Close Out
PA77 · Measurement systems laboratory NASA langley research center. New construction. All work has been completed and contractor has been paid in full. This contract…
$0
Supplemental Agreement for work within scope
PS76 · NASA measurement systems laboratory - new construction. Modification to settle outstanding items. Building is complete and occupied.
$115,000
Supplemental Agreement for work within scope
PS74 · Measurement systems laboratory at NASA langley research center. Equitable adjustment for work completed. Completion date remains the same.
$220,000
Supplemental Agreement for work within scope
PS73 · New construction - measurement systems laboratory at the NASA langley research center. Equitable adjustment for services rendered.
$1,563,311
Supplemental Agreement for work within scope
PS72 · Measurement systems laboratory at the NASA langley research center, hampton, VA. Reimbursement for permit fee. No other changes.
$473
Supplemental Agreement for work within scope
PS71 · Measurement systems laboratory at NASA langley research center - equitable adjustment. No other changes.
$268,015
Supplemental Agreement for work within scope
PS70 · Measurement systems laboratory at the NASA langley research center, hampton, VA. Supplemental work within contract.
$476,516
Supplemental Agreement for work within scope
PS69 · Measurement systems laboratory at NASA langley research center, hampton, VA. Supplemental changes to the contract. Completion date remains the same.
$35,027
Supplemental Agreement for work within scope
PS68 · Measurement systems laboratory, NASA langley research center, hampton, VA. Supplemental changes within contract.
$5,335
Supplemental Agreement for work within scope
PS67 · Measurement systems laboratory, new construction, NASA langley research center - MOD to reflect changes made to requirements. Completion date remains the same.
$9,376
Supplemental Agreement for work within scope
PS66 · Measurement systems laboratory - new construction - modification to document changes within scope. Completion date remains the same.
$2,362
Supplemental Agreement for work within scope
PS65 · New construction measurement systems laboratory at NASA langley research center, hampton, VA. Changes to contract. Completion date remains the same.
$23,272
Change Order
PC64 · Measurement systems laboratory, NASA langley research center, hampton, VA. Modification to lift restriction regarding number of personnel permitted to work at…
$0
Supplemental Agreement for work within scope
PS63 · Measurement systems laboratory, new construction, NASA langley research center, hampton, VA. Supplemental changes to scope. Period of performance remains the…
$62,747
Supplemental Agreement for work within scope
PS62 · Measurement systems laboratory at NASA langley research center in hampton, VA. Modification to add supplemental work. Completion date remains the same.
$11,054
Supplemental Agreement for work within scope
PS61 · Measurement systems laboratory, NASA langley research center, hampton, VA. Supplemental changes to contract.
$31,116
Supplemental Agreement for work within scope
PS59
$30,237
Supplemental Agreement for work within scope
PS60 · Measurement systems laboratory new construction, NASA langley research center, hampton, VA. Modification requiring contractor to reduce staff and revise…
$0
Supplemental Agreement for work within scope
PS58 · New construction measurement systems laboratory, NASA langley research center, hampton, VA. Modification to add various changes.
$61,930
Supplemental Agreement for work within scope
PS56 · NASA measurement systems laboratory, new construction. Administrative modification to implement ndaa section 889.
$0
Supplemental Agreement for work within scope
PS57 · NASA measurement systems laboratory, new construction. Modification to add changes within scope of project. Contract completion date is 5/20/2020.
$27,705
Supplemental Agreement for work within scope
PS55 · Measurements system laboratory, new construction, NASA langley research center, hampton, VA. Supplemental changes. Substantial completion remains 1/20/2020.
$81,346
Supplemental Agreement for work within scope
PS54 · NASA langley research center, measurement system laboratory, new construction. Supplemental modification for various changes. Substantial completion date is…
$6,836
Supplemental Agreement for work within scope
PS53 · Measurement systems laboratory new construction, NASA langley campus, hampton, VA. Extension of substantial completion date to 1/20/2020.
$0
Supplemental Agreement for work within scope
PS52 · NASA measurement systems laboratory, new construction, langley research center, hampton VA. Modification to reflect changes within contract. Substantial…
$55,581
Supplemental Agreement for work within scope
PS51 · NASA measurement systems laboratory, new construction, hampton VA. Modification for changes within scope. Substantial completion remains 10/3/2019.
$97,547
Supplemental Agreement for work within scope
PS50 · NASA langley research center, measurement systems laboratory, hampton, VA. Changes within scope. Completion date remains 10/3/19.
$11,489
Supplemental Agreement for work within scope
PS49 · NASA langley research center, measurement systems laboratory, new construction, hampton, VA. Modification for supplemental changes within scope. Completion date…
$76,185
Other Administrative Action
PA48 · NASA langley research center, measurement system laboratory, new construction, hampton, VA. Administrative modification to revise DIV 1 requirements. Completion…
$0
Supplemental Agreement for work within scope
PS47
$143,249
Supplemental Agreement for work within scope
PS46 · NASA langley research center, measurement systems laboratory, new construction, hampton, VA. Modification for supplemental changes within scope. Completion date…
$94,351
Change Order
PC45 · NASA langley research center, new construction of the measurement systems laboratory, price to be determined later change order to implement changes to the…
$90,000
Supplemental Agreement for work within scope
PS44
$29,773
Supplemental Agreement for work within scope
PS43 · NASA langley research center, measurement systems laboratory, new construction, hampton, VA. Modification for supplemental changes within scope. Completion date…
$32,261
Supplemental Agreement for work within scope
PS42
$111,321
Supplemental Agreement for work within scope
PS41
$432,795
Supplemental Agreement for work within scope
PS40 · NASA measurement systems laboratory, hampton, VA, new construction, modification for supplemental changes. Completion date remains the same.
$120,627
Supplemental Agreement for work within scope
PS39 · NASA langley research center, hampton, VA - measurement systems laboratory, new construction, modification for supplemental changes. Completion date remains the…
$34,295
Supplemental Agreement for work within scope
PS38 · See attached.
$22,342
Supplemental Agreement for work within scope
PS37 · NASA langley research center, hampton virginia, measurement systems laboratory, new construction, modification for supplemental changes. Completion date remains
$37,782
Supplemental Agreement for work within scope
PS36 · Measurement system laboratory - new construction, NASA langley research center, hampton, VA. Modification to add supplemental changes based on government…
$303,660
Supplemental Agreement for work within scope
PS35 · See attached
$63,116
Supplemental Agreement for work within scope
PS34 · NASA langley research center, measurement systems laboratory construction. Various change orders in result of design clarification or government changes.…
$38,909
Supplemental Agreement for work within scope
PS33 · See attached.
$114,111
Supplemental Agreement for work within scope
PS32 · Please see attached.
$162,391
Supplemental Agreement for work within scope
PS31 · NASA langley research center, measurement systems laboratory construction - two change orders to update equipment and add support to partial height walls.…
$349,748
Supplemental Agreement for work within scope
PS30 · NASA langley research center, measurement systems laboratory new construction - multiple change orders. Completion date remains 12/20/2019.
$90,781
Supplemental Agreement for work within scope
PS29 · NASA measurement systems laboratory new construction - various change orders to implement supplemental adds. Completion date remains 12/20/2019.
$132,074
Supplemental Agreement for work within scope
PS28 · NASA langley research center, measurement systems laboratory construction. Multiple change orders. Completion date remains 12/20/2019.
$140,230
Supplemental Agreement for work within scope
PS27 · NASA langley research center, measurement systems laboratory - new construction - various change orders. Completion date remains 12/20/2019.
This is a $104,802,623.78 firm-fixed-price federal contract awarded by the National Aeronautics and Space Administration (NASA) Langley Research Center to W.M. Jordan Company, Incorporated for new construction under the NASA Mars Science Laboratory (MSL) project. The contract has an ultimate completion date of January 28, 2021 and was awarded on November 29, 2016. It is not a set-aside contract.
W.M. Jordan Company is a general contractor and construction company serving clients in Virginia and the Carolinas. In addition to this NASA contract, the company holds two indefinite delivery contracts with the Naval Facilities Engineering Command for design-build and design-bid-build services in the Hampton Roads region, valued at $950 million and $334 million respectively. These contracts enable W.M. Jordan Company to compete for and receive task orders between $15-100 million for new construction, demolition, renovation, repair, and alteration activities supporting the Navy's facilities requirements.
Quick answers
Who was awarded contract GS03P17DXC0005?
GS03P17DXC0005 was awarded to W.m. Jordan Company, Incorporated by Region 3 (Public Buildings Service) on November 29, 2016.
How much is contract GS03P17DXC0005 worth?
The government has obligated $104,802,624 on GS03P17DXC0005.
Which agency awarded contract GS03P17DXC0005?
Region 3 (Public Buildings Service) awarded GS03P17DXC0005, with funding from Langley Research Center (National Aeronautics and Space Administration).
Was contract GS03P17DXC0005 competed?
The extent of competition for GS03P17DXC0005 was full and open competition. The government received 4 offers.