Upper Dewey & Upper Joker Culvert Replacement

Awarded Award Notice Posted

Solicitation number
AG-0261-S-13-0031
Agency
Region 4 - Intermountain Region Forest Service, Department of Agriculture
Awarded
to Boyd Foster Backhoe Service, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
AG-0261-P-13-0144 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Council, Idaho 83612, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Added: Mar 15, 2013 5:49 pm Modified: May 01, 2013 3:20 pmTrack Changes

AMENDMENT 2 TO PRE-SOLICITATION NOTICE
THIS AMENDMENT CONTAINS AMENDMENT 000001 OF THE SOLICITATION AG-0261-S-13-0031. PLEASE SEE DOCUMENT TITLED Amend 000001.pdf FOR DETAILS AND INSTRUCTIONS. RESPONSE DATE HAS BEEN EXTENDED AND OFFERORS ARE REQUIRED TO SEND IN A SIGNED COPY OF THE SF-30 IN ORDER FOR THEIR OFFER TO BE CONSIDERED.

AMENDMENT 1 TO PRE-SOLICITATION NOTICE

THIS AMENDMENT ADDS THE ATTACHED SOLICIATION PACKAGE.



PRE-SOLICIATION NOTICE
The Southwest Idaho and Nevada Acquisition Center anticipates awarding one contract for two culvert replacements on the Council Ranger District, Payette National Forest, in Idaho. The scope of work for the Upper Joker and Upper Dewey Culvert Replacement consists of the following:

-Install ROAD CLOSED signs on Type III barricades.
-Submit an erosion control plan that will show the stream diversion plan.
-Remove and dispose of existing arch pipes.
-Salvage rock for stream simulation material from the excavation.
-Set and maintain survey control staking by referencing Government supplied control points.
-Install concrete footings and metal arch at Upper Joker.
-Install precast box at Upper Dewey
-Place salvaged stream simulation rock to construct a natural stream channel
-Protect electric cattle fence at Upper Dewey, install brackets and posts on new precast box, and reinstall electric fence.
-Backfill and place aggregate surfacing on the new road.
-Haul any excess material to the disposal sites shown on the plans.
-Haul and place commercial crushed aggregate.
-Seed disturbed areas with government supplied seed.
-The work shall be carried out in accordance with the lines, grades, notations, and dimensions shown in the plans.

The solicitation will be posted on FedBizOpps website on or about April 2, 2013 for viewing and printing.

The Upper Dewey site may be reached from Council by driving the Mill Creek Road 50165 up to Shingle Flat Road and then down the 186 road to the East Fork Weiser Road 172. Drive up the 172 road for approximately 16 miles to the junction of the 50165 road. Drive approximately 2 miles west on 50165 to the Upper Dewey Creek Site.

The Upper Joker site may be reached by driving on the 50172 road to the junction of road 50486. Drive approximately 3 miles on the 50486 road to the site.

The East Fork Weiser Bridge is scheduled to be completed in early summer of 2013, and after it is completed the easier access to the Upper Dewey and Upper Joker will be by driving up the 50172 road from the intersection of the 50172 road and State highway 95.

Anticipated start date is May 1, 2013 and project must be completed no later than August 15, 2013.

Per FAR 36.204 - Disclosure of Magnitude of Construction Projects, the estimated price of this award is between $150,000 and $250,000.

FUNDS ARE CURRENTLY NOT AVAILABLE FOR THIS REQUIREMENT.
The Government reserves the right to cancel this requirement at any time.


 

Update #2 ·

Added: Mar 15, 2013 5:49 pm Modified: Apr 11, 2013 4:39 pmTrack Changes

AMENDMENT 1 TO PRE-SOLICITATION NOTICE

THIS AMENDMENT ADDS THE ATTACHED SOLICIATION PACKAGE.



PRE-SOLICIATION NOTICE
The Southwest Idaho and Nevada Acquisition Center anticipates awarding one contract for two culvert replacements on the Council Ranger District, Payette National Forest, in Idaho. The scope of work for the Upper Joker and Upper Dewey Culvert Replacement consists of the following:

-Install ROAD CLOSED signs on Type III barricades.
-Submit an erosion control plan that will show the stream diversion plan.
-Remove and dispose of existing arch pipes.
-Salvage rock for stream simulation material from the excavation.
-Set and maintain survey control staking by referencing Government supplied control points.
-Install concrete footings and metal arch at Upper Joker.
-Install precast box at Upper Dewey
-Place salvaged stream simulation rock to construct a natural stream channel
-Protect electric cattle fence at Upper Dewey, install brackets and posts on new precast box, and reinstall electric fence.
-Backfill and place aggregate surfacing on the new road.
-Haul any excess material to the disposal sites shown on the plans.
-Haul and place commercial crushed aggregate.
-Seed disturbed areas with government supplied seed.
-The work shall be carried out in accordance with the lines, grades, notations, and dimensions shown in the plans.

The solicitation will be posted on FedBizOpps website on or about April 2, 2013 for viewing and printing.

The Upper Dewey site may be reached from Council by driving the Mill Creek Road 50165 up to Shingle Flat Road and then down the 186 road to the East Fork Weiser Road 172. Drive up the 172 road for approximately 16 miles to the junction of the 50165 road. Drive approximately 2 miles west on 50165 to the Upper Dewey Creek Site.

The Upper Joker site may be reached by driving on the 50172 road to the junction of road 50486. Drive approximately 3 miles on the 50486 road to the site.

The East Fork Weiser Bridge is scheduled to be completed in early summer of 2013, and after it is completed the easier access to the Upper Dewey and Upper Joker will be by driving up the 50172 road from the intersection of the 50172 road and State highway 95.

Anticipated start date is May 1, 2013 and project must be completed no later than August 15, 2013.

Per FAR 36.204 - Disclosure of Magnitude of Construction Projects, the estimated price of this award is between $150,000 and $250,000.

FUNDS ARE CURRENTLY NOT AVAILABLE FOR THIS REQUIREMENT.
The Government reserves the right to cancel this requirement at any time.


 

Update #1 ·

Added: Mar 15, 2013 5:49 pm

The Southwest Idaho and Nevada Acquisition Center anticipates awarding one contract for two culvert replacements on the Council Ranger District, Payette National Forest, in Idaho. The scope of work for the Upper Joker and Upper Dewey Culvert Replacement consists of the following:

-Install ROAD CLOSED signs on Type III barricades.
-Submit an erosion control plan that will show the stream diversion plan.
-Remove and dispose of existing arch pipes.
-Salvage rock for stream simulation material from the excavation.
-Set and maintain survey control staking by referencing Government supplied control points.
-Install concrete footings and metal arch at Upper Joker.
-Install precast box at Upper Dewey
-Place salvaged stream simulation rock to construct a natural stream channel
-Protect electric cattle fence at Upper Dewey, install brackets and posts on new precast box, and reinstall electric fence.
-Backfill and place aggregate surfacing on the new road.
-Haul any excess material to the disposal sites shown on the plans.
-Haul and place commercial crushed aggregate.
-Seed disturbed areas with government supplied seed.
-The work shall be carried out in accordance with the lines, grades, notations, and dimensions shown in the plans.

The solicitation will be posted on FedBizOpps website on or about April 2, 2013 for viewing and printing.

The Upper Dewey site may be reached from Council by driving the Mill Creek Road 50165 up to Shingle Flat Road and then down the 186 road to the East Fork Weiser Road 172. Drive up the 172 road for approximately 16 miles to the junction of the 50165 road. Drive approximately 2 miles west on 50165 to the Upper Dewey Creek Site.

The Upper Joker site may be reached by driving on the 50172 road to the junction of road 50486. Drive approximately 3 miles on the 50486 road to the site.

The East Fork Weiser Bridge is scheduled to be completed in early summer of 2013, and after it is completed the easier access to the Upper Dewey and Upper Joker will be by driving up the 50172 road from the intersection of the 50172 road and State highway 95.

Anticipated start date is May 1, 2013 and project must be completed no later than August 15, 2013.

Per FAR 36.204 - Disclosure of Magnitude of Construction Projects, the estimated price of this award is between $150,000 and $250,000.

FUNDS ARE CURRENTLY NOT AVAILABLE FOR THIS REQUIREMENT.
The Government reserves the right to cancel this requirement at any time.


 

Attachments

Files attached to this notice, newest first
File Type Posted
Amend_000001.pdf PDF
Construction_Cost_Estimate_Breakdown0031.xlsx XLSX spreadsheet
Photos_Upper_Joker.pdf PDF
WageDetermination_ID130010.pdf PDF
Joker_DeweyMapDrawings.pdf PDF
Specs_UpperJokerUpperDewey.pdf PDF
AG0261S130031_SF1442_T_and_C.pdf PDF
Photo_Upper_Dewey.pdf PDF