The City of Bellevue, Washington is soliciting bids for sewer pipe defect repair and trenchless rehabilitation across thirty-three municipal assets, with proposals due November 5, 2026.
The scope encompasses installation of approximately 38 lineal feet of 8-inch diameter PVC SDR 35 pipe; 1,010 lineal feet of 6-inch diameter main CIPP full-length liner; 8,534 lineal feet of 8-inch diameter main CIPP full-length liner; and 381 lineal feet of 10-inch diameter main CIPP full-length liner. The work also includes approximately 14 CIPP side sewer liners, 2 CIPP tee liners, 2 side sewer tees, and 1 inside drop structure on an 8-inch diameter main. Ancillary activities include mobilization and demobilization, traffic control, pipe cleaning, pre-construction and post-construction closed-circuit television inspection of mains and side sewers to the right-of-way or easement edge, water pollution and erosion control, bypass systems, property restoration, record documentation, trench and excavation protection, and supporting miscellaneous work.
The source document does not specify contract value, contract duration, evaluation criteria, pre-bid meeting or site-visit dates, or a question-due deadline. Bidders should obtain the full bid documents and specifications from the City of Bellevue.
Opportunity text
Work contemplated to be performed under this contract is as follows: installation of approximately thirty-eight (38) lineal feet (LF) of 8-inch diameter PVC SDR 35 pipe; installation of approximately one thousand, ten (1,010) lineal feet (LF) of 6-inch diameter main CIPP full-length liner; installation of approximately eight thousand, five hundred and thirty-four (8,534) lineal feet (LF) of 8-inch diameter main CIPP full-length liner; installation of approximately three hundred eighty-one (381) LF of 10-inch diameter main CIPP full-length liner; installation of approximately fourteen (14) CIPP side sewer liners on multiple sized diameter mains and side sewers; installation of approximately two (2) CIPP tee liners on multiple sized diameter mains and side sewers; installation of approximately two (2) side sewer tees on multiple sized diameter mains and side sewers. installation of approximately one (1) inside drop structure on an 8 diameter main; including other related work such as mobilization / demobilization, traffic control, pipe cleaning, pre-construction and post-construction closed circuit TV (CCTV) inspection (mains and side sewers up to the edge of the right-of-way (ROW) and / or easements), water pollution and erosion control, bypass system, property restoration, record documents, trench / excavation protection, and miscellaneous work as needed to support the above activities at thirty-three (33) assets throughout the City of Bellevue as shown on the cover sheet of the Contract Plans;