Construction - spirit lake tunnel inlet repair
Active Definitive Contract Awarded Last action
- Contract number
- W9127N23C0007
- Awardee
-
Advanced American Construction, Inc. UEI C2SKL5QBJRD3
- Awarding agency
-
ENDIST Portland
US Army Corps of Engineers, Department of Defense
- Obligated
- $22,338,439
Award facts
- Opportunity
-
- Mount ST. Helens spirit lake intake headwall Pre-Solicitation · W9127N22R0020 · Posted Mar 8, 2021
- Contract value 99% obligated
- $22,502,374.99 Current and potential, with all options
- Completion date 71% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z2KA Repair Or Alteration Of Dams
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 6 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Stevenson, WA 98648, USA
- Legislative mandates
-
- Service Contract Act FAR subpart 22.10
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $160,385 | |
| Supplemental Agreement for work within scope | -$48,946 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Original award | $22,227,000 |
About this award
The U.S. Army Corps of Engineers Portland District awarded a $22.3 million definitive contract to Advanced American Construction, Inc. for construction of Spirit Lake Tunnel Inlet Repair and crushed concrete aggregate procurement on April 30, 2023, under a total small business set-aside. Advanced American Construction is a small disadvantaged business.
The originating pre-solicitation, posted in March 2021, sought capability statements for replacement of the aging intake gate and repairs at the Mount St. Helens Spirit Lake headwall. The project scope includes a 3-mile temporary access road, barge loading facility, mechanical dredging from barges or floating platforms, cofferdam design and construction, and replacement of inlet and slide gates in a remote, environmentally sensitive area with limited cellular service. Place of performance is Stevenson, WA. The contract carries a firm fixed price and an ultimate completion date of April 1, 2028.
Quick answers
Who was awarded contract W9127N23C0007?
W9127N23C0007 was awarded to Advanced American Construction, Inc. by ENDIST Portland (US Army Corps of Engineers) on April 30, 2023.
How much is contract W9127N23C0007 worth?
The government has obligated $22,338,439 on W9127N23C0007. Its current value, with exercised options, is $22,502,375.
Was contract W9127N23C0007 competed?
The extent of competition for W9127N23C0007 was full and open competition after exclusion of sources. The government received 6 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award