About this opportunity

The City of Seguin, Texas is requesting sealed bids for the Nolan Street Outfall Emergency Repair project (Project No. AF-2026-53) with bids due July 28, 2026 at 3:00 p.m. through BidNet, and a mandatory pre-bid conference on July 14 at 10:00 a.m. at the project site (933 Nolan Street, Seguin, TX 78155).

The scope consists of removal of a damaged outfall structure and approximately 230 linear feet of 84-inch corrugated metal pipe, replacement with a concrete and gabion outfall structure, installation of approximately 200 linear feet of 8-foot by 8-foot single box culvert, installation of a curb inlet, approximately 46 linear feet of 30-inch PVC drainage pipe, removal of erosion control matting and replacement with sod, and incidental removal and replacement of curb, sidewalk, and pavement. Work occurs within City right-of-way and on Guadalupe Blanco River Authority (GBRA) property.

The contract requires substantial completion within 90 calendar days from Notice to Proceed, with final completion required within 30 days thereafter. Bidders must submit a bid bond equal to 5 percent of the total bid amount; performance and payment bonds each equal to 100 percent of the contract price are required upon award. Unit pricing and a 24-month warranty from the date of acceptance are mandatory bid components. Monthly progress payments are made based on percentage of completion with 5 percent retainage until final completion. Liquidated damages range from $500 per day for contracts under $500,000 to $1,000 per day for contracts exceeding $1 million.

Contractors must comply with Davis-Bacon Related Acts wage requirements and equal employment opportunity requirements, and maintain workers' compensation insurance, commercial general liability insurance ($1 million per occurrence), and comprehensive automobile liability insurance ($1 million per occurrence). The project engineer is Pape-Dawson Engineers, LLC.

Opportunity text

Nolan Street Outfall Emergency Repair which consists of: removal of damaged outfall structure and +/- 230 LF 84 corrugated metal pipe, and replacement with a concrete and gabion outfall structure and approximately 200 LF 8x8 single box culvert.