Definitize Change Order
PS57 · Construction for laredo 1 & 2 ports of entry, laredo, texas modification PS55 is issued to definitize the price determined later (PDL) modification numbers…
$554,012
Change Order
PS56 · Contract modification to extend the contract completion date from august 30, 2019 to january 6, 2019; modernization of the laredo 1 & 2 port of entry in…
$0
Supplemental Agreement for work within scope
PS55 · The contract completion date is changed from august 9, 2019 to august 30, 2019. Location laredo, TX
$0
Supplemental Agreement for work within scope
PS54 · Contract modification (PS52) is for the compensability portion of request for equitable adjustment (REA) 003, dated june 10, 2019 for the construction…
$1,653,171
Supplemental Agreement for work within scope
PS53
-$97,082
Supplemental Agreement for work within scope
PS52
$0
Supplemental Agreement for work within scope
PS51
$0
Supplemental Agreement for work within scope
PS50
$599,534
Change Order
PC49
$319,580
Change Order
PC48
$482,083
Definitize Change Order
PS47 · Contract GS-07-p-15-HH-c-7001 construction for laredo 1 & 2 ports of entry, laredo, texas modification PS45 (easi MOD PS47) modification PS45 is issued to…
$728,102
Supplemental Agreement for work within scope
PS46 · Description of amendment/modification contract GS-07-p-15-HH-c-7001 construction for laredo 1 & 2 ports of entry, laredo, texas modification PS44 (easi MOD…
$369,105
Change Order
PC45 · This modification is to address various items at the convent and j & l port of entry, modernization project in laredo, texas.
$75,736
Supplemental Agreement for work within scope
PS44 · This modification is to extend the contract time at j & l port of entry, modernization project in laredo, texas.
$0
Change Order
PC43 · Modification PC41 is to add additional bus processing booths at j & l port of entry, modernization project in laredo, texas.
$164,292
Change Order
PC42 · Modification PC40 is for miscellaneous completion items at the convent and j & l port of entries, modernization project in laredo, texas.
$12,864
Definitize Change Order
PS41 · Modification PS39 is to definitize modifications PC23, PC24, PC26 & PC30 for the convent & j&l port of entries, modernization project in laredo, texas.
$453,401
Change Order
PC40 · Modification PC38 is a price determined later (PDL) MOD is for construction services for several items necessary to complete the construction modernization…
$196,852
Supplemental Agreement for work within scope
PS39 · Modification PS37 is for time extension for the convent AVE. Port of entry, bridge 1, modernization project in laredo, texas.
$0
Change Order
PC38 · Modification PC36 is for miscellaneous items necessary for the completion of the convent AVE. Port of entry and phase 2 of juarez-lincoln port of entry…
$401,150
Supplemental Agreement for work within scope
PS37 · This modification is to compensate the contractor for the time impact for delays associated at juarez lincoln port of entry modernization project in laredo,…
$0
Supplemental Agreement for work within scope
PS36 · Modification PS34 is for pre-settlement costs for request for equitable adjustment 002 for the convent AVE. Port of entry modernization in laredo, texas.
$324,540
Supplemental Agreement for work within scope
PS35 · Modification PS33 is to incorporate architectural supplemental instruction (ASI) #09 into the contract for the convent and juarez lincoln port of entry…
$317,213
Supplemental Agreement for work within scope
PS34 · Modification PS32 is to incorporate architectural supplemental instruction (ASI) #11 into the contract for the convent and juarez lincoln port of entry…
$706,311
Supplemental Agreement for work within scope
PS33 · Modification PS31 is for several modifications required at the juarez- lincoln ports or entry in laredo, texas.
$85,360
Change Order
PC32 · This a price determined later (PDL) modification to add a bridge expansion joint for the convent avenue port of entry construction modernization project in…
$20,290
Change Order
PC31 · This a price determined later (PDL) modification for CBP requested security and office of information technology (OIT) changes at bridge 1 & 2 port of…
$677,231
Definitize Change Order
PS30 · Modification PS28 is issued to definitize PC21 for CBP requested security and OIT changes at bridge 1 & 2 port of entries, laredo TX.
$0
Definitize Change Order
PS29 · This modification is issued to definitize PC18 for unforeseen structural issues at the convent port of entry, laredo, texas.
$70,983
Change Order
PC28 · This is a price determined later (PDL) modification to address water leakage, and floor preparation and finishes at the convent port of entry, laredo TX.
$5,000
Supplemental Agreement for work within scope
PS27 · Modification PS25 is issued to extend the period of performance for the convent AVE, bridge 1, port of entry, laredo, texas.
$0
Change Order
PC26
$436,235
Change Order
PC25 · This a price determined later (PDL) modification for CBP requested security and office of information technology (OIT) changes at bridge 1 & 2 port of…
$573,743
Supplemental Agreement for work within scope
PS24 · This modification is for several window glass replacements at the convent avenue port of entry in laredo, texas.
$68,141
Change Order
PC23 · This a price determined later (PDL) modification for CBP requested security and OIT changes at bridge 1 & 2 port of entries, laredo TX
$477,837
Supplemental Agreement for work within scope
PS22 · Modification PS20 is issued for additional construction services needed to remediate unforeseen cisterns found at laredo 1 & 2 ports of entry, laredo, texas.
$315,126
Other Administrative Action
PA21 · This is an administrative modification to correct the designated billing office (DBO) for the laredo 1 & 2 ports in laredo, texas.
$0
Change Order
PC20 · Modification PC18 is a price determined later modification for unforeseen structural issues at the convent port of entry, laredo, texas.
$97,000
Supplemental Agreement for work within scope
PS19 · Modification PS17 is issued to add scope for security system and OIT conduit rough-in at laredo 1 & 2 ports of entry, laredo, texas.
$51,775
Supplemental Agreement for work within scope
PS18 · Modification PS16 is for several modifications required to address unforeseen field conditions and functional requirements of the project not previously…
$97,366
Supplemental Agreement for work within scope
PS17 · Modification PS15 is to additional scope for walker duct and fire riser at the laredo 1 & 2 ports or entry in laredo, texas.
$75,868
Supplemental Agreement for work within scope
PS16 · This modification is to definitize the price to be determined later (PDL) MOD PC09 at the bridge 1 & 2 point of entry in laredo, TX.
-$2,782
Supplemental Agreement for work within scope
PS15 · This modification is for office of information technology (OIT) related changes to requirements involving OIT and miscellaneous alterations to the temporary…
$80,642
Change Order
PC14 · This a price determined later (PDL) modification for work needed to remedy the unforeseen conditions by repair / replacing affected section(s) of the…
$50,000
Other Administrative Action
AA13 · This is an administrative modification to correct line items 0002 and 00010. Total obligation remains unchanged. This is for bridge 1 & 2 port of entry…
$0
Supplemental Agreement for work within scope
PS12 · This modification is to address unforeseen field conditions and revised functional requirements of the project at bridge 1 & 2 port of entry, laredo, TX.
$99,258
Change Order
PC11 · This a price determined later (PDL) modification for miscellaneous work needed as a result of differing site conditions and customer changes at bridge 1 & 2…
$646,152
Definitize Change Order
PS10 · This modification is to definitize the price to be determined later (PDL) MOD PC05 at the bridge 1 & 2 point of entry in laredo, TX.
$315
Supplemental Agreement for work within scope
PS09 · This modification is to incorporate revised convent drawings and specifications to the laredo convent avenue bridge 1 port of entry, laredo, TX.
-$6,728
Supplemental Agreement for work within scope
PS07 · This modification is for additional cooling units at the juarez-lincoln point of entry building 4 in laredo, TX.
This is a $100,897,309.00 firm fixed-price definitive contract awarded by the General Services Administration (GSA) Region 7 to Brasfield & Gorrie LLC, a large construction firm, for construction services related to the Juarez-Lincoln Bridge 2 at the Laredo 1 and 2 Ports of Entry in Laredo, Texas. The contract has an ultimate completion date of January 6, 2020 and was awarded on June 24, 2015. Brasfield & Gorrie holds two significant indefinite delivery/indefinite quantity (IDIQ) contract vehicles with the GSA and U.S. Coast Guard, which provide sustained opportunities for federal infrastructure development projects. This contract was awarded through full and open competition and does not have a set-aside designation.
Quick answers
Who was awarded contract GS07P15HHC7001?
GS07P15HHC7001 was awarded to Brasfield & Gorrie LLC by Region 7 (Public Buildings Service) on June 24, 2015.
How much is contract GS07P15HHC7001 worth?
The government has obligated $100,897,309 on GS07P15HHC7001.
Was contract GS07P15HHC7001 competed?
The extent of competition for GS07P15HHC7001 was full and open competition. The government received 2 offers.