CA ftnp/NPS yose 500(2)16(7) valley loop & EL portal road repairs

Ended Definitive Contract Awarded Last action

Contract number
DTFH6816C00030
Awardee
Awarding agency
Obligated
$17,488,002

Award facts

Opportunity
Contract value 100% obligated
$17,488,001.78 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Yosemite National Park, California, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 33 · Modification to deobligate remaining funding and closeout this contract. -$632,710
Supplemental Agreement for work within scope 32 · CA ftnp/NPS yose 500(2)16(7) valley loop & EL portal road repairs final settlement agreement $0
Other Administrative Action 31 · Administrative modification to update lines of accounting $0
Definitize Change Order 30 · Wawona road fire definitization modification $40,981
Other Administrative Action 29 · Correcting mods 27 and 28; account string on approved PR. CA ftnp/NPS yose 500(2)16(7) valley loop & EL portal road repairs $0
Definitize Change Order 28 · MOD to definitize MOD 25 actions/costs CA ftnp/NPS yose 500(2)16(7) valley loop & EL portal road repairs -$87,775
Change Order 27 · Post-fire mitigation work and repairs $0
Supplemental Agreement for work within scope 26 · Repairs to a damaged unmarked waterline -$201
Change Order 25 · Repairs to forest area roads as a result of the august 2018 ferguson fire. Work includes roadway reconditions, rolling DIP installation, surface course… $0
Supplemental Agreement for work within scope 24 · Waste disposal for pohono PIT and time extension $0
Supplemental Agreement for work within scope 23 · Time extension due to ferguson fire delay $0
Supplemental Agreement for work within scope 22 · Addition of portable toilets to camp 4 and supply and delivery of materials to the national park service. -$7,768
Funding Only Action 21 · Funding change $0
Supplemental Agreement for work within scope 20 · Time extension and installation of 4350 linear feet of split rail fence. -$90
Supplemental Agreement for work within scope 18 · Settlement of time acceleration costs -$249
Definitize Change Order 19 · Definitize change order modification 0014 -$471
Supplemental Agreement for work within scope 17 · Parking lot change from aggregate surface course to hot asphalt concrete pavement change and other minor additions to parking lots. -$1,045
Definitize Change Order 15 · Curb definitization -$9,319
Supplemental Agreement for work within scope 16 · Geogrid stabilization -$158
Change Order 14 · Change order to add wheelstops to CAMP4 $0
Other Administrative Action 13 · Time extension modification $0
Supplemental Agreement for work within scope 12 · Southside road repair addition $37,752
Supplemental Agreement for work within scope 11 · Addition of an underdrain to project $23,183
Definitize Change Order 10 · Culvert MOD definitization $0
Funding Only Action 9 · Funding change - admin MOD $0
Supplemental Agreement for work within scope 8 · Admin MOD $0
Supplemental Agreement for work within scope 7 · Installation of 2" waterline -$2,375
Supplemental Agreement for work within scope 6 · Concrete curb adjustment $90,000
Other Administrative Action 4 · Change road closure information on project $0
Supplemental Agreement for work within scope 5 · Add culvert replacement -$75
Other Administrative Action 3 · Add utility potholing to contract $89,450
Supplemental Agreement for work within scope 2 · Additional riprap added to project $0
Supplemental Agreement for work within scope 1 · Modification to add 4" waterline $0
Original award $17,948,872
Show all 34

About this award

This is a $17,488,001.78 firm fixed-price definitive contract awarded by the Federal Highway Administration, a civilian agency, to the prime contractor George Reed Inc. The contract is for repairs to the Valley Loop and El Portal Road in Yosemite National Park. This is not a set-aside contract. George Reed Inc. is a for-profit company that provides concrete supply services as a subcontractor on federal construction projects. In this case, George Reed has provided concrete supply support to the Flatiron-Dragados-Sukut Joint Venture, the prime contractor on the Yosemite National Park road repair project. The contract has a period of performance ending on March 21, 2019.

Quick answers

Who was awarded contract DTFH6816C00030?

DTFH6816C00030 was awarded to George Reed Inc. by Federal Highway Administration (Department of Transportation) on July 27, 2016.

How much is contract DTFH6816C00030 worth?

The government has obligated $17,488,002 on DTFH6816C00030.

Was contract DTFH6816C00030 competed?

The extent of competition for DTFH6816C00030 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award