Replace asbestos sewer pipe (cany 230753 ) and non-functional fire pump at the maze district (cany 241190), canyonlands national park, UT

Ended Awarded Last action

Contract number
140P1218F0136
Awardee
Awarding agency
Obligated
$267,801

Award facts

Contract value 100% obligated
$267,801.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Moab, UT 84532, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00005 · Modification to extend the period of performance end date from april 15, 2019 to may 1, 2019 to allow for final inspection and commissioning; canyonlands… $0
Definitize Change Order P00004 · Modification to definitize change order modification P00003 and extend the period of performance end date from march 31, 2019 to april 15, 2019 to allow for… $30,682
Change Order P00003 · Unilateral change order modification to incorporate within scope work; canyonlands national park, sewer line/fire pump, cany 230753 & 241190 $0
Supplemental Agreement for work within scope P00002 · No cost modification to extend the period of performance end date from february 15, 2019 to march 31, 2019, to allow for completion of the project. Delay due to… $0
Supplemental Agreement for work within scope P00001 · No cost modification to extend the period of performance end date from december 31, 2018 to february 15, 2019 due to an extended lead time for the fire pump… $0
Original award $237,119

About this award

This firm fixed-price delivery order was awarded by the Department of the Interior's National Park Service Intermountain Region to Bairco Construction Inc., a minority-owned, woman-owned small business, to replace asbestos sewer pipe and a non-functional fire pump at the Maze District in Canyonlands National Park, Utah. The $267,801.00 contract has a completion date of May 1, 2019. Bairco Construction Inc. has been awarded over $30 million in federal contracts from agencies like the National Park Service and Bureau of Reclamation to provide general construction services, including infrastructure repairs and facility improvements in National Parks and recreation areas.

Quick answers

Who was awarded contract 140P1218F0136?

140P1218F0136 was awarded to Bairco Construction Inc. by Intermountain Region (National Park Service) on September 17, 2018.

How much is contract 140P1218F0136 worth?

The government has obligated $267,801 on 140P1218F0136.

Is contract 140P1218F0136 an order under another contract?

Yes. 140P1218F0136 is a delivery order under INP15PC00784, an indefinite delivery contract.

Was contract 140P1218F0136 competed?

The extent of competition for 140P1218F0136 was full and open competition after exclusion of sources. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award