US bankruptcy design build space consolidation at martin luther king, JR. Federal courthouse, newark, NJ

Ended Awarded Last action

Contract number
47PC1018F0001
Awardee
Awarding agency
Obligated
$860,579

Award facts

Contract value 100% obligated
$860,579.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Headquarters Division Federal Bureau of Investigation, Department of Justice
Set-aside
No set-aside
Competition
Competed under SAP Simplified Acquisition
Pricing
Firm Fixed Price
Place of performance
Newark, NJ 07102, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA0008 · The purpose for this mass modification change is to change the designated billing office code to bcfa and the designated billing office address code to 0001. $0
Change Order PC0007 · PDN EN47PC1018F0001 task order number 47PC1018F0001 US bankruptcy court design build space consolidation, MLK federal courthouse, 50 walnut street, newark, NJ… $8,087
Change Order PC0006 · PDN EN47PC1018F0001 US bankruptcy design build space consolidation, MLK federal courthouse, 50 walnut street, newark, NJ this modification PC0006 under task… $0
Funding Only Action PA0005 · Design build space consolidation at MLK federal courthouse, newark, NJ $16,450
Change Order PC0004 · Design build space consolidation for US bankruptcy courts newark, NJ $0
Change Order PC0002 · US bankruptcy DB space consolidation design and construction changes @ MLK federal courthouse 50 walnut street, newark, NJ $13,500
Change Order PC0001 · Revision of design build space consolidation project at US bankruptcy courts, 50 walnut street, newark, NJ $10,400
Original award $812,142

About this award

The Department of Justice Federal Bureau of Investigation Headquarters Division (DOJ - FBI) awarded a firm fixed price delivery order contract to DCM Architecture & Engineering, LLC - doing business as DCM for the United States Bankruptcy Design Build Space Consolidation at the Martin Luther King, Jr. Federal Courthouse in Newark, New Jersey. The scope of work involved consolidating bankruptcy court space at the courthouse with a start date of October 20, 2017 and an end date of April 30, 2019. The place of performance was specified as Newark, New Jersey 07102. This contract aimed to consolidate bankruptcy court space through a design-build approach, leveraging DCM's expertise in architecture and engineering to streamline the project delivery process within the given timeframe and budget at the Martin Luther King, Jr. Federal Courthouse location in Newark.

Quick answers

Who was awarded contract 47PC1018F0001?

47PC1018F0001 was awarded to DCM Architecture & Engineering, LLC by Region 2 (Public Buildings Service) on October 20, 2017.

How much is contract 47PC1018F0001 worth?

The government has obligated $860,579 on 47PC1018F0001.

Which agency awarded contract 47PC1018F0001?

Region 2 (Public Buildings Service) awarded 47PC1018F0001, with funding from Headquarters Division (Federal Bureau of Investigation).

Is contract 47PC1018F0001 an order under another contract?

Yes. 47PC1018F0001 is a delivery order under GS02P17PED0001, an indefinite delivery contract.

Was contract 47PC1018F0001 competed?

The extent of competition for 47PC1018F0001 was competed under sap.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award