00010029_ITB.docx

DOCX document 155 KB Posted

Attached to
ITB - D1 Bridge Deck Seals 2024
Solicitation number
S-73000-00010029
Issued by
Tillamook County, Oregon

About this file

This is an Invitation to Bid (ITB) issued by the Oregon Department of Transportation (ODOT) for the D1 Bridge Deck Seals 2024 project. ODOT is seeking one qualified contractor to perform bridge deck sealing work at two locations on US101 in Tillamook County. The work includes mobilization, temporary work zone traffic control, pollution control plan, penetrating concrete sealing of 14,926 square feet, and concrete and crack sealing of 5,626 square feet. Bids must be submitted through the OregonBuys eProcurement system prior to the bid opening date and time specified in the ITB. The project requires substantial completion by September 30, 2024 and final completion by October 14, 2024. Liquidated damages will apply for failure to meet the substantial completion date.

The contract price will be based on the bid items and estimated quantities provided. Payment will be made based on actual measured quantities. Contractors must be licensed with the Oregon Construction Contractors Board and comply with prevailing wage rate requirements. ODOT is committed to promoting diversity, equity, and inclusion in the procurement process. Bidders must provide required information and certifications outlined in the ITB. The selected contractor will be required to submit additional documents after notification of the intent to award, including insurance certificates, required bonds, and responsibility documentation.

View the file

Other files

File Type Posted
00010029_Att A_Special Provisions.docx DOCX document
Bid tabulation~15.xlsx XLSX spreadsheet
Zoom Bid Opening Instructions 5.1.24~2.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB/Bid Solicitation No.S-73000-00010029

ITB/BID Solicitation No.: S-73000-00010029

Issue Date: See “Available Date” in OregonBuys

OREGON DEPARTMENT OF TRANSPORTATION

INVITATION TO BID (ITB)

FOR STATE-FUNDED PUBLIC IMPROVEMENT AND PUBLIC WORKS CONTRACT

Project Title: D1 Bridge Deck Seals 2024

Notes:

· OregonBuys. This ITB is advertised as a “Bid Solicitation” in the OregonBuys web-based eProcurement system (https://oregonbuys.gov/bso/). Bids must be submitted through the OregonBuys system. See ITB section C.1 – OregonBuys for information regarding vendor registration and terminology used in OregonBuys platform.

· Hyperlinks. This document must be viewed electronically to access files, forms, provisions or other documents provided via hyperlinks within this ITB. Prospective Bidders that do not have compatible software or are unable to open any of the attached documents, forms or Addenda may contact the Purchaser listed in OregonBuys for alternative electronic formats or hard copies.

· Accessibility. The Oregon Department of Transportation is committed to complying with all statutory requirements to ensure that it is providing information that is more accessible to people with disabilities, as required by Section 508 of the Rehabilitation Act of 1973, as amended (29 U.S.C. 794d), and 36 C.F.R. 1194 Appendix A. This includes information regarding the solicitation process. Please contact the Purchaser/Single Point of Contact identified in OregonBuys (see “Buyer”) to request reasonable accommodation for access, due to a disability, to information related to this solicitation, or the solicitation process, or both. Accommodation requests must be received by the Purchaser/Single Point of Contact 3 business days prior to the Bid Submission Deadline (see “Bid Opening Date” and time in OregonBuys).

PRE-BID CONFERENCE: None.

BID/QUOTE DUE DATE AND TIME. Bids must be submitted through the OregonBuys eProcurement system prior to the “Bid Opening Date” and time listed in OregonBuys for this ITB. All Bid submittal requirements are set forth in ITB Section B.

PURCHASER/SINGLE POINT OF CONTACT. See “Purchaser” and “Info Contact”, including email address, for this ITB in OregonBuys. This is the only point of contact for this ITB. Any questions or issues that may arise regarding the Specifications, the bidding process, and/or the award process shall be directed to the Purchaser/Single Point of Contact.

NON-DISCRIMINATION: ODOT, in accordance with the Title VI of the Civil Rights Act of 1964, 78 Stat. 252. 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations, Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Nondiscrimination in Federally-Assisted programs of the Department of Transportation issued pursuant to such Act, hereby notifies all Bidders that it will affirmatively ensure that all business enterprises will be afforded full opportunity to submit Bids in response to this solicitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.

COMMITMENT TO DIVERSITY, EQUITY, AND INCLUSION: The State of Oregon is committed to taking active steps toward increasing and promoting diversity, equity, and inclusion values across procurement processes for minority, women, emerging small, and veteran owned businesses by reducing barriers to compete for and be awarded state contracts. All interested businesses are encouraged to submit Bids for this contracting opportunity.

TABLE OF CONTENTS

SEE SECTION B FOR ITEMS THAT MUST BE COMPLETED AND SUBMITTED WITH BID RESPONSE.

SECTION A
INTRODUCTION and DEFINITIONS
SECTION B
BID SUBMITTAL REQUIREMENTS
SECTION C
OREGONBUYS; GENERAL BIDDING INFORMATION; INSTRUCTIONS TO BIDDERS/PROCUREMENT PROCESS
SECTION D
BID SECURITY REQUIREMENTS – RESERVED – NOT REQUIRED
SECTION E
PREVAILING WAGE REQUIREMENTS
SECTION F
FIRST-TIER SUBCONTRACTOR DISCLOSURE – RESERVED – NOT REQUIRED
SECTION G
LICENSING REQUIREMENTS; JOINT VENTURE - PARTNERSHIP DISCLOSURE
SECTION H
ADDENDA ACKNOWLEDGEMENT
SECTION I
BIDDER INFORMATION
SECTION J
RECYCLED PRODUCTS
SECTION K
RESIDENCY INFORMATION
SECTION L
CERTIFICATION OF COMPLIANCE WITH TAX LAWS
SECTION M
CERTIFICATION OF DRUG-TESTING LAW REQUIREMENTS
SECTION N
CERTIFICATION OF COMPLIANCE WITH NON-DISCRIMINATION LAWS
SECTION O
SIGNATURE OF BIDDER’S DULY AUTHORIZED REPRESENTATIVE
EXHIBIT 1
RESERVED
EXHIBIT 2
BID BOND FORM – RESERVED – NOT REQUIRED
EXHIBIT 3
PERFORMANCE BOND FORM – RESERVED – NOT REQUIRED
EXHIBIT 4
PAYMENT FORM – RESERVED – NOT REQUIRED
EXHIBIT 5
PUBLIC IMPROVEMENT AGREEMENT FORM
EXHIBIT 6
SUPPLEMENTAL GENERAL CONDITIONS
EXHIBIT 7
RESERVED
EXHIBIT 8
CONTRACT CLOSEOUT COMPLIANCE CHECKLIST

ITB ATTACHMENTS: Attachments to this ITB are posted in OregonBuys (see ITB Section C.1.3).

Bidder is responsible for completing and returning any page(s) in any attachment(s) requiring a response.

Attachment A
SPECIAL PROVISIONS

The following provisions/documents are not physically attached but are incorporated into this ITB from web sites with the same force and effect as though fully set forth herein:

· State of Oregon General Conditions for Public Improvement Contracts January 1, 2012 Edition:

http://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf

· Conflict of Interest (COI) Guidelines for Procurements and Contracts: http://www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx (under Guidance, Policy & Resources). See ITB Section C.2.3.)

· Bureau of Labor and Industries (“BOLI”) Prevailing Wage Rates: http://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx See Section E for the specific rates that apply to this project.

See Section C.3.19 for a list of documents (and the deadline for submission) that will be required from the selected Bidder upon Notice of Intent to Award.

SECTION A – INTRODUCTION and DEFINITIONS

A.1 INTRODUCTION

A.1.1 ITB PURPOSE. The purpose of this ITB is to establish a Contract for performing bridge deck sealing work at 2 locations for the benefit of ODOT:

· Silane seal bridge deck at US101 MP65.55 (9300 sq ft)

· Silane and epoxy seal bridge deck at US101 MP82.92 (5626 sq ft)

The work contemplated under this Contract includes all labor, materials, transportation, equipment and services for, and incidental to, the completion of all construction Work in connection with the project described in the Contract Documents.

A.1.2 REQUIRED PROJECT DATES and SOLICITATION SCHEDULE.

A.1.2.1 REQUIRED PROJECT DATES.

· SUBSTANTIAL COMPLETION: 9/30/2024

· FINAL COMPLETION: 10/14/2024

A.1.2.2 SOLICITATION SCHEDULE

All dates listed are subject to change. All times listed in this ITB and OregonBuys are Pacific Time.

ACTIVITY

SCHEDULE/DEADLINE

Pre-Bid Conference
See page 1 of ITB
Deadline for requests for change, protests, and requests for approved equal brands (if applicable)
5 calendar days prior to the Bid Opening Date identified in OregonBuys for this ITB
Deadline for questions or requests for clarification
5 calendar days prior to the Bid Opening Date identified in OregonBuys for this ITB
Deadline for Bid submittal
See “Bid Opening Date” and time identified in OregonBuys for this ITB
Public Bid opening
Immediately after Bid Opening Date and time identified in OregonBuys for this ITB. See ITB Section C.3.4.2 for a link to remotely attend the Bid opening meeting.
Posting of Intent to Award
Within 5 Business Days after the Bid Opening Date identified in OregonBuys for this ITB
Deadline for Award protest
5 calendar days after issuance of the notice of intent to award. See ITB Section C.3.14

A.1.3 PREVAILING WAGE RATES: State Prevailing Wage Rates (PWRs) apply to this ITB and the resulting Contract. See ITB Section E for BOLI related requirements and applicable wage rates.

A.1.4 LIQUIDATED DAMAGES: Liquidated damages will apply to the Contract resulting from this ITB for failure to complete the project by the Substantial Completion Date. (See Exhibit 5, Section 4 for detailed information.)

A.2 ITB DEFINITIONS

Together with the Definitions found in Section A.1 of the General Conditions, the following definitions apply to this ITB and the resulting Contract:

“Addendum” or “Addenda” (referred to as “Amendment” in OregonBuys) means an addition or deletion to, a material change in, or clarification of, this ITB. Addenda shall be labeled as such and shall be made available to all interested Bidders in accordance with OAR 137-049-0250(2).

“Agency” means the Oregon Department of Transportation (“ODOT”).

“Bid” (referred to as “Quote” in OregonBuys) means the Bidder’s written offer submitted in response to this ITB, including all necessary attachments and information required to be submitted prior to award. Bid also means “Offer” (as defined in Section A.1 of the General Conditions).

“Bid Item” means a specific unit of Work for which a price is provided in the Bid and resulting Contract.

“Bidder” means a “Person” (as defined in Section A.1 of the General Conditions) that submits a Bid in response to an ITB. Bidder also means “Offeror” (as defined in Section A.1 of the General Conditions).

“Bid Price” means the Total Bid amount, including any alternates selected by ODOT provided by the Bidder in the Pricing Submittal.

“Closing” (referred to as “Bid Opening Date” in OregonBuys) means the date and time set for Bid submission in response to this ITB, after which Bids may not be submitted, modified, or withdrawn by Bidder.

“Invitation to Bid” or “ITB” means this document, including all exhibits, attachments and other documents referenced herein, whether attached or incorporated by reference, and any Addenda thereto, used for soliciting Bids.

“ODOT Procurement Office” or “OPO” means the Procurement Office Section of the Oregon Department of Transportation.

“Opening” means the date/time set to read the Bid submittals.

“OregonBuys” means the on-line electronic Oregon automated procurement system administered by the State’s Department of Administrative Services. The OregonBuys website is: https://oregonbuys.gov/bso

“Pay Item” means a specific unit of Work for which a price is provided in the Contract. Also referred to as “Bid Item”.

“State” means the State of Oregon.

SECTION B - BID SUBMITTAL REQUIREMENTS

B.1 GENERAL BID REQUIREMENTS

Bidder shall provide required information on the forms specified in this ITB. Any information Bidder submits that is not required to be included on forms prescribed by the ODOT Procurement Office must be formatted in the manner called for in this ITB and submitted on Bidder’s letterhead.

Bidder shall not make the Bid contingent upon the Owner’s acceptance of Specifications, Plans or Contract terms that conflict with or are in addition to those advertised in this ITB. Bidder must select the “Yes” option on the Terms & Conditions tab in OregonBuys. If Bidder selects “Yes with exceptions” or “No,”, the Bid will be rejected.

B.2 SUBMITTALS VIA OREGONBUYS

Bidder must be a registered Vendor in OregonBuys (see Section C.1.1).

Bidder should select the “Confidential” checkbox in OregonBuys when uploading any files required in response to this ITB.

B.2.1 ON-LINE PRICING ENTRY. Bidder must complete on-line entry of all required pricing information specified in the “Item Information” section for this ITB in OregonBuys. Failure to supply the required pricing information may result in rejection of the Bid as non-responsive. In the event of a discrepancy between extended prices and unit prices, unit prices will prevail.

If the Bid item information for this ITB is modified by an Addendum, then Bidders shall update pricing data entry, as necessary, to address revisions to the Item Information specified in OregonBuys for this ITB.

B.2.2 ADDITIONAL INFORMATION TO BE SUBMITTED WITH THE OFFER. Bidder must submit the following items via upload in OregonBuys no later than the Bid Opening Date and time specified in OregonBuys for this ITB, or the Offer will be determined not Responsive.

SECTION G
LICENSING REQUIREMENTS; JOINT VENTURE - PARTNERSHIP DISCLOSURE
SECTION H
SOLICITATION ADDENDA ACKNOWLEDGEMENT
SECTION I
BIDDER INFORMATION
SECTION J
RECYCLED PRODUCTS
SECTION K
RESIDENCY STATEMENT
SECTION L
CERTIFICATION OF COMPLIANCE WITH TAX LAWS
SECTION M
CERTIFICATION OF DRUG-TESTING LAW REQUIREMENTS
SECTION N
CERTIFICATION OF COMPLIANCE WITH NON-DISCRIMINATION LAWS
SECTION O
SIGNATURE OF BIDDER’S DULY AUTHORIZED REPRESENTATIVE

B.2.3 ELECTRONIC BID PROVISIONS.

B.2.3.1. Bidder shall make reasonable efforts to minimize the file size of attachments so the total submittal does not exceed 5 megabytes (for tips on reducing file size, see How to reduce PDF file size (https://www.wikihow.com/Reduce-PDF-File-Size) and How to reduce the size of Word documents that contain images (https://www.howtogeek.com/255379/how-to-reduce-the-size-of-microsoft-office-documents-that-contain-images/).

B.2.3.2.ODOT reserves the right to reject any Bid that is unreadable.
B.2.3.3.ODOT reserves the right to award the Contract solely on the Bid submitted electronically through OregonBuys; however, upon ODOT’s request, the apparent successful Bidder shall promptly submit its complete original signed bid.
B.2.3.4.Per OAR 731-146-0150(4) in the event of a failure of an Electronic Procurement System or email system that interferes with the ability to submit electronic Bids, to protest or to otherwise participate in the procurement, ODOT may cancel the procurement or may extend the date and time of receipt of electronic Bids by providing notice of the extension immediately after the Electronic Procurement System or email system becomes available.
B.2.3.5.By submitting a Bid in response to this ITB, the Bidder (and if selected for award, also as the Contractor) agrees with ODOT that signatures, and other forms of authorized representative certification, showing on documents submitted via OregonBuys or email are “Electronic Signatures” under ORS Chapter 84 and bind the signing party and are intended to be and can be relied upon by the parties.

SECTION C – OREGONBUYS; GENERAL BIDDING INFORMATION; INSTRUCTIONS TO BIDDERS/PROCUREMENT PROCESS

C.1. OREGONBUYS INFORMATION

C.1.1 REGISTRATION REQUIREMENT; OREGONBUYS USER GUIDES. All vendors must be registered in OregonBuys to do business with the State. Registration is free. To create a vendor account, click the blue “Register” button in the top right corner of the OregonBuys website: https://oregonbuys.gov/bso. For registration assistance see vendor registration guidance (https://www.oregon.gov/das/ORBuys/Documents/SupplierRegistrationGuide.pdf). Vendors are responsible for ensuring that their vendor registration and information is current and correct in OregonBuys. ODOT shall not be responsible for defective registration or incorrect vendor information.

See OregonBuys User Guides located on OPO’s Contracting with ODOT page (https://www.oregon.gov/odot/Business/Procurement/Pages/HowTo.aspx) for quick reference information regarding common questions from vendors when using OregonBuys.

C.1.2 CROSSWALK of TERMS.

Terms used in OregonBuys
Definition
Amendment
“Addendum” or “Addenda”, as defined in OAR 137-046-0110(1); or any form of notice associated with the solicitation, such as intent to award, cancellation, etc., as set forth in the Amendment.
Bid Opening Date
“Closing” as defined in OAR 137-046-0110(5). In OregonBuys it is the deadline for submitting Quotes (Bids, Proposals or other required responses) required by a Bid Solicitation, after which the Bid “Opening” as defined in OAR 137-046-0110(21) will immediately occur.
Bid Solicitation
Any form of solicitation: Request for Proposal, Invitation to Bid, Request for Quote, Request for Information, etc., including notices (sole source notice, intent to participate, etc.). Each Bid Solicitation has a separate page and ID number in OregonBuys.
Change Order
A formal change to an existing MBPO (i.e., any form of contract; agreement; price agreement or on-call contract, etc.; purchase order; or work order contract.
Master Blanket Purchase Order (“MBPO”)
Any form of contract; agreement; price agreement or on-call contract, etc.; purchase order; or work order contract.
Quote
Any form of offer submission by vendors; i.e., Bids, Quotes, or any other type of offer required by a Bid Solicitation.
Vendor
Any form of business entity registered in OregonBuys. Only registered Vendors are eligible to submit a Quote and enter into any form of Contract pursuant to Bid Solicitations advertised in OregonBuys.

C.1.3 ITB ATTACHMENTS AND ADDENDA. In addition to the provisions set forth and linked within this ITB, this ITB incorporates by this reference the information published or linked on the OregonBuys “Bid Solicitation” page for this ITB, including but not limited to:

· Details entered in the Header Information section;

· All ITB attachments, Addenda and notices (“Amendments” in OregonBuys), question and answer documents, and any other files linked in the File Attachments and Form Attachments subsections; and

· Information, if any, entered in the “Questions” and “Item Information” sections.

C.2 GENERAL BIDDING INFORMATION

C.2.1 OBTAINING ITB DOCUMENTS. This ITB, ITB attachments and any Addenda and notices (“Amendments”) may be downloaded from the OregonBuys eProcurement system at: https://oregonbuys.gov/bso. Contact the Purchaser identified in OregonBuys for this ITB if unable to access solicitation documents via OregonBuys.

Bidders are solely responsible for checking OregonBuys regularly until the Bid Opening Date and time specified in OregonBuys to assure that they have not missed any Addenda or other notices issued as “Amendments” in OregonBuys for this ITB.

C.2.2 TRADE SECRETS. Any information Bidder submits in response to this ITB that Bidder considers a trade secret under ORS 192.345(2) or ORS 646.461(4), and that Bidder wishes to protect from public disclosure, must be clearly labeled with the following: “This information constitutes a trade secret under ORS 192.345(2) or confidential proprietary information and is not to be disclosed except in accordance with the Oregon Public Records Law, ORS Chapter 192.” Each item so labeled must include a justification and citation of the authority relied upon. Identifying the entire Bid submittal as trade secret, confidential, or otherwise exempt from disclosure is not acceptable. Bidders are cautioned that price information submitted in response to an ITB is generally not considered a trade secret under Oregon public records law. Further, information submitted by Bidder that is already in the public domain is not protected. ODOT is not liable for disclosure or release of information when authorized or required by law or court order. ODOT is also immune from liability for disclosure or release of information under the circumstances set out in ORS 646.473(3).

C.2.3 CONFLICT OF INTEREST (COI) DISCLOSURE. Bidder must be in compliance with ODOT’s COI Guidelines. If there are any disclosures required for Bidder or its subcontractors, as detailed in the ODOT Conflict of Interest Guidelines, Bidder must submit the required signed COI Disclosure Form(s) with its Bid.

If there are no COI disclosures required for Bidder or its subcontractors, per the ODOT COI Guidelines, submittal of COI Disclosure form(s) is not required.

The ODOT Conflict of Interest Guidelines for Procurements and Contracts and ODOT’s COI Disclosure Form are available at the following internet site: http://www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx

C.2.4 SOLICITATION LAW AND RULES. This ITB and the resulting Contract are governed by and construed and enforced in accordance with Oregon Law. Specific laws and rules that govern the solicitation process are found in Chapters 279A and 279C of the Oregon Revised Statutes and the Attorney General’s Model Public Contract Rules (“Model Rules”) OAR 137 Divisions 046 and 049, as adopted and modified by the Department of Transportation Rules OAR 731, Divisions 146 and 149. The ITB and resulting Contract may be subject to other laws and rules. Bidders should obtain and become acquainted with the applicable provisions of the above laws and rules.

REQUIREMENTS APPLICABLE to PUBLIC IMPROVEMENTS APPLY to PUBLIC WORKS. If this is a Public Works project, all requirements applicable to Public Works projects apply to this project. In addition, ODOT has chosen to apply the requirements applicable to Public Improvement projects to this project whether or not it is a Public Improvement project. Therefore, throughout this ITB, wherever there is a reference to or requirement concerning Public Improvements, ODOT is applying the same requirement to the project, whether or not otherwise required by rule or statute.

C.2.5 STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS. In addition to the solicitation laws and rules, this ITB and the resulting Contract are governed by the STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS, January 1, 2012 Edition (“General Conditions”) which, although not physically attached, is incorporated herein by reference with the same force and effect as though fully set forth herein. The General Conditions can be obtained on line at: http://www.oregon.gov/das/Procurement/Guiddoc/GenCon4PI.pdf

C.2.6 2024 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION. The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Specifications. Sections of the technical specifications not identified in the Plans and Specifications remain applicable to the Contract according to their original terms.

Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in an exhibit or attachment to the Contract or in the Plans and Specifications as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

C.2.7 BRAND NAME USAGE.

C.2.7.1 BRAND NAME. Any brand name listed in the specifications with or without a designation of "or equal" or "or equivalent" shall establish the minimum requirements for quality, utility, durability, function, and purpose. Unless the product named is the subject of an exemption per ORS 279C.345, other brand names may be used in the construction of the project as long as they are equal to or better than the product brand named, and are approved by ODOT prior to installation.

C.2.7.2 BRAND NAME "OR APPROVED EQUAL” OR “OR APPROVED EQUIVALENT”. Any brand name listed in the specifications followed by "or approved equal" or “or approved equivalent” shall establish the minimum requirements for quality, utility, durability, function, and purpose. Unless the product named is the subject of an exemption per ORS 279C.345, other brand names may be used in the construction of the project as long as they are equal to or better than the product brand named, and are approved by ODOT during the bidding process in accordance with the Request for Brand Approval procedures specified in Section C.3.1.4.

ODOT shall determine, in its sole discretion, whether a product offered is "or equal".

C.3 INSTRUCTIONS TO BIDDERS/PROCUREMENT PROCESS

Note: If a Pre-Bid conference is scheduled, the details are set forth on page 1 of the ITB.

C.3.1 REQUEST FOR CLARIFICATION; REQUEST FOR CHANGE; REQUEST FOR BRAND APPROVAL; SOLICITATION PROTEST. The appropriate means of seeking clarifications of or modifications to provisions of an ITB are through (a) requests for clarification; (b) requests for changes to contractual terms or Specifications or Plans; (c) requests for brand approval; and (d) protests of contractual terms or Specifications or Plans. Any Bid response that includes non-approved alternate product brands where approval is required, or that takes exception to the Specifications or Plans or contractual terms of this ITB may be deemed non-responsive and may be rejected.

C.3.1.1 METHOD OF SUBMITTING REQUESTS AND PROTESTS. Requests and protests must be marked as follows: Request for Clarification/ Request for Change/ Request for Brand Approval/ Solicitation Protest ITB Number Closing Date Closing Time

Requests and protests must be in writing and must be submitted via email to and received by the Purchaser specified in OregonBuys for this ITB no later than the applicable deadline specified in ITB Section A.1.2.2 – Solicitation Schedule. Unless the specific deadline is extended by subsequent Addenda, requests for clarification, requests for change, protests pertaining to provisions contained in the originally-issued ITB, or requests for brand approval will not be considered after the specified deadline.

C.3.1.2 REQUEST FOR CLARIFICATION. Any Bidder that finds discrepancies in, or omissions from, any provision of this ITB, Plans, Specifications, or Contract Documents, or has doubt as to the meaning, may submit a request for clarification in conformance with submittal requirements in Section C.3.1.1)

C.3.1.3 REQUEST FOR CHANGE. Any Bidder may submit a request for changes to contractual terms, Plans, or Specifications in conformance with submittal requirements in Section C.3.1.1. The request must include the specific changes requested, and the reason for the requested changes supported by factual documentation.

C.3.1.4 REQUEST FOR BRAND APPROVAL. Pursuant to Section C.2.7.2, Bidder shall provide the named product unless another is approved through a request for brand approval in conformance with submittal requirements in Section C.3.1.1. Other brands of equal quality, merit and utility will be considered upon proper submittal of a request for brand approval with appropriate documentation, unless the named product has been exempted per ORS 279C.345.

· Requester must provide sufficient information for ODOT to determine product acceptability including, but not limited to, detailed product specifications.

· Requester’s failure to provide sufficient information with the request shall be cause for the proposed product not to be considered equal.

· Any product subsequently approved for substitution will be listed on an Addendum issued by the ODOT Procurement Office and posted on the OregonBuys system.

C.3.1.5 SOLICITATION PROTEST. Any Bidder may, in conformance with submittal requirements in Section C.3.1.1, submit a protest of solicitation terms and conditions, contract terms and conditions or Specifications in accordance with OAR 137-049-0260. The protest must include the legal and factual grounds for the protest, a description of the resulting prejudice to the Bidder if the protest is not upheld, and a statement of the desired changes.

C.3.1.6 RESPONSE TO REQUESTS FOR CLARIFICATION. Clarifications, whether verbal, in writing, or included in an Addendum as a "clarification," do not change Plans, Specifications, contractual terms, or procurement requirements of this ITB. If a request for clarification raises an issue that ODOT determines should be handled by formally amending this ITB, ODOT will do so only by specifying such a change in an Addendum, not through information identified as a "clarification."

C.3.1.7 RESPONSE TO REQUESTS FOR CHANGE,REQUESTS FOR BRAND APPROVAL, AND SOLICITATION PROTESTS. The ODOT Procurement Office will promptly respond to each properly-submitted written request for change, request for brand approval, and protest. When appropriate, the ODOT Procurement Office will issue ITB revisions via Addenda posted on the OregonBuys system. ODOT may also informally respond to Bidder questions.

C.3.1.8 QUESTION AND ANSWER DOCUMENTS. ODOT may post question and answer documents on OregonBuys to respond to inquiries when ODOT determines, in its sole discretion, the answers do not effect changes to this ITB.

INFORMAL RESPONSES, OR QUESTIONS AND ANSWERS POSTED ON OREGONBUYS, DO NOT AFFECT THE PROVISIONS OF THIS ITB. PLANS, SPECIFICATIONS, CONTRACTUAL TERMS, AND PROCUREMENT REQUIREMENTS OF THE ITB CAN ONLY BE CHANGED VIA ADDENDA ISSUED BY THE ODOT PROCUREMENT OFFICE AND POSTED ON OREGONBUYS.

C.3.1.9 REQUESTS OR PROTESTS RELATED TO ADDENDA. Requests for clarification, requests for change, and protests of an Addendum may be submitted in conformance with submittal requirements in Section C.3.1.1. Requests or protests related to an Addendum must be received by 5:00 pm on the next business day following issuance of the Addendum, unless a different deadline is set forth in the Addendum, or they will not be considered. ODOT will not consider requests or protests pertaining to matters not added or modified by the Addendum.

C.3.2 BID MODIFICATION PRIOR TO CLOSING/BID OPENING. Alterations and erasures made before Bid submission must EACH be INDIVIDUALLY initialed by the person signing the Bid. Bids, once submitted, may be modified in writing, before the Bid Opening Date and time specified in OregonBuys for this ITB. Modifications made after Bid submission must be uploaded in OregonBuys after deleting prior submittal items using the “Withdraw Quote” button.

C.3.2.1 Nothing in this Section C.3.2 shall be construed as allowing Bidder to alter or otherwise change the form of the Bid, the form of the Contract, the conditions of the Bid, the Specifications, or the Plans attached to the Bid documents.

C.3.2.3 Bidders may not modify Bids after the ”Bid Opening Date” and time specified in OregonBuys for this ITB.

C.3.3 BID WITHDRAWALS PRIOR TO CLOSING/BID OPENING. If a Bidder wishes to withdraw a submitted Bid, the Bidder must do so using the “Withdraw Quote” button in OregonBuys prior to Closing/”Bid Opening Date” and time specified in OregonBuys for this ITB.

C.3.4 BIDS RECEIVED AND BID OPENING.

C.3.4.1 BIDS RECEIVED. Offers must be received in accordance with all instructions in this ITB prior to the ”Bid Opening Date” and time specified in OregonBuys for this ITB. Offers received after the Bid Opening Date and time, or as may be extended by any subsequently issued Addendum, will not be considered for award.

C.3.4.2 BID OPENING. Bid Opening will occur immediately following ”Bid Opening Date” and time as specified in OregonBuys. Only the name of each Bidder and the Bid amounts will be read at the Opening. Award decisions will not be made at the Bid Opening.

ODOT will hold the public Opening through electronic means. Interested parties may attend the Opening for this solicitation electronically as follows (It is attendee’s choice to use video or audio only.):

Microsoft Teams Need help?

Join the meeting now Meeting ID: 232 708 876 225 Passcode: xy3wFm

Dial-in by phone +1 971-277-1965,,629390294# United States, Portland Find a local number Phone conference ID: 629 390 294# For organizers: Meeting options | Reset dial-in PIN

C.3.5 PRELIMINARY BID RESULTS. Prior to posting its notice of its intent to award on the OregonBuys system (“Intent-to-Award Announcement”), the ODOT Procurement Office may post preliminary Bid results. Such postings may not be correct and are not final.

C.3.6 TIME FOR OFFER ACCEPTANCE. An Offer is a firm offer, irrevocable, valid and binding on the Bidder for not less than thirty (30) calendar days from the Closing.

C.3.7 EXTENSION OF TIME FOR OFFER ACCEPTANCE. The ODOT Procurement Office may request, orally or in writing, that Bidders extend, in writing, the time during which ODOT may consider their Offer(s). If a Bidder agrees to such extension, the Offer shall continue as a firm Offer, irrevocable, valid and binding on the Bidder for the agreed-upon extension period.

C.3.8 SUBSTANTIAL COMPLIANCE REQUIRED. Offers not in substantial compliance with ITB requirements cannot be considered and cannot be supplemented by submissions delivered after Closing. However, ODOT may waive minor informalities and irregularities, and may seek clarification of any response that, in its sole discretion, it deems necessary or advisable.

C.3.9 OFFER EVALUATION CRITERIA and METHOD OF AWARD.

C.3.9.1 RESPONSIVENESS. To be considered responsive, the Bidder must substantially comply in all material respects with applicable solicitation procedures and requirements and the solicitation documents. In making such evaluation, ODOT may waive minor informalities and irregularities.

C.3.9.2 RESPONSIBILITY. Prior to award of a Contract, ODOT will evaluate whether the apparent successful Bidder meets the applicable standards of responsibility identified in OAR 137-049-0390. See also, OAR 137-049-0440(1)(c)(H). In doing so, ODOT may investigate Bidder and request information in addition to that already required in this ITB, when ODOT, in its sole discretion, considers it necessary or advisable.

C.3.9.3 OREGON PREFERENCE. Awards shall be subject to preference for goods or services that have been produced or manufactured in Oregon, if price, fitness, availability and quality are otherwise equal (ORS 279A.120); See also; OAR 137-046-0300.

C.3.9.4 RECIPROCAL PREFERENCE. Solely for the purpose of evaluating offers, ODOT will add a percent increase to the Offer of a non-resident Bidder equal to the percent, if any, of the preference given to the Bidder in the state in which the Bidder resides. For example, if the Bidder is from a state that grants a ten (10) percent preference to local Bidders, ODOT will add ten (10) percent to that Bidder’s Offer price. (OAR 137-046-0310). No such adjustments shall operate to amend an Offer or any Contract awarded pursuant thereto.

C.3.9.5 RESERVED

C.3.9.6 REJECTION OF OFFER DUE TO CERTAIN DEBT. Included among the reasons ODOT may reject an Offer is if the Bidder has liquidated and delinquent debt owed to the State or any department or agency of the State.

C.3.9.7 METHOD OF AWARD. Provided Agency does not cancel the solicitation or reject all Offers pursuant to OAR 137-049-0270, award will be made to the responsible Bidder that submits a responsive Bid with the lowest total Bid Price (including adjustments, if any, per C.3.9.4) for the items selected for award. Award will be made to one Bidder only. ODOT reserves the right to withdraw any item from award consideration if it is in the best interest of the State to do so.

C.3.10 PROCESSING OF BIDS. Neither the release of a Bid security, nor acknowledgment that the selection process is complete (whether by posting of a Bid tabulation sheet, issuance of Intent-to-Award Announcement, or otherwise), shall operate as a representation by ODOT that any Offer submitted was complete, sufficient, lawful in any respect, or otherwise in substantial compliance with the requirements of this ITB.

C.3.11 WITHDRAWAL BY ODOT OF BID ITEMS PRIOR TO AWARD. ODOT reserves the right to delete Bid items. The deletion of one or more Bid items will not affect the method of award.

C.3.12 REJECTION OF OFFERS.

C.3.12.1 REJECTION OF ALL OFFERS. ODOT may reject all Offers for good cause upon its finding that it is in the public interest to do so.

C.3.12.2 REJECTION OF PARTICULAR OFFERS. ODOT may reject a particular Offer for any of the reasons listed under OAR 137-049-0440.

C.3.13 INTENT-TO-AWARD ANNOUNCEMENT. Prior to formal Contract award, ODOT will post its Intent-to-Award Announcement on the OregonBuys system The Intent-to-Award Announcement shall serve as notice to all Bidders that ODOT intends to make an award.

C.3.14 PROTEST OF INTENT TO AWARD. Adversely affected or aggrieved Bidders shall have 5 calendar days from the date of the Intent-to-Award Announcement within which to file a written protest via email to the Purchaser at the email specified for this ITB in OregonBuys. Protests submitted after that date will not be considered. Protests must specify the grounds upon which the protest is based.

C.3.14.1 In order to be an adversely affected or aggrieved Bidder, the Bidder must claim to be eligible for award of the Contract as the lowest responsible and responsive Bidder and that any and all lower Bids are ineligible to receive Contract award.

C.3.14.2 An actual Bidder who is adversely affected or aggrieved by the award of the Contract to another Bidder may protest award, in writing, within the timeline established. The written protest shall state the grounds upon which the protest is based. No protest of award shall be considered after the deadline.

C.3.14.3 Pursuant to OAR 137-049-0260, no protest against award shall be considered because of the content of Bid Specifications, Plans, or contract Terms after the deadline established for submitting protests of Bid Specifications, Plans or Contract Terms.

C.3.15 RESPONSE TO INTENT-TO-AWARD PROTESTS. The ODOT Procurement Office will respond in writing to intent-to-award protests submitted by adversely-affected or aggrieved Bidders. ODOT may also respond to intent-to-award protests submitted by other Bidders for purposes of clarification. However, any response provided by ODOT is not intended to, and shall not in and of itself constitute, confirmation that the bidder is, in fact, adversely affected or aggrieved, and therefore entitled to protest an intent to award, or that the protest was timely filed.

C.3.16 AWARD. After expiration of the protest period, and resolution of all protests, ODOT will proceed with final award. (If ODOT receives only one Bid, ODOT may dispense with the intent-to-award protest period and proceed with award of a Contract.)

C.3.17 COMMENCEMENT OF WORK. Contractor shall not commence Work under a Contract resulting from this ITB until a Notice to Proceed has been issued.

C.3.18 REVIEW OF AWARDED BID FILES. Awarded Bid files are public records and available for review. Contact the Single Point of Contact to arrange for review of the documents.

C.3.19 INFORMATION TO BE SUBMITTED BY THE APPARENT SUCCESSFUL BIDDER. ODOT will notify the apparent successful Bidder by email of its intent to award a Contract. The apparent successful Bidder shall submit the following items via email no later than seven calendar days after the date of ODOT’s notification of intent to award unless another date is specified in the Intent-to-Award Announcement. Failure to provide any required items may result in Bid rejection.

C.3.19.1 INSURANCE. The selected Bidder shall submit certificates of insurance for all coverages required by this ITB. If the Bidder specifies, in Exhibit 7, prior to the execution of the Contract that a Subcontractor will satisfy an insurance requirement that is permitted to be satisfied by a Subcontractor, the Contractor shall obtain ODOT approval of Subcontractor and Subcontractor’s insurance coverage(s), at least 35 Calendar Days prior to commencement of subcontracted work. Bidders are encouraged to consult their insurance agent(s) about the insurance requirements as identified in Section G.3 of the General Conditions and the Supplemental General Conditions in Exhibit 6 (if any) prior to Offer submission.

C.3.19.2 RESERVED

C.3.19.3 JOINT VENTURE/PARTNERSHIP INFORMATION. The selected Bidder, if a Joint Venture/Partnership, shall provide a copy of the joint venture agreement or partnership agreement evidencing authority to offer and to enter into the resulting Contract that may be awarded, together with corporate resolutions (if applicable) evidencing corporate authority to participate as a joint venturer or partner. A contact person must also be designated for purposes of receiving all notices and communications under the Contract. All partners and joint venturers will be required to sign the Contract awarded.

C.3.19.4 RESPONSIBILITY DOCUMENTATION.

3.19.4.1 RESPONSIBILITY INQUIRY FORM. The selected Bidder shall provide a completed, accurate, and signed Responsibility Inquiry form. The Responsibility Inquiry form is available at: http://www.oregon.gov/ODOT/Business/Procurement/DocsPSK/ResponsibilityInquiry.docx

C.3.19.4.2 PAY EQUITY COMPLIANCE TRAINING AND CERTIFICATION. This requirement applies to Bidders with 50 or more full-time employees that Bid on State agency contracts valued at $500,000 or more. If applicable, the selected Bidder will be required to submit a copy of an unexpired certificate (held by an authorized representative of the Bidder) issued by the Oregon Department of Administrative Services (DAS) documenting completion of the pay equity overview training. Following notice of intent to award, the selected Bidder shall submit the certificate with the Responsibility Inquiry Form prior to being awarded a Contract. For information about free on-line training and certification please click on the following hyperlink: http://www.oregon.gov/ODOT/Business/Procurement/DocsGTS/SB491Flyer.pdf

C.3.19.4.3 ADDITIONAL INFORMATION MAY BE REQUIRED. Pursuant to ORS 279C.375, OAR 137-049-0390, and OAR 137-049-0440, ODOT will evaluate the apparent successful Bidder’s responsibility to perform the Contract prior to award and execution of a Contract. Submission of a signed Offer shall constitute approval for ODOT to obtain any information ODOT deems necessary to conduct its evaluation. ODOT will notify the apparent successful Bidder, in writing, of any other documentation required, which may include, but is not limited to, recent profit-and-loss history; current balance statements; assets-to-liabilities ratio, including number and amount of secured versus unsecured creditor claims; availability of short and long-term financing; bonding capacity; credit information; material; equipment; facility and personnel information; performance record of Contract performance; etc. Failure to promptly provide this information will result in Offer rejection.

ODOT may postpone the award of the Contract after announcement of the apparent successful Bidder in order to complete its evaluation. Failure of the apparent successful Bidder to demonstrate responsibility shall render the Bidder non-responsible and shall constitute grounds for Offer rejection, as required under OAR 137-049-0390 and OAR 137-049-0440.

C.3.19.5 TAX ID NUMBER. The selected Bidder shall provide their Taxpayer Identification Number and backup withholding status on a completed W-9 form if either of the following applies:

· When requested by Agency (normally in an intent to award notice), or

· When the backup withholding status or any other information of Bidder has changed since the last submitted W-9 form, if any.

The W-9 form is available from the Internet at: http://www.irs.gov/pub/irs-pdf/fw9.pdf. No payment can be made until a properly completed W-9 is on file with Agency.

C.3.19.6 BUSINESS REGISTRY NUMBER/REGISTERED AGENT. The apparent successful Bidder must be duly authorized by the State of Oregon to transact business before executing the Agreement. Firms that contract with ODOT are responsible for compliance at all times with all applicable legal requirements regarding business organization, authorization, and registration.

· Oregon Business Registry – If requested by ODOT the apparent successful Bidder shall (unless the name of Bidder’s business includes the "real and true" name of each owner or the business is otherwise exempt under applicable laws) provide to ODOT a current Oregon Secretary of State business registry number if: a) Bidder is an Oregon business or has offices or employees located or conducting business in Oregon, or b) as a result of the prospective Agreement, Bidder will have offices or employees located, or conducting business, in Oregon. See process for obtaining a business registry number and guidance regarding exceptions (https://sos.oregon.gov/business/Pages/doing-business-means.aspx).

· Foreign Businesses – The apparent successful Bidder shall provide to ODOT a current business registry number for the state in which the business is located unless: a) the name of Bidder’s business includes the "real and true" name of each owner or the business is otherwise exempt under applicable laws or, b) Bidder is registered in Oregon and Bidder is submitting an Oregon business registry number.

· Registered Agent – All corporations and other business entities (domestic and foreign) must have a registered agent in Oregon unless an exception applies. See requirements and exceptions regarding registered agents (https://sos.oregon.gov/business/pages/registered-agents-service-of-process.aspx).

· For more information, see Oregon Business Guide, How to Start a Business in Oregon and Laws and Rules (https://sos.oregon.gov/business/pages/laws-rules.aspx). The titles in this subsection are available on the Secretary of State’s Business site: https://sos.oregon.gov/business/Pages/default.aspx.

C.3.19.7 Direct Deposit via Automated Clearing House (“ACH”). [This item is OPTIONAL] For contractors that receive ongoing monthly payments from Agency on one or more contracts or price agreements, ODOT prefers making payments via ACH direct deposit. While not required, if the selected Bidder has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, a Vendor ACH Authorization form (https://www.oregon.gov/ODOT/Forms/2ODOT/7310781.pdf) must be completed and submitted to ODOT (per the instructions on the form) after the Contract is executed. To expedite Contractor’s payments to its subcontractors, Contractor should make reasonable efforts to offer ACH direct deposit payments.

C.3.20 EXECUTION OF AGREEMENT FORM. Once all items required under Section C.3.19 have been received from the apparent successful Bidder and accepted by ODOT, ODOT will finalize and email the Public Improvement Agreement Form (see Exhibit 5) to the Bidder, which the Bidder shall sign and return by email as soon as possible, and within 2 business days of receipt. ODOT will then sign the Public Improvement Agreement Form and email a fully-executed copy of it to the Bidder.

SECTION D - BID SECURITY REQUIREMENTS – RESERVED – NOT REQUIRED

SECTION E – PREVAILING WAGE REQUIREMENTS

Pursuant to ORS 279C.800 through 279C.870, the Contractor and all subcontractors are required to pay Prevailing Wage Rates (“PWRs”) for any contract valued at more than $50,000.

E.1 The Contractor and all subcontractors shall comply with the provisions of ORS 279C.800 through 279C.870, relative to PWRs and the required public works bond as outlined in Sections C.1, C.2 & G.2.3 of the General Conditions.

E.2 Before starting Work the Contractor shall file with the Construction Contractors Board, and maintain in full force and effect, the separate public works bond required by ORS 279C.836 and OAR 839-025-0015, unless otherwise exempt under those provisions. The Contractor shall also include in every subcontract a provision requiring the Subcontractor to have a public works bond filed with the Construction Contractors Board before starting Work, unless otherwise exempt, and shall verify that the Subcontractor has filed a public works bond before permitting the Subcontractor to start Work.

E.3 This ITB and the resulting Contract are subject to the following Bureau of Labor and Industries (“BOLI”) prevailing wage rate requirements and the prevailing wage rates set forth in the following rate book which, while not physically attached, is incorporated herein by reference with the same force and effect as though fully set forth herein:

BOLI “PREVAILING WAGE RATES for Public Works Contracts in Oregon” dated January 5, 2024 and as amended April 5, 2024 These BOLI wage rates are available on line at:

https://www.oregon.gov/boli/employers/Pages/prevailing-wage-rates.aspx

E.4 The Work will take place in Tillamook County, BOLI Region 1

E.5 The fee required by ORS 279C.825(1) will be paid by the Agency to the Commissioner of the Bureau of Labor and Industries under the administrative rules of the Commissioner.

SECTION F – FIRST-TIER SUBCONTRACTOR DISCLOSURE – RESERVED – NOT REQUIRED

SECTION G –LICENSING REQUIREMENTS; JOINT VENTURE - PARTNERSHIP DISCLOSURE

G.1 CONSTRUCTION CONTRACTORS BOARD (CCB) REQUIREMENTS

G.1.1 Bidder must be licensed with the State of Oregon CCB (ORS Chapter 701) prior to bidding on Public Improvement Contract(s). FAILURE TO COMPLY WITH THIS REQUIREMENT SHALL RESULT IN BID REJECTION. Bidder shall provide its CCB license number and expiration date in the spaces provided in Section I – Bidder Information.

G.1.2 All Subcontractors participating in the project shall be similarly licensed with the CCB prior to engaging in subcontract work. The CCB license requirements apply to all public works contracts unless superseded by federal law.

G.2 RESERVED

G.3 ASBESTOS ABATEMENT LICENSING REQUIREMENTS

An asbestos abatement license under ORS 468A.720 will not be required of the Contractor or its subcontractors.

G.4 JOINT VENTURE/PARTNERSHIP DISCLOSURE

Is this Offer being submitted by a partnership or joint venture?

NO: ________ YES: _______

If yes, Bidder shall provide the name of the contact person for the partnership or joint venture.

Name: __________________________________________________________

SECTION H - ADDENDA ACKNOWLEDGEMENT

H.1 ODOT reserves the right to make changes to the Invitation to Bid and the resulting Contract, by written Addendum, prior to the Bid Opening Date and time specified in OregonBuys for this ITB. Addenda will be advertised on the OregonBuys System. ODOT is not responsible for a Bidder’s failure to receive notice of Addenda if such are advertised in the foregoing manner. Addenda shall only be issued by the ODOT Procurement Office and upon issuance are incorporated into the Invitation to Bid or the resulting Contract. If required by the Addendum, Bidder shall sign and return the Addendum prior to the Bid Opening Date and time.

H.2 By Bidder’s signature in Section O of this ITB, BIDDER ACKNOWLEDGES, AGREES and CERTIFIES TO THE FOLLOWING:

H.2.1 If any Addenda are issued in connection with this ITB, Bidder has received and duly considered such Addenda, and has completed…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .