Contract amount
$631,020

Award facts

Completion date

Award details come from statecontracts.nebraska.gov. Updated .

About this award

The Nebraska Department of Transportation awarded a right-of-way mowing services contract to C5 Mowing LLC, a Nebraska-limited liability company based in McCook, Nebraska, and managed by Scott Repass. The contract (NH2301) was executed on June 5, 2026, with a contract value of $631,019.90 covering the period from June 5, 2026, through June 4, 2027. Services are performed in District 7, Area 720, encompassing approximately 7,471.85 acres of right-of-way maintenance across the designated service area.

Under the contract terms, C5 Mowing LLC provides comprehensive mowing services including all labor, equipment, fuel, materials, and required insurance coverage. The work consists of three mowing cycles conducted between May 1 and October 31 annually: a first cycle with 15-foot cutting width between May 1 and June 7, a second cycle with 15-foot cutting width between June 25 and August 15, and a third cycle with 30-foot cutting width between September 1 and October 31. Machine rotary mowing is performed at specified cutting heights of 6 inches with 1-inch tolerance (minimum 5 inches), supplemented by hand mowing around obstructions. The contractor must maintain performance bonds, comprehensive insurance coverage including workers' compensation and commercial liability, and comply with all environmental and safety requirements. The contract includes provisions for three optional one-year renewal periods at mutually agreed terms, with optional pricing available for additional mowing locations within the District Superintendent's area.

Line items

Item Total
Highway ROW Mowing: Contractor shall be responsible for providing all labor, equipment, fuel, materials and insurance to properly accomplish right-of-way mowing services as specified in the RFP. 7,471 Acre × $22.15 $165,482.65
Contract price for right-of-way mowing per acre for additional locations within the District Superintendent Area that are not specified in the mowing schedule. $22.15 per acre —
Highway ROW Mowing: Contractor shall be responsible for providing all labor, equipment, fuel, materials and insurance to properly accomplish right-of-way mowing services as specified in the RFP. 7,471 Acre × $22.15 $165,482.65
Contract price for right-of-way mowing per acre for additional locations within the District Superintendent Area that are not specified in the mowing schedule. $22.15 per acre —
Highway ROW Mowing: Contractor shall be responsible for providing all labor, equipment, fuel, materials and insurance to properly accomplish right-of-way mowing services as specified in the RFP. 7,471 Acre × $22.15 $165,482.65
Contract price for right-of-way mowing per acre for additional locations within the District Superintendent Area that are not specified in the mowing schedule. $22.15 per acre —
Highway ROW Mowing: Contractor shall be responsible for providing all labor, equipment, fuel, materials and insurance to properly accomplish right-of-way mowing services as specified in the RFP. 7,471 Acre × $21.50 $160,626.50
Contract price for right-of-way mowing per acre for additional locations within the District Superintendent Area that are not specified in the mowing schedule. $21.50 per acre —
Highway ROW Mowing: Contractor shall be responsible for providing all labor, equipment, fuel, materials and insurance to properly accomplish right-of-way mowing services as specified in the RFP. 7,271 Acre × $21.50 $156,326.50
Highway ROW Mowing: Contractor shall be responsible for providing all labor, equipment, fuel, materials and insurance to properly accomplish right-of-way mowing services as specified in the RFP. 7,471 Acre × $19.90 $148,672.90
Highway ROW Mowing: Contractor shall be responsible for providing all labor, equipment, fuel, materials and insurance to properly accomplish right-of-way mowing services as specified in the RFP. 7,471 Acre × $20.90 $156,143.90
Contract price for right-of-way mowing per acre for additional locations within the District Superintendent Area that are not specified in the mowing schedule. $19.90 per acre —
Contract price for right-of-way mowing per acre for additional locations within the District Superintendent Area that are not specified in the mowing schedule. $20.90 per acre —
Show all 13

Files

File Type Posted
NH2301_003.pdf PDF
NH2301_002.pdf PDF
NH2301_000.pdf PDF
NH2301_001.pdf PDF

Quick answers

Who was awarded contract 104776?

Contract 104776 was awarded to C5 MOWING LLC by Dept of Transportation in Nebraska on June 5, 2026.

How much is contract 104776 worth?

Its contract amount is $631,020.

On GovTribe

See this award's full record

  • Every line item and file
  • The contract it was ordered under and its other orders
  • Similar state and local awards and opportunities
  • Ask GovTribe AI about this award