Phase 14 Sewer System Rehabilitation

Closed State & local contract opportunity Posted

Solicitation number
27-03
State
Massachusetts
Responses due

Opportunity facts

Jurisdiction

Opportunity details come from constructionbidsource.com. Updated .

About this opportunity

The Town of Reading, Massachusetts is requesting sealed bids on Phase 14 Sewer System Rehabilitation (Contract No. 27-03), with bids due September 28, 2026 at 1:00 PM at the Town Clerk's office and a non-mandatory pre-bid site walk on September 9, 2026 at 11:00 AM at the intersection of John Carver Road and Woodland Street.

The Base Bid scope includes furnishing and installing approximately 6,000 linear feet of 8-inch through 12-inch cured-in-place pipe lining; preparatory sewer cleaning; television inspection; testing and sealing of service connection joints; bypass pumping; manhole rehabilitation; and miscellaneous cleanup. The Base Bid also covers spot repairs of sewer segments identified during pre-inspection, including removal and disposal of existing asbestos cement pipe, installation of polyvinyl chloride pipe sewer service connections and appurtenances, earthwork, dewatering, drainage, paving, and surface restoration. Bid Alternate No. 1 adds approximately 1,300 linear feet of 8-inch through 10-inch CIPP lining with equivalent repair and restoration work.

Massachusetts prevailing wage rates apply. The contractor must submit a Qualification and Reference Statement documenting three similar projects completed within the past five years. All employees must complete a minimum of 10 hours of OSHA-approved safety and health training prior to work commencement. Base Bid work must be completed within 90 calendar days (excluding final paving and winter shutdown), with Alternate No. 1 requiring an additional 30 calendar days. Winter shutdown is enforced December 1 through April 1 unless approved by the Owner.

The successful bidder must submit 5 percent bid security and, upon award, execute the contract within seven days and provide a performance bond and labor and materials payment bond each for the full contract amount. Insurance requirements include Commercial General Liability of $1 million per occurrence and $3 million general aggregate, Automobile Liability of $1 million combined single limit, and Umbrella Liability of at least $5 million. The contract is subject to monthly price adjustments for liquid asphalt, Portland cement, diesel fuel, and gasoline when material cost changes exceed plus or minus 5 percent. Written requests for clarification were due September 11, 2026 at 4:00 PM.

Opportunity text

The Base Bid work of this Contract includes furnishing and installing approximately 6,000 linear feet of 8-inch through 12-inch cured-in-place pipe lining; preparatory cleaning of sewers; television inspection; testing and sealing of the first two joints of each service connection; bypass pumping; manhole rehabilitation; and all miscellaneous work and cleanup. The Base Bid work also includes bid items for spot repairs of sewer segments that must be repaired before they can be CIPP lined and which may be identified during pre-inspection of sewer lines identified for CIPP. These repairs include, but not are limited to, removal and disposal of existing asbestos cement (AC) sewer pipe and furnishing and installing polyvinyl chloride (PVC) sewer pipe including, sewer service connections and appurtenances; earthwork; dewatering and drainage; paving; surface restoration; bypass pumping; and all miscellaneous work and cleanup, as specified. The Bid Alternate No.1 work of this Contract includes furnishing and installing approximately 1,300 linear feet of 8-inch through 10-inch cured-in-place pipe lining; preparatory cleaning of sewers; television inspection; testing and sealing of the first two joints of each service connection; bypass pumping; manhole rehabilitation; and all miscellaneous work and cleanup. The Bid Alternate No.1 work also includes the spot repair of sewer segments that must be repaired before they can be CIPP lined and which have been identified during pre-inspection of sewer lines identified for CIPP. These repairs include, but not are limited to, removal and disposal of existing AC sewer pipe and furnishing and installing PVC sewer pipe including, sewer service connections and appurtenances; earthwork; dewatering and drainage; paving; surface restoration; bypass pumping; and all miscellaneous work and cleanup, as specified.