06168H-Project Manual-Opera House-Lighting Equipment.pdf
PDF 9 MB Posted
- Attached to
- Lancaster Opera House Lighting Equipment
- Solicitation number
- 2138896
- Issued by
- Erie County, New York
About this file
This is a Project Manual and Bid Documents package for the Town of Lancaster, Erie County, New York, for the design, supply, and installation of lighting equipment at the Lancaster Opera House located at 21 Central Avenue, Lancaster, New York. The project consists of a complete theatrical lighting control system including lighting fixtures, controls equipment, and installation services. Bids were to be received at the Town Clerk's office until Wednesday, September 30, 2026 at 10:00 AM local time, with public opening and reading of bids at that same time. Bidding documents were available beginning Tuesday, September 9, 2026 at 9:00 AM through the issuing office of Wm. Schutt Associates. The project completion timeline specifies 90 days from the effective date of the contract. Only official plan holders are permitted to bid on the project, and all bidders must be registered with the New York State Department of Labor and submit proof with their bid.
The bid structure divides the work into three distinct divisions: Division A for Lighting Fixture Procurement, Division B for Lighting Controls Procurement, and Division C for Installation on a separate time and material basis. The bid form includes a lump sum item for the Lighting System with a contingency allowance of $10,000. Liquidated damages are established at $750.00 per day for each day of delay beyond the 90-day completion period. Contract payment will be made monthly based on the percentage of actual work completed as agreed with the Engineer, with five percent retainage until substantial completion. The contract is funded wholly or partially with state funds and is subject to state policy encouraging minority and women business enterprise participation. All bidders must provide performance and payment bonds equal to the contract price, and comprehensive insurance including workers' compensation, general liability, automobile liability, and pollution liability with minimum coverage amounts specified in the contract documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Manual
Lancaster Opera House Lighting Equipment
Town of Lancaster Erie County, New York
August 2026
Town of Lancaster Town Hall
21 Central Avenue Lancaster, New York 14086
Lancaster Opera House
Lighting Equipment
Town of Lancaster
Erie County, New York
August 2026
Supervisor Robert Leary
Councilmembers Thomas Antic°la
Dawn Schroeder
Melissa Studley
Mark Burkard
WARNING
It is a violation of Section 7209, subdivision 2, of the New York State Education Law for any person, unless acting under the direction of a licensed Professional Engineer or Land Surveyor, to alter in any way any plans, specifications, or reports to which the seal of a Professional Engineer or Land Surveyor has been applied.
Prepared by:
Wm. Schutt Associates 37 Central Avenue
Lancaster, New York 14086
TABLE OF CONTENTS
Town of Lancaster
Erie County, New York
Lancaster Opera House Lighting Equipment
Advertisement For Bids
Bid Form
Performance Bond
Contract
Appendices
A Lighting Fixture & Controls Procurement Requirements & Technical Design Manual B Included Control Devices
C Included Fixture Types
D Prevailing Rate
E Insurance Requirements
Table of Contents
ADVERTISEMENT FOR BIDS
TOWN OF LANCASTER
ERIE COUNTY, NEW YORK
Lancaster Opera House
Lighting Equipment
21 Central Avenue
General Notice
The Town of Lancaster is requesting Bids for the construction of the following Project:
Lancaster Opera House
Lighting Equipment
21 Central Avenue
Bids for the design, supply and installation of Lighting Equipment will be received at the office of the
Town Clerk, 21 Central Avenue, Lancaster, New York 14086 until Wednesday, September 30, 2026 at
10:00 AM local time. At that time the Bids received will be publicly opened and read.
The Project consists of design, supply and installation of Lighting Equipment in the Town of Lancaster Opera House.
Obtaining the Bidding Documents
The Issuing Office for the Bidding Documents is the offices of Wm. Schutt Associates. Copies of the
Bidding Documents may be obtained from the Issuing Office as described below. Partial sets of Bidding
Documents will not be available from the Issuing Office. Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including addenda, if any, obtained from sources other than the Issuing Office.
Beginning at 9:00 AM, on Tuesday September 9, 2026 if bidders wish to obtain printed copies of the
Contract Documents, they must be obtained through the issuing office. Only official plan holders will be allowed to bid on the project. Bidders acknowledge that they are responsible for review of all components of the Contract Documents, including all specification sections and drawings, regardless of how many drawings they print and in which format/size they are printed.
Instructions to Bidders.
ALL BIDDERS MUST BE REGISTERED WITH NEW YOUR STATE DEPARTMENT OF LABOR AND SUBMIT PROOF WITH BID. For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents. This contract will be funded wholly or partially with state funds, and as such, is subject to all state rules and regulations pertinent thereto, including, but not limited to, state policy of encouraging the participation of minority and women business enterprises as sources of suppliers, equipment, construction and services.
This Advertisement is issued by:
Owner: Town of Lancaster, New York
By: Andrea Crage Title: Town Clerk
Date: Tuesday September 8, 2026
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
NON-COLLUSIVE BIDDING CERTIFICATE
By submission of this Bid the undersigned, Bidder or person signing on behalf of the Bidder, certifies under the penalty of perjury that to the best of knowledge and belief:
(1) The prices in this Bid have been arrived at independently without collusion, consultations, communication, or agreement, for the purpose of restricting competition, as to any matter relating to such prices with any other Bidder or with any competitor;
(2) Unless otherwise required by law, the prices which have been quoted in this Bid have not knowingly disclosed by the Bidder prior to opening, directly or indirectly, to any other Bidder or to any competitor; and
(3) No attempt has been made or will be made by the Bidder to induce any other person, partnership or corporation to submit or not to submit a Bid for the purpose of restricting competition.
Attached hereto (if a corporate bidder) is a certified copy of resolution authorizing the execution of this certificate by the signatory of this Bid in behalf of the corporate Bidder.
Dated:
Bidder:
By:
Title:
Signature:
WAIVER OF IMMUNITY CERTIFICATION
This is to certify that neither the undersigned nor any member, partner, director, or officer of the firm has refused to sign a waiver of immunity against subsequent criminal prosecution or to answer any relevant question concerning a transaction or contract with the state, any political division thereof, a public authority or with a public department, agency or official of the state or of any political subdivision thereof or of a public authority, when called before a grand jury, head of a state department, temporary state commission, or other state agency, the organized crime task force in the department of law, head of a city department, or other city agency, which is empowered to compel the attendance of witnesses and examine them under oath.
By:
Signature:
Title:
Business Name:
Business Address:
(SEAL - if Bid is by a corporation)
BID FORM
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders.
ARTICLE 1—OWNER AND BIDDER
1.01 This Bid is submitted to the Town of Lancaster, Town Hall, 21 Central Avenue, Lancaster, New York 14086 for the Opera House Lighting System.
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2—ATTACHMENTS TO THIS BID
2.01 The following documents are submitted with and made a condition of this Bid:
A. Certified copy of Board of Directors' Resolution authorizing bid (if Bidder is a Corporation).
B. Non-Collusive Bidding Certificate; and
C. Waiver of Immunity.
ARTICLE 3—BASIS OF BID—UNIT PRICES AND LUMP SUMS
3.01 Bid Items
A. Bidder will perform the following Work at the indicated prices:
Bid
Item Description Unit
Estimated
Quantity
Fixed
Price Bid Price Bid Amount
1 Lighting System LS 1 $ $
2 Contingency Allowance LS 1 - $10,000 $10,000
B. Bidder acknowledges that:
1. Each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor's overhead and profit for each separately identified item, and
2. Estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.
°CDC® C-410, Bid Form for Construction Contract.
Copyright o 2018 National Society of Professional Engineers, American Council of Engineering Companies, C. Fixed minimum unit prices may have been established for some of the items in the Bid. The prices represent the minimum amounts, which will be paid the CONTRACTOR for these items.
The Bidder shall include a price not less than the stated minimum. If in the opinion of the
Bidder these prices do not reflect the actual value of the work involved, the Bidder may void the given fixed minimum unit price for that specific item and enter a higher unit price in the spaces provided in the Bid Form sheets. Bidder's Proposals received which include a unit price less than the stated minimum shall be adjusted to meet the fixed minimum unit price.
3.02 Total Bid Price
Total Bid Price (Total of all Lump Sum and Unit Price Bids)
ARTICLE 4— NOT USED
ARTICLE 5—NOT USED
ARTICLE 6—TIME OF COMPLETION
6.01 Bidder agrees that the Audio and Projection Equipment projects shall be completed within 90 days from the effective date of this contract.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
ARTICLE 7—BIDDER'S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF
ADDENDA
7.01 Bid Acceptance Period
A. This Bid will remain subject to acceptance for 45 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
7.02 Instructions to Bidders
A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.
7.03 Receipt of Addenda
A. Bidder hereby acknowledges receipt of the following Addenda:
Addendum Number Addendum Date
LICDCe C-410, Bid Form for Construction Contract.
Copyright' 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 8—BIDDER'S REPRESENTATIONS AND CERTIFICATIONS
8.01 Bidder's Representations
A. In submitting this Bid, Bidder represents the following:
1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.
2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have, with respect to the Technical Data in such reports and drawings.
5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been with respect to Technical Data in such reports and drawings.
6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical
Data by definition, with respect to the effect of such information, observations, and
Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by
Bidder, if selected as Contractor; and (c) Bidder's (Contractor's) safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract
Times, and in accordance with the other terms and conditions of the Contract.
8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
EJCDC® C-410, Bid Form for Construction Contract.
Copyright° 2018 National Society of Professional Engineers, American Council of Engineering Companies,
8.02 Bidder's Certifications
A. The Bidder certifies the following:
1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.
2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
3. Bidder has not solicited or induced any individual or entity to refrain from bidding.
4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:
a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.
b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.
c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.
d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, BIDDER hereby submits this Bid as set forth above:
Bidder:
(typed or printed name of organization)
By:
Name:
Title:
Date:
(individual's signature)
(typed or printed)
If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.
Attest:
(individual's signature)
Name:
(typed or printed)
Title:
(typed or printed)
Date:
(typed or printed)
Address for giving notices:
Bidder's Contact:
Name:
(typed or printed)
Title:
(typed or printed)
Phone:
Email:
Address:
Bidder's Contractor License No.: (if applicable)
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, PERFORMANCE BOND
Contractor
Name:
Address (principal place of business):
Surety
Name:
Address (principal place of business):
Owner
Name: Town of Lancaster
Mailing address (principal place of business):
Town Hall
21 Central Avenue
Lancaster, New York 14086
Contract
Description (name and location):
Lancaster Opera House Lighting Equipment
Contract Price:
Effective Date of Contract:
Bond
Bond Amount:
Date of Bond:
(Date of Bond cannot be earlier than Effective Date of Contract)
Modifications to this Bond form:
GI None D See Paragraph 16
Surety and Contractor, intending to be legally bound hereby, subject to the terms set forth in this
Performance Bond, do each cause this Performance Bond to be duly executed by an authorized officer, agent, or representative.
Contractor as Principal Surety
(Full formal name of Contractor) (Full formal name of Surety) (corporate seal)
By: By:
(Signature) (Signature)(Attach Power of Attorney)
Name: Name:
(Printed or typed) (Printed or typed)
Title: Title:
Attest: Attest:
(Signature) (Signature)
Name: Name:
(Printed or typed) (Printed or typed)
Title: Title:
Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to Contractor, Surety, Owner, or other party is considered plural where applicable.
EJCDC® C-610, Performance Bond.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
1. The Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Owner for the performance of the Construction Contract, which is incorporated herein by reference.
2. If the Contractor performs the Construction Contract, the Surety and the Contractor shall have no obligation under this Bond, except when applicable to participate in a conference as provided in Paragraph 3.
3. If there is no Owner Default under the Construction Contract, the Surety's obligation under this Bond will arise after:
3.1. The Owner first provides notice to the Contractor and the Surety that the Owner is considering declaring a Contractor Default. Such notice may indicate whether the Owner is requesting a conference among the Owner, Contractor, and Surety to discuss the Contractor's performance.
If the Owner does not request a conference, the Surety may, within five (5) business days after receipt of the Owner's notice, request such a conference. If the Surety timely requests a conference, the Owner shall attend. Unless the Owner agrees otherwise, any conference requested under this Paragraph 3.1 will be held within ten (10) business days of the Surety's receipt of the Owner's notice. If the Owner, the Contractor, and the Surety agree, the
Contractor shall be allowed a reasonable time to perform the Construction Contract, but such an agreement does not waive the Owner's right, if any, subsequently to declare a Contractor Default;
3.2. The Owner declares a Contractor Default, terminates the Construction Contract and notifies the Surety; and
3.3. The Owner has agreed to pay the Balance of the Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract.
4. Failure on the part of the Owner to comply with the notice requirement in Paragraph 3.1 does not constitute a failure to comply with a condition precedent to the Surety's obligations, or release the
Surety from its obligations, except to the extent the Surety demonstrates actual prejudice.
5. When the Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly and at the Surety's expense take one of the following actions:
5.1. Arrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract;
5.2. Undertake to perform and complete the Construction Contract itself, through its agents or independent contractors;
5.3. Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrange for a contract to be prepared for execution by the Owner and a contractor selected with the Owners concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 7 in excess of the Balance of the Contract Price incurred by the Owner as a result of the Contractor Default; or
5.4. Waive its right to perform and complete, arrange for completion, or obtain a new contractor, and with reasonable promptness under the circumstances:
EJCDC® C-610, Performance Bond.
Copyrighto 2018 National Society of Professional Engineers, American Council of Engineering Companies,
5.4.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, make payment to the Owner; or
5.4.2 Deny liability in whole or in part and notify the Owner, citing the reasons for denial.
6. If the Surety does not proceed as provided in Paragraph 5 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner. If the Surety proceeds as provided in Paragraph 5.4, and the Owner refuses the payment, or the Surety has denied liability, in whole or in part, without further notice, the Owner shall be entitled to enforce any remedy available to the Owner.
7. If the Surety elects to act under Paragraph 5.1, 5.2, or 5.3, then the responsibilities of the Surety to the Owner will not be greater than those of the Contractor under the Construction Contract, and the responsibilities of the Owner to the Surety will not be greater than those of the Owner under the
Construction Contract. Subject to the commitment by the Owner to pay the Balance of the Contract Price, the Surety is obligated, without duplication for:
7.1. the responsibilities of the Contractor for correction of defective work and completion of the Construction Contract;
7.2. additional legal, design professional, and delay costs resulting from the Contractor's Default, and resulting from the actions or failure to act of the Surety under Paragraph 5; and
7.3. liquidated damages, or if no liquidated damages are specified in the Construction Contract, actual damages caused by delayed performance or non-performance of the Contractor.
8. If the Surety elects to act under Paragraph 5.1, 5.3, or 5.4, the Surety's liability is limited to the amount of this Bond.
9. The Surety shall not be liable to the Owner or others for obligations of the Contractor that are unrelated to the Construction Contract, and the Balance of the Contract Price will not be reduced or set off on account of any such unrelated obligations. No right of action will accrue on this Bond to any person or entity other than the Owner or its heirs, executors, administrators, successors, and assigns.
10. The Surety hereby waives notice of any change, including changes of time, to the Construction
Contract or to related subcontracts, purchase orders, and other obligations.
11. Any proceeding, legal or equitable, under this Bond must be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and must be instituted within two years after a declaration of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this paragraph are void or prohibited by law, the minimum periods of limitations available to sureties as a defense in the jurisdiction of the suit will be applicable.
12. Notice to the Surety, the Owner, or the Contractor must be mailed or delivered to the address shown on the page on which their signature appears.
13. When this Bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement will be deemed deleted therefrom and provisions conforming to such
EJCDC® C-610, Performance Bond.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, statutory or other legal requirement will be deemed incorporated herein. When so furnished, the intent is that this Bond will be construed as a statutory bond and not as a common law bond.
14. Definitions
14.1. Balance of the Contract Price—The total amount payable by the Owner to the Contractor under the Construction Contract after all proper adjustments have been made including allowance for the Contractor for any amounts received or to be received by the Owner in settlement of insurance or other claims for damages to which the Contractor is entitled, reduced by all valid and proper payments made to or on behalf of the Contractor under the Construction Contract.
14.2. Construction Contract—The agreement between the Owner and Contractor identified on the cover page, including all Contract Documents and changes made to the agreement and the
Contract Documents.
14.3. Contractor Default—Failure of the Contractor, which has not been remedied or waived, to perform or otherwise to comply with a material term of the Construction Contract.
14.4. Owner Default—Failure of the Owner, which has not been remedied or waived, to pay the
Contractor as required under the Construction Contract or to perform and complete or comply with the other material terms of the Construction Contract.
14.5. Contract Documents—All the documents that comprise the agreement between the Owner and Contractor.
15. If this Bond is issued for an agreement between a contractor and subcontractor, the term Contractor in this Bond will be deemed to be Subcontractor and the term Owner will be deemed to be Contractor.
16. Modifications to this Bond are as follows: None.
EJCDO C-610, Performance Bond.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, CONTRACT
This Contract is by and between the Town Board of the Town of Lancaster on behalf of all of the Town of Lancaster (Owner) and (Contractor). Owner and Contractor hereby agree as follows:
ARTICLE 1—THE WORK
1.01 Work
A. Work includes all labor, materials, equipment, services, and documentation necessary to construct the Project defined herein. The Work may include related services such as testing, start-up, and commissioning, all as required by the Contract Documents.
B. The Contractor shall complete all Work as specified or indicated in the Contract Documents.
The Project is generally described as follows:
1. Design, Supply and Installation of Lighting Equipment.
2. The Site of the Work is located at the Town of Lancaster Opera House, Lancaster, New
York, 14086.
ARTICLE 2—CONTRACT DOCUMENTS
2.01 Intent of Contract Documents
A. It is the intent of the Contract Documents to describe a functionally complete Project. The
Contract Documents do not indicate or describe all of the Work required to complete the
Project. Additional details required for the correct installation of selected products are to be provided by the Contractor and coordinated with Owner and Engineer. This Contract constitutes the entire agreement between Owner and Contractor, and supersedes prior negotiations, representations, and agreements, whether written or oral. The Contract
Documents are complementary; what is required by one part of the Contract Documents is as binding as if required by other parts of the Contract Documents.
B. Engineer will be the initial interpreter of the requirements of the Contract Documents, and judge of the acceptability of the Work under the Contract Documents. During the performance of the Work and until final payment, Contractor and Owner shall submit to
Engineer all matters in question concerning the requirements of the Contract Documents, or relating to the acceptability of the Work. Engineer will render a written clarification, interpretation, or decision on the issue submitted, or initiate a modification to the Contract
Documents.
C. Contractor, and its subcontractors and suppliers, shall not have or acquire any title to or ownership rights to any of the Drawings, Specifications, or other documents (including copies or electronic media versions) prepared by Engineer or its consultants.
D. Contract Price or Contract Times: References to a change in "Contract Price or Contract
Times" or "Contract Times or Contract Price" or similar, indicate that such change applies to
(1) Contract Price, (2) Contract Times, or (3) both Contract Price and Contract Times, as warranted, even if the term "or both" is not expressed.
E.ICOC° C-522, Contract for Construction of a Small Project.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, E. Nothing in the Contract Documents creates any contractual relationship between Owner or
Engineer and any Subcontractor, Supplier, or other individual or entity performing or furnishing any of the Work, for the benefit of such Subcontractor, Supplier, or other individual or entity.
2.02 Contract Documents Defined
A. The Contract Documents consist of the following documents:
1. This Contract.
2. Performance bond.
3. Payment bond.
4. Specifications as listed in the Table of Contents.
5. Drawings as listed in the Table of Contents.
6. Addenda.
7. Exhibits to this Contract (enumerated as follows):
a. Contractor's Bid.
8. The following which may be delivered or issued on or after the Effective Date of the
Contract:
a. Notice to Proceed (EJCDC® C-550).
b. Work Change Directives (EJCDC® C-940).
c. Change Orders (EJCDC® C-941).
d. Field Orders (EJCDC® C-942).
ARTICLE 3—ENGINEER
3.01 Engineer
A. The Engineer for this Project is Wm. Schutt Associates, 37 Central Avenue, Lancaster, New
York 14086.
ARTICLE 4—CONTRACT TIMES
4.01 Contract Times
A. The Audio and Projection System shall be completed within 90 days from the effective date of this contract. All Work Schedules to be Coordinated with the Opera House.
4.02 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence in the performance of the
Contract, and that Owner will incur damages if Contractor does not complete the Work according to the requirements of Paragraph 4.01. Because such damages would be difficult and costly to determine, Owner and Contractor agree that as liquidated damages for delay in completion (but not as a penalty) Contractor shall pay Owner $750.00 for each day that expires after the Contract Times under Paragraph 4.01.
EJCDC ° C-522, Contract for Construction of a Small Project.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,
4.03 Delays in Contractor's Progress
A. If Owner, Engineer, or anyone for whom Owner is responsible, delays, disrupts, or interferes with the performance or progress of the Work, then Contractor shall be entitled to an equitable adjustment in the Contract Times or Contract Price.
B. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for delay, disruption, or interference caused by or within the control of Contractor or its subcontractors or suppliers.
C. If Contractor's performance or progress is delayed, disrupted, or interfered with by unanticipated causes not the fault of and beyond the control of Owner, Contractor, and those for which they are responsible, then Contractor shall be entitled to an equitable adjustment in Contract Times.
D. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for any delay, disruption, or interference if such delay is concurrent with a delay, disruption, or interference caused by or within the control of Contractor or Contractor's subcontractors or suppliers.
4.04 Progress Schedules
A. Contractor shall develop a progress schedule and submit it to Engineer for review and comment before starting Work on the Site. Contractor shall modify the schedule in accordance with Engineer's comments.
B. Contractor shall update and submit the progress schedule to Engineer each month. Owner may withhold payment if Contractor fails to submit the schedule.
ARTICLE 5—CONTRACT PRICE
5.01 Payment
A. Owner shall pay Contractor, in accordance with the Contract Documents, for all Work, at the prices stated in the Contractor's Bid.
Payment will be made in an amount equal to the percentage of actual Work completed.
Percentages completed will be agreed to with the Engineer.
ARTICLE 6—BONDS AND INSURANCE
6.01 Bonds
A. When Contractor delivers the signed counterparts of the Contract to Owner, Contractor shall also deliver the performance bond and payment bond to Owner. Each bond must be in an amount equal to the Contract Price, as security for the faithful performance and payment of all of Contractor's obligations under the Contract. These bonds must remain in effect until the completion of the correction period specified in Paragraph 7.12 but, in any case, not less than two years after the date when final payment becomes due.
B. Upon request, Owner will provide a copy of the payment bond to any person or entity claiming to have furnished labor, services, materials, or equipment used in the performance of the Work.
EICDO C-522, Contract for Construction of a Small Project.
Copyright° 2018 National Society of Professional Engineers, American Council of Engineering Companies,
6.02 Insurance
A. When Contractor delivers the signed counterparts of the Contract to Owner, Contractor shall furnish certificates, endorsements, and any other evidence of insurance requested by
Owner. Insurance is to be provided by companies that are duly licensed or authorized in the jurisdiction in which the Project is located with a minimum A.M. Best rating of A-VII or better.
Contractor shall provide insurance in accordance with the following:
1. Contractor shall provide coverage for not less than the following amounts, or greater where required by Laws and Regulations:
a. Workers' Compensation and Employer's Liability
Workers' Compensation Statutory
Employer's Liability
Each Accident $1,000,000.00
Each Employee $1,000,000.00
Policy Limit $1,000,000.00
b. Commercial General Liability
General Aggregate $2,000,000.00
Products - Completed Operations Aggregate $2,000,000.00
Personal and Advertising Injury $1,000,000.00
Bodily Injury and Property Damage—Each Occurrence $1,000,000.00
c. Automobile Liability
Combined Single Limit (Bodily Injury and Property Damage) $1,000,000.00
d. Excess or Umbrella Liability
Per Occurrence $2,000,000.00
General Aggregate $2,000,000.00
e. Contractor's Pollution Liability
Each Occurrence/Claim $2,000,000.00
General Aggregate $2,000,000.00
B. All insurance policies required to be purchased and maintained will contain a provision or endorsement that the coverage afforded will not be canceled or materially changed or renewal refused until at least 10 days after notice has been received by the purchasing policyholder. Within three days of receipt of any such notice, the purchasing policyholder shall provide a copy of the notice to each other insured and Engineer.
C. Automobile liability insurance provided by Contractor will be written on an occurrence basis and provide coverage against claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance, or use of any motor vehicle.
E.ICDC6 C-522, Contract for Construction of a Small Project.
Copyright(' 2018 National Society of Professional Engineers, American Council of Engineering Companies, D. Contractor's commercial general liability policy will be written on a 1996 or later ISO commercial general liability occurrence form and include the following coverages and endorsements:
1. Products and completed operations coverage maintained for three years after final payment;
2. Blanket contractual liability coverage to the extent permitted by law;
3. Broad form property damage coverage; and
4. Severability of interest; underground, explosion, and collapse coverage; personal injury coverage.
E. The Contractor's commercial general liability and automobile liability, umbrella or excess, and pollution liability policies will include and list Owner and Engineer and the respective officers, directors, members, partners, employees, agents, consultants, and subcontractors of each as additional insureds; and the insurance afforded to these additional insureds will provide primary coverage for all claims covered thereby (including, as applicable, those arising from both ongoing and completed operations) on a non-contributory basis.
1. Additional insured endorsements will include both ongoing operations and products and completed operations coverage through ISO Endorsements CG 20 10 10 01 and
CG 20 37 10 01 (together). If Contractor demonstrates to Owner that the specified ISO endorsements are not commercially available, then Contractor may satisfy this requirement by providing equivalent endorsements.
2. Contractor shall provide ISO Endorsement CG 20 32 07 04, "Additional Insured—
Engineers, Architects or Surveyors Not Engaged by the Named Insured" or its equivalent for design professional additional insureds.
F. Umbrella or excess liability insurance will be written over the underlying employer's liability, commercial general liability, and automobile liability insurance. The coverage afforded must be at least as broad as that of each and every one of the underlying policies. Contractor may meet the policy limits specified for employer's liability, commercial general liability, and automobile liability through the primary policies alone, or through combinations of the primary insurance policy's policy limits and partial attribution of the policy limits of an umbrella or excess liability policy that is at least as broad in coverage as that of the underlying policy.
G. The Contractor shall provide property insurance covering physical loss or damage during construction to structures, materials, fixtures, and equipment, including those materials, fixtures, or equipment in storage or transit.
H. If Contractor has failed to obtain and maintain required insurance, Owner may exclude the
Contractor from the Site, impose an appropriate set-off against payment, and exercise Owner's termination rights under Article 15.
ARTICLE 7—CONTRACTOR'S RESPONSIBILITIES
7.01 Contractor's Means and Methods of Construction
A. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction.
EICDC° C-522, Contract for Construction of a Small Project.
Copyright° 2018 National Society of Professional Engineers, American Council of Engineering Companies, B. If professional engineering or other design services are needed to carry out Contractor's responsibilities for construction means, methods, techniques, sequences, and procedures, or for Site safety, then Contractor shall cause such services to be provided by a properly licensed design professional, at Contractor's expense. Neither Owner nor Engineer has any responsibility with respect to (1) Contractor's determination of the need for such services,
(2) the qualifications or licensing of the design professionals retained or employed by
Contractor, (3) the performance of such services, or (4) any errors, omissions, or defects in such services.
7.02 Supervision and Superintendence
A. Contractor shall supervise and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Work in accordance with the Contract Documents.
B. At all times during the progress of the Work, Contractor shall assign a competent resident superintendent who will not be replaced without notice to and approval by the Owner and Engineer except under extraordinary circumstances.
C. Contractor shall maintain good discipline and order at the Site.
D. Except as otherwise required for the safety or protection of the Work or persons or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site will be performed during regular working hours, Monday through Friday.
7.03 Other Work at the Site
A. In addition to and apart from the Work of the Contractor, other work may occur at or adjacent to the Site. Contractor shall take reasonable and customary measures to avoid damaging, delaying, disrupting, or interfering with the work of Owner, any other contractor, or any utility owner performing other work at or adjacent to the Site.
B. Contractor shall notify Owner, the owners of adjacent property, the owners of underground facilities and other utilities (if the identity of such owners is known to Contractor), and other contractors and utility owners performing work at or adjacent to the Site when Contractor knows that prosecution of the Work may affect them; and Contractor shall cooperate with them in the protection, removal, relocation, and replacement of their property or work in progress.
7.04 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for everything necessary for the performance, testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work must be new and of good quality, and be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable supplier, except as otherwise may be provided in the Contract Documents.
7.05 Subcontractors and Suppliers
A. Just as Contractor is responsible for its own acts and omissions, Contractor shall be fully responsible to Owner and Engineer for all acts and omissions of Contractor's employees; of suppliers and subcontractors, and their employees; and of any other individuals or entities
EJCDC° C-522, Contract for Construction of a Small Project.
Copyright ° 2018 National Society of Professional Engineers, American Council of Engineering Companies, performing or furnishing any of the Work. The Contractor's retention of a subcontractor or supplier for the performance of parts of the Work will not relieve Contractor's obligation to
Owner to perform and complete the Work in accordance with the Contract Documents.
7.06 Licenses, Fees and Permits
A. Contractor shall pay all license fees and royalties and assume all costs incident to performing the Work or the incorporation in the Work of any invention, design, process, product, or device which is the subject of patent rights or copyrights held by others.
B. Contractor shall obtain and pay for all construction permits, licenses, and certificates of occupancy, unless otherwise provided in the Contract Documents.
7.07 Laws and Regulations; Taxes
A. Contractor shall give all notices required by, and shall comply with, all local, state, and federal laws and regulations applicable to the performance of the Work. Neither Owner nor Engineer shall be responsible for monitoring Contractor's compliance with any laws or regulations.
B. If Contractor performs any Work or takes any other action knowing or having reason to know that it is contrary to laws or regulations, Contractor shall bear all resulting costs and losses, and to the fullest extent permitted by law Contractor shall indemnify and hold harmless
Owner and Engineer, and the officers, directors, members, partners, employees, agents, consultants, and subcontractors of each and any of them, from and against all such claims, costs, losses, and damages.
C. Contractor shall pay all applicable sales, consumer, use, and other similar taxes.
7.08 Record Documents
A. Contractor shall maintain one printed record copy of all Drawings, Specifications, Addenda, Change Orders, Work Change Directives, Field Orders, written interpretations and clarifications, and approved shop drawings in a safe place at the Site. Contractor shall annotate them to show changes made during construction. Contractor shall deliver these record documents to Engineer upon completion of the Work.
7.09 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the Work.
B. Contractor shall designate a qualified and experienced safety representative whose duties and responsibilities are the prevention of Work-related accidents and the maintenance and supervision of safety precautions and programs.
C. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury, or loss to:
1. All persons on the Site or who may be affected by the Work;
2. All the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and
3. Other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, other work in progress, utilities, and underground
EJCDC® C-522, Contract for Construction of a Small Project.
Copyright® 2018 National Society of Professional Engineers, American Council of Engineering Companies, facilities not designated for removal, relocation, or replacement in the course of construction.
D. All damage, injury, or loss to any property caused, directly or indirectly, in whole or in part, by Contractor, or anyone for whose acts the Contractor may be liable, will be remedied by
Contractor at its expense (except damage or loss attributable to the fault of the Contract
Documents or to the acts or omissions of Owner or Engineer and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of Contractor).
E. Contractor shall be responsible for coordinating any exchange of safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers at the Site in accordance with laws or regulations.
F. In emergencies affecting the safety or protection of the Work or persons or property at the
Site or adjacent thereto, Contractor shall act to prevent damage, injury, or loss. Contractor shall give Engineer prompt notice if Contractor believes that any significant changes in the
Work or variations from the Contract Documents have been caused by an emergency, or are required as a result of Contractor's response to an emergency. If Engineer determines that a change in the Contract Documents is required because of an emergency or Contractor's response, a Work Change Directive or Change Order will be issued.
7.10 Submittals
A. Contractor shall review and coordinate shop drawings, samples, and other submittals with the requirements of the Work and the Contract Documents, and shall verify all related field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information. Contractor shall confirm that the submittal is complete with respect to all related data included in the submittal.
B. Shop drawings and samples must bear a stamp or specific written certification that
Contractor has satisfied its obligations under the Contract Documents with respect to
Contractor's review of that submittal, and that Contractor approves the submittal.
C. With each shop drawing or sample submittal, Contractor shall give Engineer specific written notification, in a communication separate from the shop drawing or sample, of any variations that the shop drawing or sample may have from the requirements of the Contract Documents.
D. Engineer will provide timely review of submittals. Engineer's review and approval of submittals will not extend to the means, methods, techniques, sequences, or procedures of construction, or to safety precautions or programs.
E. Engineer's review of shop drawings and samples will be only to determine if the items covered will, after installation or incorporation in the Work, comply with the requirements of the Contract Documents, and be compatible with the design concept of the completed Project as a functioning whole.
F. Engineer's review and approval of a separate item in a shop drawing or sample does not indicate approval of the assembly in which the item functions.
G. Contractor shall make corrections required by Engineer, return the required number of corrected copies of shop drawings, and submit new samples for review and approval.
E.ICDC° C-522, Contract for Construction of a Small Project.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Contractor shall direct specific attention in writing to revisions other than the corrections called for by Engineer on previous submittals.
H. Shop drawings are not Contract Documents.
7.11 Warranties and Guarantees
A. Contractor warrants and guarantees to Owner that all Work will be in accordance with the
Contract Documents and will not be defective. Engineer and its consultants are entitled to rely on Contractor's warranty and guarantee.
7.12 Correction Period
A. If within two years after the date of substantial completion, any Work is found to be defective, or if the repair of any damages to the Site, adjacent areas that Contractor has arranged to use through construction easements or otherwise, or other adjacent areas used by Contractor as permitted by laws and regulations, is found to be defective, then Contractor shall promptly correct any such defective Work and repairs, at no cost to Owner.
7.13 Indemnification
A. To the fullest extent permitted by law, and in addition to any other obligations of Contractor under the Contract or otherwise, Contractor shall indemnify and hold harmless Owner and
Engineer, and the officers, directors, members, partners, employees, agents, consultants, and subcontractors of each and any of them, from all losses, damages, costs, and judgments
(including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals, and all court or arbitration or other dispute resolution costs) arising from third-party claims or actions relating to or resulting from the performance or furnishing of the Work, provided that any such claim, action, loss, cost, judgment or damage is attributable to bodily injury, sickness, disease, or death, or to damage to or destruction of tangible property (other than the Work itself), including the loss of use resulting therefrom, but only to the extent caused by any negligent act or omission of Contractor, any subcontractor, any supplier, or any individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable.
ARTICLE 8—OWNER'S RESPONSIBILITIES
8.01 Responsibilities
A. Except as otherwise provided in the Contract Documents, Owner shall issue all communications to Contractor through Engineer.
B. Owner shall make payments to Contractor as provided in this Contract.
C. Owner shall provide the Site and easements required to construct the Project.
D. While at the Site, Owner's employees and representatives shall comply with the specific applicable requirements of Contractor's safety programs of which Owner has been informed.
E. Owner shall…
This is the start of the file's text. The full file is on GovTribe.