About this file
This document is a Notice of Intent to Award from the Oregon Department of Transportation's Transportation and Growth Management (TGM) Program, issued to Parametrix on June 18, 2025, for the LTD Long-Range Mobility Plan project. The Work Order Contract (WOC) is for personal services related to developing a comprehensive long-range mobility plan, with Parametrix selected as the top-ranked firm through a competitive Mini-RFP process (Bid Solicitation #S-73000-00012644). The notice outlines a detailed negotiation and contract execution timeline, with key milestones including establishing a work session to discuss the Statement of Work (SOW), responding to comments and edits, submitting a Breakdown of Costs (BOC), and completing legal sufficiency reviews, with the goal of issuing a Notice to Proceed (NTP) after contract execution.
The contract includes a Disadvantaged Business Enterprise (DBE) goal that must be demonstrated through subcontractor utilization, and requires the submission of various documents such as billing rate information, cost disclosure questionnaire, certificates of insurance, and COI disclosures. The document encourages the use of direct deposit via Automated Clearing House (ACH) for consultant payments and provides a structured approach for contract negotiations, with provisions for extending timelines if both parties are negotiating in good faith. If an agreement cannot be reached within the specified timeframe, ODOT reserves the right to terminate negotiations and approach the next highest-ranked firm. No work is authorized until the WOC is executed and a written NTP is received from the ODOT Project Manager.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 00012644_2D-23_Mini-RFP_Att A_Final.docx | DOCX document | |
| 00012644_2D-23_Mini_RFP_Final.docx | DOCX document | |
| 00012644_2D-23_Mini-RFP_Addendum 1_Final.pdf | ||
| RFQ Home Visiting Education Professional_.docx | DOCX document | |
| 00012644_QA_Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Transportation Transportation and Growth
Management (TGM) Program 355 Capitol St NE, MS#42
Salem, OR, 97301
OREGON DEPARTMENT OF TRANSPORTATION
Notice of Intent to Award
DATE: June 18, 2025 TO: Ryan Farncomb SUBJECT: Intent to Award
Mini-RFP – OregonBuys Bid Solicitation #: S-73000-00012644
Project: LTD Long-Range Mobility Plan
WOC Number: PO-73000-00005662:5 / B38922 WOC #11
Parametrix is the top ranked firm selected for negotiations of a Work Order Contract (WOC) to provide Personal Services as specified in the above referenced Mini-Solicitation / RFP. The scores and rankings of all Proposers are shown in the score matrix accompanying this notice. The award submittal requirements stated in the Mini-Solicitation / RFP are summarized on Attachment 1 of this notice.
David Helton will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work (SOW), schedule of performance and costs under the WOC. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC-NBR as applicable) and submitted to ODOT’s PM. A BOC must demonstrate subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal set forth in the Mini-Solicitation / RFP. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:
Activity Responsible Party Business Days
N eg ot ia tio ns
Establish work session to discuss the SOW with Consultant
ODOT PM / TGM Within 5-10 days of this notice (days depend on size and complexity of the project)
Respond to work session with comments/edits to SOW
Consultant Within 5 days of work session
Activity Responsible Party Business Days
Respond to SOW comments/edits ODOT PM / TGM Within 3 days of receipt of Consultant comments/edits Submission of BOC / Billing Rates Consultant Within 5-10 days of final
ODOT scope (days depend on size and complexity of the project) Respond to BOC, billing rates, negotiate, and
Submit for legal sufficiency
ODOT PM / TGM
TGM
Within 5-10 days of Consultant submission of the BOC (days depend on the size and complexity of the project) Legal Sufficiency TGM, ODOT PM, and DOJ Within 15 (Mini-
Solicitation) & 20 (Formal) days of submission by
ODOT PM
Signature routing and execution TGM, Consultant, and ODOT Expenditure Authority (if required)
Within 6-8 days from initial routing
Issue Notice to Proceed (NTP) ODOT PM 1 day after execution of both WOC & Project IGA
Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice.
If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon.
If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).
Note that no work is authorized until the WOC is executed and Consultant has received a written NTP from the ODOT PM.
ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.
Sincerely, Kelsey Maffei Procurement Contract Specialist, OPBC TGM Grants/Contracts Program Manager ODOT Policy Data & Analysis Division 355 Capitol St NE, MS42 | Salem, OR 97301 Email: kelsey.m.maffei@odot.oregon.gov mailto:kelsey.m.maffei@odot.oregon.gov
Attachment 1 – Award Submittal Requirements
Please email to me, the Contract Coordinator, the following items if marked as “REQUIRED” in the Mini-Solicitation / RFP (see detailed requirements and due date for each item in Section XX of the Mini-Solicitation / RFP).
• Billing Rate Information (if required for LOCUS Data)
• Cost Disclosure Questionnaire (if required for LOCUS Data)
• Breakdown of Costs
• Certificates of Insurance
• COI Disclosure (if any changes from your proposal submission)
• Committed DBE Breakdown & Cert. Form(s) (submission following acceptance of negotiated
BOC)
Direct Deposit via Automated Clearing House (ACH). For Consultants that receive ongoing monthly payments from Agency on one or more contracts or work orders, Agency prefers making Consultant payments via ACH direct deposit. While not required, if Consultant has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, Consultant must complete a Vendor ACH Authorization form and submit to Agency per the instructions on the form. To expedite Consultant’s payments to its subcontractors, if applicable, Consultant should make reasonable efforts to offer ACH direct deposit payments.
https://www.oregon.gov/ODOT/Forms/2ODOT/7310781.pdf https://www.oregon.gov/ODOT/Forms/2ODOT/7310781.pdf