This document is Exhibit 5 Specifications for the MBM District 3 Joint Replacement Project in Oregon, establishing technical and special provisions governing construction work on five bridge structures. The project involves joint replacement and related work on bridges 07855B, 07855C, 07855D, 16086, and 16086A, including removal of existing joint materials, reconstruction of joint surfaces, installation of various joint seal types, and elastomeric concrete nosing work. The specifications incorporate the 2024 Oregon Standard Specifications for Construction and modify specific sections through detailed special provisions covering mobilization, traffic control, environmental protection, bridge removal, expansion joints, concrete work, joint materials, and structural steel requirements. Traffic control provisions allow single lane closures on Pacific Highway (I-5) during nightly hours (9:00 p.m. to 5:00 a.m., Sunday through Friday) and establish portable changeable message sign requirements displaying bridge work notices at least seven calendar days before lane closures.

The specifications detail concrete requirements including mix design submissions allowing 21 calendar days for engineer review, trial batch testing protocols, and hardened concrete acceptance based on compressive strength testing at 28 days with criteria requiring minimum strength achievement or alternative engineer evaluation for below-specification results. Joint work specifications include estimated quantities for multiple seal types: Bonded Preformed Silicone Seals (196 feet on bridge 07855B), Precompressed Foam Silicone Joint Seals (128 feet each on bridges 07855C and 07855D, 116 feet each on bridges 16086 and 16086A), and corresponding control joints at double the linear footage. Payment terms establish lump sum pricing for mobilization, traffic control, bonded preformed silicone seals, removal of existing joint surfaces, and joint surface reconstruction, with unit pricing for elastomeric concrete nosing material (cubic foot) and construction (square foot). The specifications require manufacturer's technical representatives to be present during work, with strip seal installations requiring on-site presence throughout installation, and mandate hot-dip galvanizing of steel components to AASHTO standards with controlled silicon content verification.

View the file

Other files

File Type Posted
00017476_Att A Form A-2_Bid Pricing Form.xlsx XLSX spreadsheet
00017476 Invitation To Bid.docx DOCX document
00017476 Exhibit 6 Plans.pdf PDF
00017476 Sample Contract.PI.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 5

SPECIFICATIONS

MBM District 3 Joint Replacement Project

2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION: The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Part 00200 and beyond (“technical specifications”) that apply to this Project. Some sections of the technical specifications may be identified and modified in the Contract Documents. Sections of the technical specifications not identified in the Contract Documents remain applicable to the Contract according to their original terms.

Sections 00120-00199 in Part 00100 of the Standard Specifications are not applicable to the Contract unless they are specifically identified in the Contract Documents as being applicable. However, if a section in Part 00100, Sections 00120-00199, that has been identified as being applicable references another section in Part 00100, or if a technical specification references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Abbreviations, definitions, and conventions in Part 00100, Section 00110, apply to the ITB and any resulting Contract as required for context within the Contract Documents. The Standard Specifications are available online: https://www.oregon.gov/odot/Business/Specs/2024_STANDARD_SPECIFICATIONS.pdf

SPECIAL PROVISIONS

The special provisions below identify and modify certain sections of the Standard Specifications.

All number references in the special provisions shall be understood to refer to the sections and subsections of the Standard Specifications bearing like numbers.

TABLE OF CONTENTS FOR SPECIAL PROVISIONS

SECTION 00210 - MOBILIZATION2
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC2
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL2
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS4
SECTION 00290 - ENVIRONMENTAL PROTECTION5
SECTION 00501 - BRIDGE REMOVAL5
SECTION 00584 - ELASTOMERIC CONCRETE NOSING5
SECTION 00585 - EXPANSION JOINTS6
SECTION 02001 - CONCRETE11
SECTION 02440 – JOINT MATERIALS16
SECTION 02530 – STRUCTURAL STEEL18

ii

PROFESSIONAL OF RECORD CERTIFICATION:

June 30, 2028 I certify the Special Provision Sections listed below are applicable to the design for the subject project and modified Special Provisions were prepared by me or under my supervision.

Sections: All

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

SPECIAL PROVISIONS

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

00220.01(b) Abbreviations - Delete this subsection.

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Traffic Lanes may be closed on the Pacific Highway (I5) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

Single Lane Closures - One Traffic Lane on the Pacific Highway (I5), or it’s on and off ramps may be closed during the following times:

Nightly, Sunday night through Friday morning, between 9:00 p.m. and 5:00 a.m.

00220.40(e)(2)(a) Holidays ‑ Replace the paragraph that begins "When a holiday falls …" with the following paragraph:

When a holiday falls on Sunday, the following Monday is recognized as a legal holiday. When a holiday falls on Saturday, the preceding Friday is recognized as a legal holiday.

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.05 Regulations and Codes ‑ Replace this subsection with the following subsection:

Provide all electrical Equipment, Materials, and Work conforming to NEC requirements and all other laws that apply.

00221.06 Traffic Control Plan ‑ Replace this subsection with the following subsection:

00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs ‑

(a) Traffic Control Plan – Submit the following, 5 Calendar Days before the preconstruction conference:

· (1) Contractor Provided Traffic Control Plan – Contractor to create and submit their preferred TCP for this project to the Engineer for review. Typical crack sealing projects utilize the ODOT TM850 Temporary Traffic Control Standard Detail series and/or applicable current version OTTCH figures.

00221.10 General ‑ Replace the paragraph that begins “All Work Zone TCD shall…” with the following paragraph:

Provide Work Zone TCD complying with the crashworthiness requirements of the National Cooperative Highway Research Program (NCHRP) Report 350 or with the AASHTO Manual for Assessing Safety Hardware (MASH).

00221.20 Safety Apparel ‑ Replace the paragraph that begins “Workers, except flaggers, working …” with the following paragraph:

Workers, except flaggers, working within Highway Right of Way and exposed to traffic or construction Equipment are required to wear high visibility safety apparel that meets the Performance Class requirements of the most current version of ANSI/ISEA 107, American National Standard for High Visibility Safety Apparel and Headwear Devices. Wear safety apparel that at least meets the following minimum requirements:

00221.40 General ‑ Replace the paragraph that begins “Existing operational TCD’s shall remain…” with the following paragraph:

Maintain existing TCD’s in operation throughout the Contract or until replaced by new, permanent TCD as appropriate.

00221.60 Temporary Traffic Control Devices ‑ Replace the paragraph that begins “TCD delivered to the Project Site found…” with the following paragraph:

Repair or replace TCD delivered to the Project Site found to be in “marginal” or “unacceptable” condition, at no additional cost to the Agency.

00221.90(b) Temporary Protection and Direction of Traffic – Replace the bullet that begins “Providing, Surfacing, maintain…” with the following bullet:

Providing, surfacing, maintaining, removing, and restoring the TPAR.

00221.98 Payment, Method "B" ‑ Lump Sum Basis ‑ Replace the paragraph that begins "Payment will be payment …" with the following paragraph:

Payment will be payment in full for furnishing, installing, moving, operating, maintaining, inspecting, and removing Materials and TCD, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications modified as follows:

00222.10 Temporary Signs ‑ Replace the paragraph that begins "Furnish temporary signs meeting …" with the following paragraph:

Furnish temporary signs meeting the requirements of the "Acceptable" category shown in the ATSSA Quality Guidelines for Temporary Traffic Control Devices and Features handbook, available from the ATSSA website. Use Materials and fabricate signs according to Section 00940, Section 02910 and the following:

00222.11(b) Portable Sign Supports ‑ Replace the paragraph that begins "Use portable sign supports …" with the following paragraph:

Use portable sign supports from the QPL and according to the following:

0022.12(b) Permanent Signs ‑ Replace the paragraph that begins "Sign covers for permanent signs …" with the following paragraph:

Provide sign covers for permanent signs according to Section 00941.

00222.13 Sign Flags ‑ Replace the paragraph that begins "Sign flags shall be …" with the following paragraph:

Provide sign flags that are:

00222.15(b) Portable Changeable Message Signs - Add the following paragraph to the end of this subsection:

For PCMS mounted on rollers, use 2-line PCMS from the QPL.

00222.45(b) Portable Changeable Message Signs - Replace the bullet that begins "Messages shall not scroll …" with the following bullet:

Do not use messages that scroll horizontally or vertically across the face of the sign.

Add the following bullets to the end of this subsection:

At least seven Calendar Days before the Lane closure, place one or more PCMS displaying the following message as shown, or as approved via submittal to the Engineer for each travel direction of each bridge as applicable:

Panel 1Panel 2Panel 3
BridgeExpectDate
WorkDelaysto
Date

SECTION 00290 - ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications.

SECTION 00501 - BRIDGE REMOVAL

Comply with Section 00501 of the Standard Specifications modified as follows:

00501.00 Scope - Add the following paragraph(s) to the end of this subsection:

Remove portions of the existing bridge 07855B over Hwy 1 & Hwy 72 NB Conn as shown.

Remove portions of the existing bridge 07855C over Hwy 72 NB as shown.

Remove portions of the existing bridge 07855D over Hwy 72 SB as shown.

Remove portions of the existing bridge 16086 over Labish Bottom as shown.

Remove portions of the existing bridge 16086A over Labish Bottom as shown.

Add the following subsection:

00501.02 Plans - Plans of the existing Structure are available from the Engineer. Prints of these plans are available upon request.

SECTION 00584 - ELASTOMERIC CONCRETE NOSING

Comply with Section 00584 of the Standard Specifications modified as follows:

00584.00 Scope ‑ Add the following paragraph to the end of this subsection:

This Work also includes the replacement of existing elastomeric concrete nosing as shown and specified.

00584.80 Measurement ‑ Replace this subsection, except for the subsection number and title, with the following:

The quantities of Work performed under this Section will be measured according to the following:

(a) Elastomeric Concrete Nosing Material ‑ Elastomeric concrete nosing Material will be measured on the volume basis for Material placed in the nosing. When using a mobile mixer, the quantities will be determined by converting the weight identified on the mixer’s automatic metering device to volume, using the manufacturer’s published unit weight and yield factor. When hand batching, the quantities will be determined based on volumes calculated by batch weights and published unit weights of the Material. If placed monolithically with a premixed polymer concrete overlay, the volume will be calculated by multiplying the average depth of the nosing by the measured area.

(b) Constructing Elastomeric Concrete Nosing ‑ Constructing elastomeric concrete nosing will be measured on the area basis. The length will be determined by measuring from face of curb to face of curb along the centerline of the joint. The width will be determined by measuring to the outer limits of the installed Material perpendicular to the joint. Subtract the area of the joint opening from the area calculation.

Joint seal Material will be measured according to 00585.80.

00584.90 Payment – Replace this subsection, except for the subsection number and title, with the following:

The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a) Elastomeric Concrete Nosing MaterialCubic Foot
(b) Constructing Elastomeric Concrete NosingSquare Foot

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

Joint seal Material will be paid for according to 00585.90.

No separate or additional payment will be made for providing the manufacturer's representative.

SECTION 00585 - EXPANSION JOINTS

Comply with Section 00585 of the Standard Specifications modified as follows:

This Work also includes concrete removal and reconstruction of joint surfaces and edges as shown.

00585.01 Definitions – Add the following paragraph after the paragraph that begins “Asphaltic Plug Joint…”

Bonded Preformed Silicone Seal ‑ A Closed joint system consists of a preformed silicone seal bonded to joint surfaces with epoxy adhesive recommended by the joint manufacturer to complete the joint system.

Replace the paragraph that begins “Filled Joint…” with the following paragraph:

Filled Joint ‑ A joint using a preformed joint filler placed prior to concrete pour. Hot applied joint sealant or poured joint seal may be placed on top of the joint filler.

Add the following paragraph after the paragraph that begins “Filled Joint…”

Hot Applied Joint Seal ‑ A joint filled with hot applied, single component sealant.

Replace the paragraph that begins “Poured Joint Seal …” with the following paragraph:

Poured Joint Seal ‑ A Closed Joint seal made of Materials that remain flexible that is poured into the gap of a joint and adheres to the sides of the gap.

Replace the paragraph that begins “Precompressed Foam Silicone …” with the following paragraph:

Precompressed Foam Silicone Joint Seal ‑ A Closed Joint system consisting of a preformed, pre-compressed, silicone-coated, self-expanding foam joint system bonded to joint faces using epoxy adhesive.

Replace the paragraph that begins “Preformed Compression Joint …” with the following paragraph:

00585.02(b) Personnel Qualifications ‑ Replace this subsection, except for the subsection number and title, with the following:

At the pre-construction conference, submit the following:

Joint installer personnel certifications(s) from the manufacturer affirming that the installers have been trained in application methods of Materials and health and safety to install Closed Joints as detailed.

A letter from the manufacturer affirming that the technical representative is qualified to provide technical assistance regarding expansion joint installation.

00585.10 Materials – Add the following Material to the Material list:

Bonded Preformed Silicone Seal02440.24
Portland Cement Concrete Repair Material02015

00585.11 Concrete for Blockout Opening – Replace this subsection with the following subsection:

00585.11 Material for Blockout Opening ‑ Fill blockout openings with the same class and type of concrete used in the deck, unless otherwise shown.

For joint surface reconstruction, fill openings with Material as shown or specified. If not shown, fill openings with one of the following Materials:

Structural polymer concrete with a minimum compressive strength of 10 ksi, a minimum tensile strength of 1 ksi, and a minimum modulus of elasticity of 2,500 ksi.

High early strength concrete (HESC), Class HESC4000 – 3/4 inch, designed according to Section 02001. Incorporate the following:

Rapid hardening hydraulic cement meeting the requirements of Section 02011.

Aggregate meeting the requirements of Section 02690.

Macro fibers meeting the requirements of 02045.20.

Portland cement concrete repair materials meeting the requirements of Section 02015.

00585.30(b) Expansion Joint Seal Manufacturer’s Representative ‑ Replace this subsection with the following subsection:

00585.30(b) Expansion Joint Seal Manufacturer’s Technical Representative ‑ Provide a manufacturer’s technical representative during the Work. Prior to beginning the Work, discuss with the representative regarding the Work to be done, methods of installation, installation procedures, and required Equipment to assure correct expansion joint installation. Ensure the manufacturer’s technical representative remains available for consultation until the completion and acceptance of the Work. For strip seals, the manufacturer’s technical representative is required to be on-site during the Work.

00585.42(c) Joint Preparation ‑ Replace the paragraph that begins "For joint replacement, remove… " with the following paragraph:

For joint replacement, remove joint material from existing joints and clean the existing joints full depth and full width as directed by the Engineer. If existing joint surfaces have spalled, cracked, or deteriorated concrete, repair as shown or directed to provide a uniform and smooth surface. Unless otherwise shown or directed, epoxy inject cracks according to Section 00538 and repair surfaces using an approved PCC repair material.

00585.43 Armored Corners – Replace the title of this subsection with “Armored Corners and Edgebeam”

Replace the paragraph that begins "Provide joint corner armoring …" with the following paragraph:

Provide joint corner armoring or edgebeam with anchors as shown or specified, and according to the following:

00585.43(a) Tolerance ‑ Replace the paragraph that begins "Install armored corners that are straight…" with the following paragraph:

Install armored corners or edgebeams that are straight and do not deviate from a true line by more than 1/4 inch horizontal and 1/8 inch vertical over the length of the joint, nor more than 1/16 inch in either direction from a 12-foot straightedge.

00585.43(b) Installation ‑ Replace the paragraph that begins "Furnish armored corners in the longest …" with the following paragraph:

Furnish armored corners or edgebeams in the longest practical length as controlled by transportation and installation.

Replace the paragraph that begins "For new construction, install armored …" with the following paragraph:

For new construction, install armored corners or edgebeams with anchors in preformed blockouts at least 14 Days after the deck is cast with the joint opening as shown. Support the armored corners or edgebeams securely in position before placing concrete in the joint blockout. Install the preformed seal at least 7 Days after the concrete blockouts have been cast and after the deck concrete reaches 3,000 psi.

00585.47 Strip Seal ‑ Replace the bullet that begins "Use steel retainers acting …” with the following bullet:

Use steel retainers acting as the edgebeams according to 00585.43.

00585.48 Precompressed Foam Silicone Joint Seal ‑ Replace the paragraph that begins "Install Precompressed Foam Silicone Joint …" with the following paragraph:

Use this joint system for joint rehabilitation only, unless shown otherwise. Install Precompressed Foam Silicone Joint Seal according to the manufacturer’s recommendations and the following:

00585.49 Hot Dip Galvanizing – Replace this subsection with the following subsection:

00585.49 Bonded Preformed Silicone Seal ‑ Use this joint system for joint rehabilitation only, unless shown otherwise. Install Bonded Preformed Silicone Seal according to the manufacturer’s recommendations and the following:

Ensure that top of joint system is at a minimum distance below deck surface as shown.

Install joint seal in one continuous strip that extends across the full roadway width and into the bridge rails without splices.

00585.50 Control Joint ‑ Replace this subsection with the following subsection:

00585.50 Hot Dip Galvanizing ‑ Hot dip galvanize steel expansion joint surfaces, except stainless steel, according to AASHTO M 111 (ASTM A123).

Furnish contact surfaces at all galvanized slip critical structural bolted connections meeting Class C (slip coefficient 0.33) surface preparation requirements.

Add the following subsection:

00585.51 Control Joint

Construct Control Joints as shown. If details of the Control Joint are not shown, sawcut the surface 1 1/2 inches deep and 1/2 inch wide. Flush the sawcut thoroughly with a high-pressure water stream after the cut has been made. Before the cut dries out, blow it free of water and debris with compressed air. Fill the sawcut joint with a hot applied joint sealant from the QPL.

Add the following subsection:

00585.52 Hot Applied Joint Seal Replacement ‑ Remove existing hot applied joint sealant from joint. Clean and repair joint surfaces and edges. Install hot applied joint sealant from the QPL and according to the manufacturer’s recommendations.

Add the following subsection:

00585.53 Joint for Sidewalk, Multi-Use Path, or Other Facility Intended for Pedestrian Travel ‑ Provide an expansion joint seal having a firm, stable, and slip resistant top surface, not more than 3/8 inch below finished surface.

For joint seals installed greater than 1/4 inch below finished surface, bevel the joint surface corners with a Slope not steeper than 1V:2H.

For Precompressed Foam Silicone Joint Seals, provide a joint seal having at least double width of the seal designed for the joint size. Install the joint seal according to the manufacturer’s recommendations.

For joint openings 3 inches or wider, design and detail a steel cover plate for facilities with a Pedestrian Accessible Route, Temporary Pedestrian Accessible Route, Multi -Use Path, or other structures intended for pedestrian travel. Hot-dip galvanize the steel plate and provide a slip-resistant surface or coating. Limit the elevation change between the steel plate and deck surface with a vertical face to 1/4 inch not to exceed 1/2 inch. When the elevation change is greater than 1/4 inch, bevel the steel plate corners to a Slope not steeper than 1V:2H.

00585.80 Measurement - Replace the paragraph that begins “No measurement of … with the following paragraph:

No measurement of quantities will be made for joints, gland replacement for strip seals, or joint surface reconstruction. Estimated quantities of joints, gland replacement, and joint surface reconstruction are listed below. The listed quantities are based on the theoretical horizontal length from gutter line to gutter line.

Add the following to the end of the subsection:

The estimated quantities of joints are:

Quantity
StructureJoint Type(Foot)
Bridge No. 07855BBonded Preformed Silicone Seal196
Bridge No. 07855BControl Joint392
Bridge No. 07855CPrecompressed Foam Silicone Joint Seal128
Bridge No. 07855CControl Joint256
Bridge No. 07855DPrecompressed Foam Silicone Joint Seal128
Bridge No. 07855DControl Joint256
Bridge No. 16086Precompressed Foam Silicone Joint Seal116
Bridge No. 16086Control Joint232
Bridge No. 16086APrecompressed Foam Silicone Joint Seal116
Bridge No. 16086AControl Joint232

00585.90 Payment ‑ Replace Pay Item (h) with the following Pay Item:

Add the following Pay Items to the Pay Item list:

(i) Bonded Preformed Silicone SealLump Sum
(k)Removal of Existing Joint SurfacesLump Sum
(l)Joint Surface ReconstructionLump Sum

Add the following (two) paragraphs after the paragraph that begins “In item (d), the….”:

Item (g) includes sawcutting and hot applied joint sealant.

Item (k) includes removing concrete and existing armored corner or edgebeams, if applicable, for new blockout opening.

Add the following four paragraphs after the paragraph that begins “Payment will be payment….”:

Elastomeric concrete nosing incorporated in the Work will be paid for according to 00584.90.

Payment for steel reinforcing will be paid for according to 00530.90.

Payment for concrete will be paid for according to 00540.90.

Modification to existing gland retainer edgebeam or expansion joint type change will be paid for according to 00195.20.

In the paragraph that begins "No separate or additional payment…", replace the bullet beginning with “elastomeric concrete …” with the following bullet:

structural patching material used to provide a smooth contact surface with joint seals, to provide a plane surface on which to place the steel bridging plate, or to make level surfaces between joint.

In the paragraph that begins "No separate or additional payment…", add the following bullet to the end of the bullet list:

Furnishing and installing hot-dip galvanized steel cover plate with slip-resistant surface or coating for facilities with a Pedestrian Access Route.

SECTION 02001 - CONCRETE

Comply with Section 02001 of the Standard Specifications modified as follows:

02001.15 Concrete Mix Design ‑ Replace the paragraph that begins "Submit current or new mix …" with the following paragraph:

Submit current or new mix designs, prepared by a CCT, with the information listed in 02001.15(c), for each required class of concrete to the Engineer for review. Allow 21 Calendar Days for the review. Design mixes by the volumetric method in ACI 211.1 to achieve the properties of 02001.20 and 02001.30 when tested according to 02001.15(b). Provide a design that is workable, placeable and finishable given the specific conditions for the Project and Structure. Do not proceed with concrete placement until the Engineer has determined that the mix design complies with the Specifications. Review of concrete mix designs does not relieve the Contractor of the responsibility to provide concrete meeting the Specification and Project Site requirements.

02001.15(a) Current Mix Design ‑ Replace this subsection, except for the subsection number and title, with the following:

Mix designs that meet the requirements for the specified class of concrete and are currently being used or have been used within the past 24 months on any project, public or private may be submitted for review. Provide individual tests results that comprise the average if more than one data point exists. Provide flexural strength testing for paving designs from within the last two years. Provide length change and permeability tests for HPC designs from within the last two years.

02001.15(b) New Mix Designs ‑ Replace this subsection, except for the subsection number and title, with the following:

Make at least one trial batch for each concrete mix design. Notify the Engineer at least 48 hours before making each trial batch. The Engineer may witness preparation and testing. Prepare and test trial batches using the same Materials, at the same proportions, and having the same plastic properties of concrete that are used in the Project. Simulate haul time, batching sequence and mixing conditions to ensure the trial batch is representative of the mixture that is delivered to the Project. Furnish all Materials, Equipment, testing and Work required for designing the mixes at no additional cost to the Agency.

02001.15(b)(1) Trial Batch Plastic Properties ‑ Replace the test method that begins ”AASHTO T 23…” with the following test method:

AASHTO R 100 or R 39 3

02001.15(b)(2)(a) Compressive Strength Tests ‑ Replace this subsection, except for the subsection number and title, with the following:

For each trial batch, cast and cure at least three test cylinders according to AASHTO R 100 or AASHTO R 39, in 6‑inch by 12‑inch or 4‑inch by 8‑inch single use plastic molds. The use of unbonded caps according to ASTM C1231 is permitted. Test at 28 Days according to AASHTO T 22.

02001.15(b)(2)(b) Flexural Strength Tests ‑ Replace this subsection, except for the subsection number and title, with the following:

For each paving concrete trial batch, cast and cure at least three flexural beams according to AASHTO R 100 or AASHTO R 39. Test flexural beams at 28 Days according to AASHTO T 97.

02001.15(b)(2)(c) Length Change Tests ‑ Replace this subsection, except for the subsection number and title, with the following:

For all HPC mix designs, except for precast or prestressed elements, make at least three specimens from the trial batch for length change testing. Provide sample prisms having a square, 4‑inch by 4‑inch Cross Section. Wet cure the samples until they have reached an age of 28 Days, including the period in the molds. Following the wet cure, air store and measure samples according to AASHTO T 160, Section 11.1.2 for 28 Days. Report length change results at total specimen age of 56 Days.

02001.15(b)(2)(d) Permeability Tests ‑ Replace this subsection, except for the subsection number and title, with the following:

For alternate HPC mix designs, select from the following options:

Make at least three specimens from the trial batch for permeability testing. Prepare, cure, dry and test according to AASHTO T 277. Report permeability in coulombs at 90 Days.

Make at least two specimens from the trial batch for resistivity testing. Prepare, cure and test according to AASHTO T358 using the sealed conditioning method. Report resistivity in kΩꞏcm at 56 Days.

02001.15(c) Required Submittals for Mix Designs ‑ Replace the title of this subsection with “Submittals for Mix Designs”

02001.20 Concrete properties, Tolerances, and Limits ‑ Replace the paragraph that begins "Provide concrete that is…" with the following paragraph:

Furnish concrete that is workable, placeable, uniform in composition and consistency, and having the following properties:

02001.20(a) Strength ‑ Replace the paragraph that begins "Provide concrete meeting …" with the following paragraph:

Furnish concrete meeting the required classes shown in the Contract Documents. The class of concrete designates the minimum required compressive strength, 'c at 28 Days.

02001.20(b) Air Entrainment - Replace the paragraph that begins "Provide all concrete…" with the following paragraph:

Furnish all concrete, except PPCM with cast-in-place decks, seal concrete, and drilled shaft concrete with entrained air in the amounts shown in Table 02001-2. Provide field measured entrained air content within ± 1.5 percent of target air entrainment values.

02001.20(c) Slump - Replace the paragraph that begins "Provide concrete…" with the following paragraph:

Furnish concrete at the appropriate slump shown in Table 02001-3. Take corrective action to maintain a consistent slump at the point of discharge from the delivery vehicle.

02001.20(d) Temperature - Replace the paragraph that begins "Provide concrete…" with the following paragraph:

Provide concrete, at time of placement, at a temperature between a minimum of 50 F and a maximum of 90 F, except the maximum bridge deck concrete temperature is 80 F.

02001.20(e) Durability ‑ Replace this subsection, except for the subsection number and title, with the following:

For HPC designs the following additional requirements apply:

Test
Test Method
Acceptance Value
Length Change
AASHTO T 160
-0.045% 1
Permeability
AASHTO T 277
1,000 Coulombs (max.) at 90 Days 2

1 Not required for precast or prestressed elements.

2 Only required for alternate HPC designs. See 02001.30(b)(2). A minimum resistivity of 37.0 kΩꞏcm at 56 Days for 4x8 inch cylinders and 29 kΩꞏcm at 56 Days for 6x12 inch cylinders are accepted as equal when tested according to AASHTO T 358 using the sealed conditioning method.

Add the following subsection:

02001.20(f) Internal Curing ‑ For HPC(IC) concrete, internally cure the mixture according to the following:

Substitute 350 lbs (SSD) LWFA for standard Fine Aggregate.

Add the following subsection:

02001.20(g) Unit Weight - Furnish high performance lightweight concrete with a maximum plastic density of _____ pounds per cubic foot at time of placement and a maximum calculated approximate equilibrium density of _____ pounds per cubic foot.

02001.30(a) Portland Cement ‑ Replace this subsection, except for the subsection number and title, with the following:

For structural or paving concrete applications use cement according to 02010.10 or 02010.20, excluding Type III. Use Type III cement for precast prestressed concrete.

02001.30(b)(1) General Limits ‑ Replace the paragraph that begins "*Fly ash + other…" with the following paragraph:

* Furnish fly ash + other Pozzolans at a rate no more than 25% and silica fume at a rate no more than 5% of the total weight of Cementitious Materials.

02001.30(b)(2) HPC Cementitious Composition ‑ Replace this subsection, except for the subsection number and title, with the following:

Cement with SCM proportioned according to 02001.30(b)(1) and with trial batches performed to demonstrate that the proposed alternate mix design provides a maximum of 1,000 coulombs at 90 Days when tested according to AASHTO T 277 or a minimum resistivity of 37.0 kΩꞏcm at 56 Days for 4x8 inch cylinders and 29 kΩꞏcm at 56 Days for 6x12 inch cylinders are accepted as equal when tested according to AASHTO T358 using the sealed conditioning method.

02001.30(f) Synthetic Fiber Reinforcing for Concrete ‑ Replace this subsection, except for the subsection number and title, with the following:

Except for precast or prestressed elements, use synthetic fiber reinforcing from the QPL and according to Section 02045 in all HPC. Use synthetic fiber reinforcing according to the manufacturer’s recommendations at the rate designated on the QPL. Fiber packaging is not allowed in the mixed concrete.

02001.40 Concrete Production ‑ Replace the paragraph that begins "1 When haul time or …" with the following paragraph:

1 When haul time or placement conditions warrant exceeding the time of discharge, submit a detailed breakdown of the estimated time needed from batching to discharge of a load along with the measures that are taken to ensure slump, temperature and uniformity is maintained. Submit this request in advance and may establish a new time limit at the Engineer’s discretion.

02001.40(a) Delivery Tickets ‑ Replace the paragraph that begins "Send a concrete delivery …" with the following paragraph:

Send a concrete delivery ticket with each load of concrete supplied to the Project. Include the following information on each delivery ticket:

02001.40(b) Adjusting Concrete Proportions ‑ Replace the bullet that begins "Large admixture dosage changes…" with the following bullet:

Large admixture dosage changes, excluding adjustments for air entraining agents and Type A or D water reducers (± 25 oz/cubic yard).

02001.50 Quality Control ‑ Replace the bullet that begins "The Contractor shall…" with the following bullet:

Designate a person responsible for accepting and rejecting concrete on‑site.

02001.50(c) Concrete Control Technician (CCT) ‑ Replace the bullet that begins "Make adjustments to loads …" with the following bullet:

Make adjustments to loads that fail to meet the air content or slump criteria of the Specifications prior to the 90-minute time limit. Make adjustments complying with the provisions of ASTM C94.

02001.60 Acceptance of Concrete ‑ Replace this subsection, except for the subsection number and title, with the following:

Acceptance of concrete is according to Section 00165 and the following:

(a) Aggregate ‑ Acceptance of Aggregate is according to 02690.12.

(b) Plastic Concrete ‑ Acceptance of plastic concrete is based on tests performed by the Contractor's QCT, according to the tolerances and limits of 02001.20, when discharged within the time allotted in 02001.40.

(c) Hardened Concrete ‑ Cast and cure test specimens according to AASHTO R 100 in 6‑inch x 12‑inch or 4‑inch x 8‑inch, single-use plastic molds and test at 28 Days according to AASHTO T 22.

(1) General ‑ For all classes of concrete, acceptance of hardened concrete is based on an analysis of compressive strength tests of cylinders cast by the QCT. Test cylinders at an Agency certified laboratory.

(2) Acceptance ‑ Hardened concrete with an ASTV meeting or exceeding the specified design strength, 'c is accepted for strength. If the ASTV is less than 'c but at least 85 percent of 'c, the Engineer may review the results to determine if the concrete represented by the cylinders is suitable for the intended purpose. Remove concrete that has an ASTV less than 85 percent of 'c unless otherwise authorized, in writing, by the Engineer. If the concrete is removed, the cost of removal, replacement and all related Work is the Contractor's responsibility. If the Engineer determines that the concrete is suitable for the intended purpose, the concrete may be allowed to remain in place, subject to a price adjustment according to 00150.25. If an ASTV falls below 'c, the Contractor may submit a written plan outlining a proposed alternate method of evaluating compressive strength. Submit the plan for review by the Engineer within 3 Days of the test. Provide evidence that a reasonable 'cr (over-design) was maintained and that there is credible evidence (besides low strength) that warrants consideration of this option. The Engineer may allow an alternate method of acceptance if the compressive strength test results are determined to be suspect from definable external factors.

SECTION 02440 – JOINT MATERIALS

Comply with Section 02440 of the Standard Specifications modified as follows:

02440.10 Preformed Joint Fillers for Concrete - Replace this subsection, except for the subsection number and title, with the following:

Furnish preformed joint fillers for concrete from the QPL according to the requirements of AASHTO M 153 or AASHTO M 213.

02440.15 Lubricant/Adhesive - Replace this subsection, except for the subsection number and title, with the following:

Furnish a lubricant/adhesive according to ASTM D4070 and according to the recommendations of the seal manufacturer.

02440.20 Strip Seals - Replace this subsection, except for the subsection number and title, with the following:

Furnish strip seals from the QPL and according to ASTM D5973.

02440.22 Preformed Compression Joint Seal - Replace this subsection, except for the subsection number and title, with the following:

Furnish preformed compression joint seals from the QPL and according to the requirements of AASHTO M 297.

02440.40(a) Preformed Flexible Joint Sealant - Replace this subsection, except for the subsection number and title, with the following:

Furnish Materials for tongue and groove or key lock manhole joints according to the requirements of ASTM C990.

02440.40(b) Rubber Gaskets - Replace this subsection, except for the subsection number and title, with the following:

Furnish Materials for O-ring manhole and concrete pipe joints according to ASTM C443.

02440.50 Joint Materials for Concrete Precast Manhole Section Joints ‑ Replace this subsection, except for the subsection number and title, with the following:

(a) Mortar - Furnish mortar according to the requirements of ASTM C387, or proportioned one part Type II portland cement to two parts clean, well‑graded Sand passing a No. 6 screen. Admixtures may be used not exceeding the following percentages by weight of cement:

Hydrated lime10%
Diatomaceous earth or other inert materials5%

Furnish mortar with the consistency such that it will readily adhere to the precast concrete if using the standard tongue-and-groove type joint.

(b) Non-Epoxy (Non-Shrink) Grout - Furnish a non-epoxy (non-shrink) grout according to 02080.20. Place or pack non-epoxy (non-shrink) grouts only with the use of a non-epoxy bonding agent according to 02070.20, applied to all cured concrete surfaces being grouted. Use a bonding agent compatible with the grout used.

02440.60 Plastic Compound for Precast Manhole Section Joints ‑ Replace the bullet that begins "Is pliable at temperatures …" with the following bullet:

Is pliable at temperatures between 32 F and 135 F. Ensure a specimen at 77 F and 1/2‑inch square in Cross Section stretches at least 1 1/2 inches before rupture when tested with the apparatus described in ASTM D113.

02440.70(a) Plastic - Replace the paragraph that begins "Polyvinyl chloride water stop …" with the following paragraph:

Manufacture polyvinyl chloride water stop from virgin polyvinyl chloride (PVC) compound. Reclaimed PVC is not allowed. Furnish the water stop having the following properties:

02440.70(b) Rubber - Replace this subsection, except for the subsection number and title, with the following:

Furnish rubber water stops to the dimension shown and according to the requirements of ASTM C923, ASTM C1478, or ASTM F2510 as appropriate for the specific Structure and pipe types.

02440.80 Acceptance - Replace this subsection, except for the subsection number and title, with the following:

Acceptance of joint Materials is according to 00165.35 and this Section.

SECTION 02530 – STRUCTURAL STEEL

Comply with Section 02530 of the Standard Specifications modified as follows:

02530.10 Structural Steel for Bridges ‑ Replace the paragraph that begins “Structural steel for Bridges…” with the following:

Furnish structural steel for Bridges meeting the following, as shown or specified:

02530.20 Structural Steel for Non-Bridge Structures - Replace the paragraph that begins “Structural steel for metal…” with the following:

Structural steel for metal sign Structures and other non-Bridge Structures meeting the following, or as shown or specified:

Replace the paragraph that begins “Notch toughness…” with the following:

Ensure notch toughness of all structural steel members and plates greater than 1/2 inch thick in load carrying members of sign Bridges and cantilever sign supports meets Zone 2 requirements of AASHTO M 270.

02530.50 Universal Mill Plate - Replace the paragraph that begins “Universal mill plate…” with the following:

Universal mill plate is not allowed.

02530.70 Galvanizing ‑ Replace this subsection, except for the subsection number and title, with the following:

Hot-dip galvanize according to the following, as applicable:

AASHTO M 111 (ASTM A123)

AASHTO M 232 (ASTM A153)

Furnish steel that is finished by hot-dip galvanizing for use as sign bridges, illumination poles, traffic signal poles, sign supports, bridge rail and items designated on the Plans as "Galvanize - Control Silicon" having controlled silicon content of either 0 - 0.06 percent or 0.13 percent ‑ 0.25 percent. Before galvanizing, submit mill test certificates verifying silicon content to the Engineer and the galvanizer.

02530.80 Acceptance - Replace this subsection, except for the subsection number and title, with the following:

Acceptance of structural steel is according to 00165.35 and this Section.