement should not be listed for the preference.
Replace section 2-1.24 with:
2-1.24 SMALL BUSINESS AND NON–SMALL BUSINESS SUBCONTRACTOR PREFERENCES
2-1.24A General
Section 2-1.24 applies to a non-federal-aid contract.
The Department applies small business preferences and non–small business preferences under Govt Code § 14835 et seq. and 2 CA Code of Regs § 1896 et seq.
Any contractor, subcontractor, supplier, or service provider who qualifies as a small business or small business for the purpose of public works is encouraged to apply for certification as an SBE by submitting its application to the Department of General Services, Office of Small Business and DVBE Services.
The Department of General Services determines whether an SBE was certified on the bid opening date.
The Department of Transportation confirms an SBE’s certification status before applying the small business or non-small business preference.
Contract award is based on the total bid, not the reduced bid.
Pursuant to Govt Code § 14838, SBE participation listed on the Small Business Enterprise – Commitment form used to meet the SBE participation goal requirement should not be listed on the Certified Small Business Listing for the Non-Small Business Preference form. Listing the same SBE participation on both the Small Business Enterprise – Commitment form and on the Certified Small Business Listing for the Non-Small Business Preference form may result in disallowance of the SBE’s participation toward the small business or non-small business preference.
2-1.24B Small Business Preference
The Department allows a bidder certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, a preference if:
1. Bidder submitted a completed Request for Small Business Preference or Non–Small Business Preference form with its bid
2. Low bidder did not request the preference or is not certified as a small business
The Bidder's signature on the Request for Small Business Preference or Non–Small Business Preference form certifies that the Bidder is certified as an SBE at the date and time of bid or has submitted a complete application to the Department of General Services. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
The small business preference is a reduction for bid comparison in the total bid submitted by the small business contractor by the lesser of the following amounts:
1. 5 percent of the verified total bid of the low bidder
2. $50,000
If the Department determines that a certified small business bidder is the low bidder after the application of the small business preference, the Department does not consider a request for non–small business preference.
2-1.24C Non–Small Business Subcontractor Preference
At time of bid, the Department allows a bidder not certified as an SBE by the Department of General Services, Office of Small Business and DVBE Services, the option of requesting the non-small business subcontractor preference. If a bidder elects to pursue that option at the time of bid, the bidder is required to meet the corresponding commitment.
For the non-small business subcontractor preference, submit the following:
1. Completed Request for Small Business Preference or Non–Small Business Preference form with your bid
2. Completed Certified Small Business Listing for the Non–Small Business Preference form which shows you are subcontracting at least 25 percent to certified SBEs
Each listed SBE must be certified as a small business or small business for the purpose of public works by 5:00 p.m. on the bid opening date. The complete application and any required substantiating documentation must be received by the Department of General Services by 5:00 p.m. on the bid opening date.
Failure to submit a completed Certified Small Business Listing for the Non–Small Business Preference form by 4 p.m. on the 4th business day after bid opening will result in a nonresponsive bid.
The non–small business subcontractor preference is a reduction for bid comparison in the total bid submitted by the non–small business contractor requesting the preference by the lesser of the following amounts:
1. 5 percent of the verified total bid of the low bidder
2. $50,000
Replace the table in the 1st paragraph of section 2-1.33B(3)(b)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract with a DVBE Goal Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa
Time of bid
Certified DVBE Summary No later than 4 p.m. on the 4th business day after bid opening
California Company Preference Time of bid
Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening
Request for Small Business Preference or Non– Small Business Preferencea
Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
Replace the table in the 1st paragraph of section 2-1.33B(3)(c)(ii) with:
Bid Form Submittal Schedule for a Non-Federal-Aid Contract without a DVBE Goal Form Submittal deadline
Bid to the Department of Transportation Time of bid except for the public works contractor registration number for a joint-venture contract
For a joint-venture contract, copy of the Bid to the Department of Transportation as submitted at the time of bid with the public works contractor registration number
10 days after bid opening
Subcontractor List Time of bid In-Use Off-Road Diesel-Fueled Vehicle List 10 days after bid opening Small Business/DVBE/DBE Certification Status Time of bid Opt Out of Payment Adjustments for Price Index Fluctuationsa
Time of bid
California Company Preference Time of bid
Certified DVBE Summaryb No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Commitment No later than 4 p.m. on the 4th business day after bid opening
Small Business Enterprise – Confirmation No later than 4 p.m. on the 4th business day after bid opening
Request for Small Business Preference or Non– Small Business Preferencea
Time of bid
Certified Small Business Listing for the Non– Small Business Preferencea
No later than 4 p.m. on the 4th business day after bid opening aSubmit only if you choose the option or preference.
bSubmit only if you obtain DVBE participation or you are the apparent low bidder, 2nd low bidder, or 3rd low bidder and you choose to receive the specified incentive.
5 CONTROL OF WORK
Replace section 5-1.13D with:
5-1.13D Non-Small Business Preference
5-1.13D(1) General
Section 5-1.13D applies to a non-federal-aid contract when you have obtained a non-small business subcontractor preference under section 2-1.24.
Use each SBE as shown on the Certified Small Business Listing for the Non-Small Business Preference form unless you receive authorization for a substitution under section 5-1.13D(3).
Maintain records of subcontracts and agreements made with each SBE. Include in the records:
1. SBE subcontract or agreement
2. Name and business address of each business
3. Proof of each payment made to an SBE
Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:
1. Interviewing employees.
2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.
Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.
5-1.13D(2) Commercially Useful Function
SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Certified Small Business Listing for the Non-Small Business Preference form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the non-small business preference if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.
Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.
Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:
1. Subcontract or agreement with the SBE
2. Purchase orders
3. Bills of lading
4. Invoices
5. Proof of payment
You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:
1. Proof of ownership or lease and rental agreements for equipment
2. Tax records
3. Employee rosters
4. Certified payroll records
5. Inventory rosters
Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.
Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
5-1.13D(3) Substitutions
Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.
The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.
Include in your substitution request:
1. Copy of the written notice issued to the SBE with proof of delivery
2. Copy of the SBE response to the notice
3. Your explanation of the reason for the substitution request
4. Names and certification numbers of the listed SBE and the proposed substitute SBE
5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform
6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that non-small business preference portion of the Contract will be fulfilled
Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.
If the Department authorizes your SBE substitution request, it will do so in writing.
Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
Replace section 5-1.13E with:
5-1.13E Prompt Payment
Section 5-1.13E applies to all contracts.
Pay your subcontractors within 7 days of receipt of each progress payment under Pub Cont Code §§ 10262 and 10262.5. Pay duly authorized motor carriers of property in dump trucks for transportation charges under Bus & Prof Code § 7108.6. Pay other entities, such as material suppliers, within 30 days of receipt of each progress payment.
Each month, after the 15th and prior to 20th, submit the following payment information through the Department’s prompt payment monitoring system at https://caltrans.dbesystem.com:
1. Subcontractor’s or entity’s business name
2. Description of work performed
2.1. Bid item numbers or change order numbers
2.2. Written narrative of work performed
3. Value of work performed
4. Amount paid to subcontractor or entity
5. Withhold amount, if applicable
6. Explanation of withhold reasoning, if applicable
Your subcontractors and other entities may validate payments received using the prompt payment monitoring system.
If a subcontractor’s or other entity’s work is in dispute, provide a written withhold notification to the subcontractor or entity and the Engineer no later than 7 days after receipt of the corresponding progress payment that includes the following:
1. Value of the disputed work
2. Amount of the withhold being taken
3. Bid item numbers or change order numbers associated with the disputed work
4. Explanation of the deficiencies of the disputed work and how the corresponding value was calculated
5. Corrective actions to be taken for release of withheld amount
The Department may request additional documentation from you to evaluate whether you applied the withhold in good faith. Submit requested documents within 10 days of receipt of request.
The Department may withhold the same amount of your withhold from a future progress pay estimate if the Department determines any of the following has occurred:
1. Withhold was not applied in good faith
2. Requested additional withhold documentation records were not provided
3. Payment information was not submitted through the prompt payment monitoring system
4. Required withhold notification was not provided
The Department may also apply a 2 percent penalty on the withhold amount for every month payment is not made.
Replace section 5-1.13F with:
5-1.13F Small Business Enterprise Participation Goal Requirement
5-1.13F(1) General
Section 5-1.13F applies to a non-federal-aid contract if an SBE participation goal requirement is shown on the Notice to Bidders.
Use each SBE as shown on the Small Business Enterprise – Commitment form unless you receive authorization for a substitution under section 5-1.13F(3).
Maintain records of subcontracts and agreements made with each SBE. Include in the records:
1. SBE subcontract or agreement
2. Name and business address of each business
3. Proof of each payment made to an SBE
Upon reasonable notice and during normal business hours, permit access to the SBE premises for the purpose of:
1. Interviewing employees.
2. Inspecting and copying books, records, accounts, and other material that may be relevant to a matter under investigation.
Upon work completion, complete a Final Report – Utilization of Small Business Enterprise form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the SBE work amount or $10,000 until the form is submitted. The Department releases the withhold upon submission of the completed form. If additional payments are made to an SBE after submittal of the completed form, submit an updated form to reflect such payments.
5-1.13F(2) Commercially Useful Function
SBEs must perform a commercially useful function under 2 CA Code Regs § 1896.15 when performing tasks listed on the Small Business Enterprise – Commitment form and as a Department authorized substitute SBE. The SBE’s value of work will only count toward the SBE participation goal requirement if the SBE performs a commercially useful function under 2 CA Code Regs § 1896.15.
Provide written notification to the Engineer at least 15 days in advance of each SBE’s initial performance of work on the Contract. Include the SBE’s name, contract work to be performed, and the location, date, and time of where the SBE’s work will take place.
Monitor each SBE’s performance of a commercially useful function throughout their duration of work on the Contract. Maintain supporting documentation of commercially useful function related records. Provide copies of the following to the Department within 5 business days of a specific SBE request:
1. Subcontract or agreement with the SBE
2. Purchase orders
3. Bills of lading
4. Invoices
5. Proof of payment
You and your SBEs must submit any commercially useful function related records and documents within 5 business days of Department request such as:
1. Proof of ownership or lease and rental agreements for equipment
2. Tax records
3. Employee rosters
4. Certified payroll records
5. Inventory rosters
Notify the Engineer immediately if you believe an SBE may not be performing a commercially useful function.
Failure to submit requested records and documents, or failure of an SBE to perform a commercially useful function, will be a violation of these specifications. Such violations will result in referral to the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
5-1.13F(3) Substitutions
Substitution of an SBE may be requested for the reasons listed in Pub Cont Code § 4107. The Department will consider your SBE substitution request under 2 CA Code Regs § 1896.10. The substitute must be another SBE.
The requirement that an SBE be certified by the bid opening date does not apply to SBE substitutions after contract award.
Include in your substitution request:
1. Copy of the written notice issued to the SBE with proof of delivery
2. Copy of the SBE response to the notice
3. Your explanation of the reason for the substitution request
4. Names and certification numbers of the listed SBE and the proposed substitute SBE
5. Description of the work to be performed including dollar amount or percentage of overall contract the proposed substitute SBE will perform
6. If an SBE substitution cannot occur, written justification and the steps that were taken to try to acquire a new SBE and how that SBE participation goal requirement portion of the Contract will be fulfilled
Upon receipt of the substitution request, the listed SBE will be notified by the Department of the substitution request. The listed SBE will have 5 business days to respond. Where the listed SBE objects to the substitution, the Department will schedule a hearing.
If the Department authorizes your SBE substitution request, it will do so in writing.
Work performed by a firm other than the listed SBE or authorized substitute will be a violation of these specifications. Such violations will result in notification of the Department of General Services, and you may be subject to sanctions under Govt Code § 14842 et seq.
Replace section 5-1.15 with:
5-1.15 SAFETY REPRESENTATIVE
5-1.15A General
Designate an on-site safety representative to superintend project safety for the duration of this Contract.
The safety representative may perform other non-safety related work if safety responsibilities are fulfilled.
The safety representative must be available after work hours as needed. The safety representative is not required to be on-site during plant establishment period, erosion control establishment period, or temporary suspensions when no other Contract work is being performed.
Develop a written site-specific safety program (SSSP) that incorporates known hazards associated with the project.
5-1.15B Submittals
Submit a resume of the safety representative before starting work on the project, including education, completed safety training, and safety experience in heavy construction, heavy industrial, or oil and energy industry.
Submit a copy of the safety representative's certificate for the Cal/OSHA 30-hour – Cal/OSHA Standards for the Construction Industry or OSHA 510 - OSHA Standards for the Construction Industry training course as an informational submittal. The certificate must include:
1. Name of the entity providing certification
2. Name of the individual receiving certification
3. Date when the certification was provided
4. Expiration date, if applicable
Submit a copy of the SSSP as an informational submittal:
1. At least 15 days before starting work
2. At least 48 hours before starting work whenever a revision is made to the SSSP
5-1.15C Certifications
The safety representative must have completed training and received a certificate of completion for the Cal/OSHA 30-hour - Cal/OSHA Standards for the Construction Industry or OSHA 510 – OSHA Standards for the Construction Industry training course.
The safety representative must have one of the following certifications:
1. Certified Safety Professional from the Board of Certified Safety Professionals
2. Construction Health and Safety Technician from the Board of Certified Safety Professionals
3. Occupational Hygiene and Safety Technician from the Board of Certified Safety Professionals
4. Safety Trained Supervisor from the Board of Certified Safety Professionals
5. Safety Trained Supervisor Construction from the Board of Certified Safety Professionals
6. Associate Safety Professional from the Board of Certified Safety Professionals
7. Master Safety Professional from the National Association of Safety Professionals
8. Certified Safety Director from the National Association of Safety Professionals
5-1.15D Qualifications
The safety representative must be a competent and qualified person, as defined by Cal/OSHA, and must provide safety oversight on the project. The safety representative must have:
1. At least 3 years of safety experience in heavy construction, heavy industrial, or oil and energy industry
2. Knowledge in the area of safety procedure for all types of work being performed on this project
3. Knowledge of Department specifications and plans, Cal/OSHA policy and procedures, and 8 CA
Code of Regs safety requirements
The safety representative must have completed safety training and maintain valid certifications for:
1. First aid
2. Cardiopulmonary resuscitation
5-1.15E Duties and Responsibilities
The safety representative must be available by:
1. Cellular telephone
2. Two-way radio
3. Mobile internet access
The safety representative must:
1. Develop the SSSP
2. Conduct the on-site new project orientation for each worker assigned to the project
3. Review the construction work plans for each subcontractor before starting work
4. Conduct or attend pre-planning sessions for high hazard work such as excavations, demolition, confined space entry, falsework, crane hoisting, high-risk utilities such as high-pressure pipelines with fuel or natural gas, and tunneling or boring
5. Conduct weekly job site safety meetings
6. Review work schedules, including subcontractors' work schedules, to ensure adequacy of job hazard analyses and address all safety concerns and issues
7. Ensure safety data sheets are available on-site for all materials and have a hazard communication program for informing workers of material hazards
8. Verify compliance with hazardous waste requirements under section 14-11, including spill prevention and control measures
9. Conduct daily safety inspections of the job site for hazards and compliance with safety requirements in the specifications and 8 CA Code of Regs
10. Report all incidents to the Engineer immediately, including the investigation of any close calls
When monitoring the job site, including work zones with certified flaggers or traffic control technicians, take immediate corrective action and notify the Engineer if an imminent danger is identified.
If the Engineer determines the safety representative is not meeting the intended duties and responsibilities, you must replace the safety representative within 30 days of written notice from the Engineer. If you need to replace the safety representative, notify the Engineer and provide replacement safety representative resume and required certifications at least 15 days before the replacement.
You may submit a secondary safety representative to act on behalf of the designated safety representative during extended shifts, continuous operations, or short-term absences that will not exceed 14 days in duration. The secondary safety representative must meet the same required qualifications and certifications as the designated safety representative.
Add to the end of section 5-1.20A:
During the progress of the work under this Contract, work under the following contracts may be in progress at or near the job site of this Contract:
Coincident or Adjacent Contracts
Contract no. County–Route–Post Mile Location Type of work 09-374504 Iny-395-56.8/R58.3 Lone Pine Construct Sidewalk
Coordinate lane closures and traffic handling with the Engineer and with contractors of coincident or adjacent projects. Potential conflicts may not be limited to the contracts listed above.
Add to section 5-1.32:
The locations in the following table meet environmental compliance for parking, staging and stockpiling:
County-Route Post Mile Side of Highway
Description of Area
Iny-395 56.1 Southbound Caltrans Maintenance Yard in Lone Pine:
Contact: Ryan Lane
(760) 937-3301
Iny-395 58.1 Southbound Dirt shoulder Sta 233+50 - Sta 237+50
Iny-395 58.6 Southbound Paved shoulder Sta 258+00 - Sta 264+00
Iny-395 58.9 Northbound Paved shoulder Sta 275+00 - Sta 284+00
Add to the end of section 5-1.32:
Personal vehicles of your employees must not be parked on the traveled way or shoulders, including sections closed to traffic.
6 CONTROL OF MATERIALS
Replace section 6-1.03B with:
6-1.03B Submittals
6-1.03B(1) General
Not Used
6-1.03B(2) Work Plan
For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:
1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:
I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).
2. Land use history of the local material location and surrounding property
3. Sampling protocol
4. Number of samples per volume of local material
5. QA and QC requirements and procedures
6. Qualifications of sampling personnel
7. Stockpile history
8. Name and…