THIS IS A DESIGN BUILD MULTIPLE AWARD CONSTRUCTION CONTRACT (DB-MACC) PROJECT INTENDED TO REPLACE AND RELOCATE THE DUST COLLECTOR SYSTEM FROM THE PACKING AND CRATING AREA TO THE EXTERIOR OF BUILDING 2118. OTHER WORK INCLUDES RELOCATE AIR COMPRESSOR AND CONSTRUCT ENCLOSURE TO HOUSE THE DUST COLLECTOR AND AIR COMPRESSOR UNIT. A. THE CONTRACTOR SHALL PROVIDE ALL DESIGN, LABOR, MATERIAL, EQUIPMENT, COMPLETE AND READY FOR USE, IN ACCORDANCE WITH THE STATEMENT OF WORK (SOW), DATED 24 JANUARY 2013 FOR WR 6106303, AND MODERN INTERNATIONAL S PROPOSAL DATED 25 FEBRUARY 2013. B. LIQUIDATED DAMAGES IN THE AMOUNT OF $200.00 SHALL BE ASSESSED FOR EACH CALENDAR DAY OF DELAY UNTIL THE WORK IS COMPLETED OR ACCEPTED. C. THE SITE SAFETY AND HEALTH OFFICER FOR THIS PROJECT SHALL MEET THE REQUIREMENTS OF LEVEL 2. D. THE PERFORMANCE PERIOD IS 270 CALENDAR DAYS AFTER THE DATE OF AWARD UP TO AND INCLUDING 02 DECEMBER 2013. E. THE ASSIGNED CONTRACT SPECIALIST, CONSTRUCTION MANAGEMENT ENGINEER, AND ENGINEERING TECHNICIAN WILL BE PROVIDED BY THE CONTRACTING OFFICER PRIOR TO START OF WORK.