WY PRA yell 10(19) grand loop road, norris to golden gate, phase 2 completion contract
Ended Awarded Last action
- Contract number
- 0002
- Awardee
-
H-K Contractors, Inc. UEI FPM7V1ZC8WU2
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $37,689,773
Award facts
- Contract value 100% obligated
- $37,689,772.53 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 3 offers Multiple Award, Fair Opportunity
- Pricing
- Fixed Price with Economic Price Adjustment
- Place of performance
- Yellowstone National Park, WY 82190, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | -$666,827 | |
| Supplemental Agreement for work within scope | -$2,147,068 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $19,805 | |
| Supplemental Agreement for work within scope | -$53,898 | |
| Supplemental Agreement for work within scope | $8,975 | |
| Supplemental Agreement for work within scope | $164,209 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$4,139 | |
| Supplemental Agreement for work within scope | -$199,488 | |
| Supplemental Agreement for work within scope | -$29,455 | |
| Supplemental Agreement for work within scope | -$92,666 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $428,000 | |
| Supplemental Agreement for work within scope | -$6,630 | |
| Supplemental Agreement for work within scope | -$1,911 | |
| Definitize Change Order | $0 | |
| Definitize Change Order | $38,765 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $1,692 | |
| Supplemental Agreement for work within scope | $247,902 | |
| Supplemental Agreement for work within scope | $12,676 | |
| Supplemental Agreement for work within scope | $4,870 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $104,052 | |
| Supplemental Agreement for work within scope | -$19,566 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $168,475 | |
| Funding Only Action | $315,000 | |
| Supplemental Agreement for work within scope | $3,750 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$1,826 | |
| Supplemental Agreement for work within scope | $49,073 | |
| Supplemental Agreement for work within scope | -$16,907 | |
| Supplemental Agreement for work within scope | -$429,837 | |
| Supplemental Agreement for work within scope | $378,891 | |
| Supplemental Agreement for work within scope | $16,337 | |
| Change Order | $225,000 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$162,678 | |
| Supplemental Agreement for work within scope | $203,630 | |
| Supplemental Agreement for work within scope | $92,821 | |
| Supplemental Agreement for work within scope | $50,415 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
This is a $37,689,772.53 fixed price with economic price adjustment delivery order contract awarded by the Department of Transportation Federal Highway Administration to H-K Contractors, Inc., a for-profit construction company. The contract is for the completion of Phase 2 of the WY PRA YELL 10(19) Grand Loop Road project, which involves road construction and rehabilitation work within Yellowstone National Park. No set-aside designation was used.
H-K Contractors utilized several subcontractors to perform specialized tasks such as electrical work, blasting, excavation, crushing, kiosk construction, clearing and grubbing, micropiles, concrete, traffic control, pavement markings, guardrail installation, and milling. Notable subcontractors included Wheeler Electric Inc., Barnes Inc., All Mountain Inc., Evans Construction Company, Oftedal Construction, Inc., and Poteet Construction Inc. The contract is part of the Yellowstone, Grand Teton, and Surrounding Area 2014-2019 multiple award contract vehicle managed by the DOT FHWA.
Quick answers
Who was awarded contract 0002?
0002 was awarded to H-K Contractors, Inc. by Federal Highway Administration (Department of Transportation) on April 10, 2017.
How much is contract 0002 worth?
The government has obligated $37,689,773 on 0002.
Is contract 0002 an order under another contract?
Yes. 0002 is a delivery order under DTFH7014D00004, an indefinite delivery contract, on Yellowstone, Grand Teton, and Surrounding Area 2014-2019.
Was contract 0002 competed?
The extent of competition for 0002 was full and open competition. The government received 3 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award