About this opportunity

The City of Fillmore, California is soliciting bids for the Well 10 Equipping & Pump House Project at Delores Day Park, with proposals due October 1, 2026.

The scope encompasses mobilization; furnishing and installation of the well pump, motor, on-site and off-site valves, piping, and associated appurtenances; installation of a sodium hypochlorite chemical treatment system including storage tank, metering pumps, valves, piping, spill containment, and appurtenances; construction of a masonry pump house building and structural pad; construction of a gantry system; installation of complete electrical systems including conduit, wiring, panels, switchgear, transformers, meter housing, and all related appurtenances; furnishing and installation of a generator and automatic transfer switch (ATS); installation of water service connections and internal building distribution; installation of telecommunication conduit; construction of concrete pads for transformers and SCADA tower; and installation of decorative fencing around the SCADA tower. All work shall conform to the Plans and Specifications in the contract documents. The project is located at Delores Day Park in Fillmore.

The source material does not identify a contract value, contract term, incumbent contractor, evaluation criteria, set-aside or preference program, required qualifications or certifications, pre-bid meeting or site-visit date, or question-submission deadline.

Opportunity text

The project includes mobilization; furnishing and installation of the well pump, motor, on-site valves, on-site piping, and associated appurtenances; furnishing and installation of off-site valves, piping, connections, and appurtenances; installation of a sodium hypochlorite system including storage tank, chemical metering pumps, valves, piping, appurtenances, and spill containment; construction of the masonry pump house building and building pad; construction of a gantry system; installation of complete electrical systems including conduit, riser on power pole, meter housing, wiring, panels, switchgear, transformer connections, and all related appurtenances; furnishing and installation of transformers; furnishing and installation of a generator and automatic transfer switch (ATS); installation of water service connections and internal building distribution; installation of telecommunication conduit; construction of PCC pads for transformers and SCADA tower; and installation of a decorative fence around the SCADA tower, all in accordance with the Plans and Specifications and complete in place. The work will take place at Delores Day Park in Fillmore, and other related work as described in the Specifications and Contract Documents, by reference, made a part hereof.

Files

File Type Posted
Well 10 Equipping _ Pump House Project.pdf PDF