Construct RV sites at sanford yake part of lake meredith national recreation area, fritch, texas. Scope of work: all work, terms and conditions, clauses and provisions, as stated in task order request…

Ended Awarded Last action

Contract number
INP17PD02281
Awardee
Awarding agency
Obligated
$370,344

Award facts

Contract value 100% obligated
$370,344.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Fritch, TX 79036, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00001 $62,000
Original award $308,344

About this award

The Department of the Interior's National Park Service Intermountain Region awarded a firm fixed price delivery order worth $370,344.00 to Ridgway Valley Enterprises Inc., a small business commercial general contractor, to construct new RV sites at the Sanford Yake Part of Lake Meredith National Recreation Area in Fritch, Texas. The contract was issued under the National Park Service Intermountain Region's MATOC 2021-2026 multiple award IDIQ contract vehicle and does not have a set-aside designation. The scope of work includes site assessment and survey, design, and construction of ten concrete RV site pads, with completion required by May 30, 2018. Ridgway Valley Enterprises has been awarded multiple delivery orders from the National Park Service Intermountain Region totaling over $9.5 million since 2019 for construction, facilities maintenance, and infrastructure rehabilitation services across national parks in the Intermountain West region.

Description

Construct RV sites at sanford yake part of lake meredith national recreation area, fritch, texas. Scope of work: all work, terms and conditions, clauses and provisions, as stated in task order request T0040338372, with all attachments, is herein expressly incorporated into this contract, less line item 4 living areas. Contract line item no. 1 site assessment and survey: this item consists of a site visit to provide recommendations and a detailed scope of work. This work also consists of conducting a survey of the proposed location to reveal and identify weaknesses in existing and planned use. This item also consists of a topographic survey of sufficient detail to complete design and construction of the facility. Contract line item no. 2 design: this item consists of engineer drawings and specifications, product datasheets, shop drawings, schematics, and records of detailed analysis. Also includes providing schematic drawings, final drawings and specifications, cost proposals for construction, and layout plans. This item also includes the costs of getting the permits and NPS approval for construction, which includes any permit application fees. Contract line item no. 3 concrete RV site pads: this item consists of the construction and installation of ten concrete RV site pads. Construction shall comply with industry standards. Payment shall be full compensation for all material and assembly related to the concrete pad; clearing; excavation; restoration of all existing roads, sidewalks, and driveways, protection of existing utilities; compaction; grading; provision of record drawings as-builts, supplementary construction staking, testing, and all equipment and materials required. This also includes final grading disturbed areas with native topsoil, revegetation, and bringing to final grade. This item also includes mobilization, costs of preparatory work and operations, including but not limited to those necessary for the movement of personnel, equipment, supplies, materials and incidentals to the project site, site facilities necessary for the work on the project, sanitary facilities, traffic control, all other work or costs necessary for the completion of the project, inspections, testing, system startup, project closeout, punchlists, final cleanup and demobilization from the project site upon completion of work. Also included are costs related to fees, permits, licenses, insurance, bonds, taxes and all other costs that the contractor is to obtain or pay to perform the work. Finally, IT includes construction management and inspection. Contract line item 4 living areas has been removed from this contract.

Quick answers

Who was awarded contract INP17PD02281?

INP17PD02281 was awarded to Ridgway Valley Enterprises Inc. by Intermountain Region (National Park Service) on August 8, 2017.

How much is contract INP17PD02281 worth?

The government has obligated $370,344 on INP17PD02281.

Is contract INP17PD02281 an order under another contract?

Yes. INP17PD02281 is a delivery order under INP13PC00009, an indefinite delivery contract.

Was contract INP17PD02281 competed?

The extent of competition for INP17PD02281 was full and open competition after exclusion of sources. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award