Project FW-bimu 107(1): the project consists of improving the intersection at brady lane and missouri state highway 98 and improving paving and drainage along brady lane within the big muddy…

Active Definitive Contract Awarded Last action

Contract number
693C7321C000016
Awardee
Awarding agency
Obligated
$1,405,078

Award facts

Opportunity
Contract value 100% obligated
$1,405,077.54 Current and potential, with all options
Completion date 86% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 7 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
California, MO 65018, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00005 · FW-bimu 107(1) - CM #5: 693C7321C000016 $0
Other Administrative Action P00004 · FW-bimu 107(1) 693C7321C000016 CM #4 no change to contract amount no change to contract time extend period of performance to august 31, 2026 $0
Funding Only Action P00003 · FW-bimu 107(1) 693C7321C000016 CM #3 increase contract amount by $108,228.44 extend contract time by 672 calendar days the total amount of the contract is… $108,228
Other Administrative Action P00002 · FW-bimu 107(1) 693C7321C000016 CM #2 no change to contract amount no change to contract time extend period of performance to august 31, 2025 $0
Other Administrative Action P00001 · FW-bimu 107(1) CM #1 no change to contract amount no change to contract time extend period of performance to august 31, 2023 $0
Original award $1,296,849

About this award

The Federal Highway Administration awarded a definitive contract to Higgins Asphalt Paving Co Inc. for highway construction and infrastructure improvements at the Big Muddy National Fish and Wildlife Refuge on June 2, 2021, with a ceiling value of $1,405,077.54 under a total small business set-aside.

The project (FW-BIMU 107(1)) consists of improving the intersection at Brady Lane and Missouri State Highway 98, including installing two right-turn lanes, replacing culverts and headwalls, and resurfacing roadway within the refuge. Place of performance is California, MO 65018. The contract is priced firm fixed price. Performance period was extended through August 31, 2027 by contract modification CM #5. The originating solicitation was posted March 5, 2021 with a bid due date of April 22, 2021.

Description

Project FW-bimu 107(1): the project consists of improving the intersection at brady lane and missouri state highway 98 and improving paving and drainage along brady lane within the big muddy national fish and wildlife refuge. The work includes, the

Quick answers

Who was awarded contract 693C7321C000016?

693C7321C000016 was awarded to Higgins Asphalt Paving Co Inc. by Federal Highway Administration (Department of Transportation) on June 2, 2021.

How much is contract 693C7321C000016 worth?

The government has obligated $1,405,078 on 693C7321C000016.

Was contract 693C7321C000016 competed?

The extent of competition for 693C7321C000016 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award