Guadalupe County Municipal Utility District No. 10 is requesting sealed bids for construction of Kayden Springs Unit 2, a mixed-infrastructure project with sealed bids due September 9, 2026 at 1:00 p.m. Local Time, and a mandatory pre-bid conference scheduled for August 31, 2026 at 1:00 p.m. via Microsoft Teams. The issuing body is the utility district; Lennar Homes of Texas Land and Construction, LTD acts as Owner's representative, and Westwood Professional Services, Inc. serves as Engineer.

The scope encompasses approximately 126,075 cubic yards of excavation, 20,308 cubic yards of embankment, 3,315 linear feet of 8-inch water pipe, 851 linear feet of 12-inch water pipe, 3,039 linear feet of 8-inch sanitary sewer pipe, 948 linear feet of 12-inch sanitary sewer pipe, drainage facilities, dry utilities, detention pond, and approximately 4,025 linear feet of street improvements. The contract completion period is 270 working days from contractor notification, with work to begin within five calendar days of notification.

Bid security of not less than 2 percent of the total bid amount (cashier's check or bid bond) must accompany each bid. Bidders must demonstrate qualifications by submitting detailed written evidence within two days after bid opening, including financial data, proposed subcontractors, construction schedule, present commitments, and minimum three comparable projects completed within the past three years. The successful bidder must provide performance and payment bonds and required insurance certificates within seven days of notification.

Contract price is determined by the sum of unit prices multiplied by measured quantities, with monthly progress payments at 90 percent of work completed, due by the 3rd of the following month and payable by the Monday after the 15th. A 10 percent retainage applies until final payment approval. Liquidated damages are assessed at $1,000 per calendar day for work uncompleted after contract time expires. Contractors must comply with Texas prevailing wage requirements under Texas Government Code Chapter 2258, provide workers' compensation insurance, and submit Form 1295 and comply with Texas prohibitions on boycotting Israel, contracting with terrorist organizations, boycotting energy companies, and discriminating against firearm entities. Specifications, plans, soils reports, and environmental reports are available at www.CivcastUSA.com.

Opportunity text

The project scope includes approximately 126,075 cubic yards of excavation, 20,308 cubic yards of embankment, 3,315 linear feet of 8 water pipe, 851 linear feet of 12 water pipe, 3,039 linear feet of 8 sanitary sewer pipe, 948 linear feet of 12 sanitary sewer pipe, drainage facilities, dry utilities, detention pond, and approximately 4,025 linear feet of street improvements.

Files

File Type Posted
02. Bid Docs - Kayden Springs Unit 2.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity