About this opportunity

The City of Temecula, California, Department of Public Works is requesting bids for construction of Fire Station 73 New Apparatus Bay and Gym (Project PW19-13), with electronic bids due August 19, 2026 at 10:00 a.m. PDT and questions due August 12, 2026.

The scope comprises demolition of existing concrete, construction of a new 897-square-foot gym facility and a new 2,217-square-foot apparatus bay with integrated shop and storage space, accessibility improvements, and full mechanical, electrical, and plumbing systems. Exterior work includes a concrete parking lot, storm drain pipe, lighting, trash enclosure, and landscape with irrigation. Soils improvement using stone columns or approved equivalent is required prior to construction based on geotechnical recommendations.

The estimated bid value is $4,035,000 on a lump-sum basis. The project has a 180 working-day completion timeline commencing upon issuance of the Notice to Proceed, with liquidated damages assessed at $1,000 per calendar day for delays beyond the scheduled completion date.

A Class B California contractor license is required. All contractors and subcontractors must be registered with the Department of Industrial Relations per Labor Code section 1725.5. Bidders must submit a bid bond equal to 10 percent of the bid amount, with performance and payment bonds each at 100 percent of the bid amount. Bids are valid for 90 calendar days and must be submitted electronically in PDF format through the City's PlanetBids system; hard-copy submissions are not accepted.

No pre-bid meeting is scheduled. Questions and contact requests may be directed to Emalee Manning, Hossein Ajideh, Ryan Castillo, Taylor Martin, or Cassandra Tabares through the City's provided contact information.

Opportunity text

The work to be done consists of furnishing all materials, equipment, tools, labor and incidentals as required by the Contract Documents to construct for the above-stated project. The general items of work include Construction work generally consists of concrete demolition, construction of a new 897 square foot gym, a new 2,217 square foot apparatus bay & shop/storage building; the buildings include all accessibility improvements, construction materials, finishes, plumbing, mechanical, electrical, and related work. Exterior improvements include a concrete parking lot, storm drainpipe, lighting, new trash enclosure, and landscape & irrigation. Prior to any construction, the soils will need to be improved with stone columns (or approved equal) per recommendations based on the soils report.

Files

File Type Posted
Fire Station 73 New Apparatus Bay and Gym.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity