The State University Construction Fund (SUCF) is requesting bids on boiler replacement and central heating plant upgrades at an Albany County campus, with bids due August 12, 2026 and a mandatory project walk-through on July 15, 2026 at 10:00 a.m. at Hamilton Hall near the heating plant entrance.

The scope includes furnishing and installing two new 500 HP high-pressure steam firetube boilers to replace existing boilers; replacement of steam distribution piping serving Bicknell Hall, East Hall, Shannon Hall, and Galbreath Hall with new direct-buried steam piping; replacement of existing steam manhole MH-1; and conversion of the distribution system serving Oneida Hall, Mohawk Hall, and Cayuga Hall from steam to direct-buried low-temperature water (LTW) service, including installation of an LTW heat exchanger, distribution pump, and associated direct-buried LTW piping originating at Galbreath Hall.

All bidders must present evidence of skill, experience, and financial qualifications per Information to Bidders, Section 7 of the project specifications. Subcontracting is permitted; principal subcontractors must be named within 48 hours after bid opening. Bidders must submit within 48 hours of bid opening a certification of the NYS VendRep questionnaire (preferred) or a signed and notarized paper CCA2 form (Version 3/22 only), along with Attachments A, B, and C, Appendix A form, work descriptions, and preliminary project schedule. Plans are available through Plan & Print Systems, Inc. (315-437-5111 or https://planandprint.com/). Bidders should review the Bid and Post Bid Checklist on SUCF's website (https://www.sucf.suny.edu/).

Opportunity text

The work of this single bid project includes furnishing and installing two new 500 HP high-pressure steam firetube boilers to replace the existing boilers in the heating plant, along with upgrades to the campus steam and heating distribution systems. Work includes replacement of steam distribution piping serving Bicknell Hall, East Hall, Shannon Hall, and Galbreath Hall with new direct-buried steam piping; and replacement of existing steam manhole MH-1. The project also includes conversion of the distribution system serving Oneida Hall, Mohawk Hall, and Cayuga Hall from steam to direct-buried lowtemperature water (LTW) service, including installation of an LTW heat exchanger, distribution pump, and associated direct-buried LTW piping originating at Galbreath Hall. Plans will be available after July 7, 2026, through Plan & Print Systems, Inc. (315-437-5111 & https://planandprint.com/ ). A project walk-through has been scheduled for July 15, 2026, at 10:00AM, meeting outside at Hamilton Hall near the heating plant entrance.Please confirm the date/time with the Consultant. Special Notice to Potential Bidders: Please review the Bid and Post Bid Checklist on the Construction Opportunities page on the Fund's website (https://www.sucf.suny.edu/) for more information on bidder's qualifications and other requirements. All bidders must present evidence of skill, experience and financial qualifications per Information to Bidders, Section 7 of the project specs. Subcontracting is permitted (Section 2.18 of SUCF Agreement). Principal subcontractors must be named within 48 hrs after bid opening per Information for Bidders Section 8. Bidders must submit within 48 hrs either certification of its NYS VendRep questionnaire (preferred) or a signed and notarized paper CCA2 form (Version 3/22 only), Attachments A, B, and C, Appendix A form, work descriptions, and preliminary project schedule. In accordance with State Finance Law §139-j, all non-technical inquiries regarding this procurement must be directed to Robbilee Luedtke at SUCF.ConstructionBids@suny.edu or for MWBE related issues, Scott Clay at SUCF.OpportunityAdmin@suny.edu . Contact made to other staff regarding this procurement may disqualify the firm and affect future procurements with government entities in the State of New York. Please refer to OGS' website (www.ogs.ny.gov/aboutogs/regulations/defaultAdvisoryCouncil.html), for more information regarding this law. EEO goals for this project: 6% minority workforce and 3% female workforce Business enterprises awarded an identical or substantially similar procurement contract within the past five years: none Service-Disabled Veteran-Owned Business (SDVOB) SDVOB Goal: 3.00% Minority / Women Business Enterprise contracting goals (MWBE) MBE Goal: 5.00% WBE Goal: 5.00%