USCGC bernard c webber updd FY26 MRG replace (DS)
Past New Requirement Updated
- Agency
-
Coast Guard
Department of Homeland Security
- Solicitation expected
- Estimated value
- $1,000,000 to $2,000,000
- Set-aside
- Total Small Business
Forecast facts
- Anticipated award
- Through
- NAICS code
- 336611 Ship Building and Repairing
- Forecast number
- F2026072903
- Points of contact
-
- Larry M. Hatalla larry.m.hatalla@uscg.mil (775) 225-8903
- Alexandra Lombardi alexandra.p.lombardi@uscg.mil (781) 715-5683
Forecast details come from DHS's Acquisition Planning Forecast System. Agencies' dates and values are estimates.
About this forecast
The U.S. Coast Guard is seeking a contractor to perform unplanned dry dock maintenance on the USCGC Bernard C. Webber, specifically focused on replacing reduction gears and ensuring proper shaft alignment, along with tank cleaning and preservation. The solicitation is scheduled for release on February 13, 2026, with an anticipated award date of March 17, 2026. This is a small business set-aside contract utilizing a firm fixed price structure under a definitive contract vehicle.
The estimated award value ranges from $1,000,000 to $2,000,000, with performance scheduled to commence on March 17, 2026, and conclude by June 2, 2026—a total performance period of approximately 2.5 months. Work will be executed at the contractor's facility unless otherwise specified in the statement of work. For inquiries, interested parties should contact Larry Hatalla (requirements contact) at larry.m.hatalla@uscg.mil or (775) 225-8903, or Alexandra Lombardi (alternate contact) at alexandra.p.lombardi@uscg.mil or (781) 715-5683.
Forecast text
This will be a ship repair contract for USCGC BERNARD WEBBER Unplanned Dry Dock maintenance availability designed to replace both reduction gears and ensure proper shaft alignment: tank cleaning/preservation. The execution of this contract and following work will take place at the contractor’s facility unless otherwise specified within the solicitation and provided statement of work.
The estimated period of performance start date is 17MAR26 and end date is 02JUN26.
On GovTribe
Work this forecast
- Track it in your pipeline
- Find teaming partners
- Similar forecasts
- Ask GovTribe AI about this forecast