Tumbling Creek Culvert Replacement, Chattahoochee National Forest
Awarded Award Notice Posted
- Solicitation number
- AG-435H-S-13-0022
- Agency
- Region 8 - Southern Region Forest Service, Department of Agriculture
- Awarded
- to Patton Excavation
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- AG-435H-C-13-0024 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- Fannin county, Georgia, United States
Notice details come from SAM.gov. Updated .
Notice text
5 versions
Update #5 · Latest ·
Added: Sep 20, 2013 4:17 pm Contract Award
Update #4 ·
Added: Jul 10, 2013 1:05 pm
Modified: Sep 04, 2013 11:23 amTrack Changes
Amendment 1 changes option and extends due date.
The date for issuing and posting this solicitation has been postponed to August 9, 2013. The due date for receipt of proposals has been postponed to September 6, 2013.
The files uploaded on July 19 were for the wrong project. The correct documents for the Tumbling Creek Culvert project are scheduled to be uploaded July 25.
PROJECT DESCRIPTION: Project consists of removing the existing 24" culverts at two different sites (three culvert per site including rock headwalls and wingwalls) and replacing them with the following: Site #1 aluminum structural plate open-bottom arch culvert 13'-0" X 4'-1" X 27'-0"; Site #2 aluminum structural plate open-bottom arch culvert 14'-0" X 4'-8" X 27'-0" including, for both sites, aluminum headwalls, wingwalls, all appurtenances and concrete footings, also the constructions of rock headwalls and wingwalls to match rock work of existing culverts in the area.
PROJECT LOCATION: The project sites are along FSR 22 in Fannin County Georgia. (Google search: Forest Service Road 22-2 Epworth GA) Site #1 is located on FSR-22 over No Name Creek approximately 4 miles north from intersection with Old Ga Highway 2. Site #2 is located over Walnut Creek approximately 5.2 miles north from Old Ga Highway 2.
ESTIMATE COST RANGE: between $150,000 and $300,000.
OTHER INFORMATION: A pre-bid conference and site showing is scheduled tentatively for August 7, 2013. Details will be in the solicitation.
SOLICITATION DOCUMENTS, SPECIFICATIONS AND DRAWINGS: The solicitation, AG-435H-S-13-0022 and related documents will be issued via FedBizOpps and will be available for downloading on or about July 25, 2013 at the website address: http://www.fedbizopps.gov/
Update #3 ·
Added: Jul 10, 2013 1:05 pm
Modified: Jul 22, 2013 2:09 pmTrack Changes
The date for issuing and posting this solicitation has been postponed to August 9, 2013. The due date for receipt of proposals has been postponed to September 6, 2013.
The files uploaded on July 19 were for the wrong project. The correct documents for the Tumbling Creek Culvert project are scheduled to be uploaded July 25.
PROJECT DESCRIPTION: Project consists of removing the existing 24" culverts at two different sites (three culvert per site including rock headwalls and wingwalls) and replacing them with the following: Site #1 aluminum structural plate open-bottom arch culvert 13'-0" X 4'-1" X 27'-0"; Site #2 aluminum structural plate open-bottom arch culvert 14'-0" X 4'-8" X 27'-0" including, for both sites, aluminum headwalls, wingwalls, all appurtenances and concrete footings, also the constructions of rock headwalls and wingwalls to match rock work of existing culverts in the area.
PROJECT LOCATION: The project sites are along FSR 22 in Fannin County Georgia. (Google search: Forest Service Road 22-2 Epworth GA) Site #1 is located on FSR-22 over No Name Creek approximately 4 miles north from intersection with Old Ga Highway 2. Site #2 is located over Walnut Creek approximately 5.2 miles north from Old Ga Highway 2.
ESTIMATE COST RANGE: between $150,000 and $300,000.
OTHER INFORMATION: A pre-bid conference and site showing is scheduled tentatively for August 7, 2013. Details will be in the solicitation.
SOLICITATION DOCUMENTS, SPECIFICATIONS AND DRAWINGS: The solicitation, AG-435H-S-13-0022 and related documents will be issued via FedBizOpps and will be available for downloading on or about July 25, 2013 at the website address: http://www.fedbizopps.gov/
Update #2 ·
Added: Jul 10, 2013 1:05 pm
Modified: Jul 20, 2013 11:25 amTrack Changes
The files uploaded on July 19 were for the wrong project. The correct documents for the Tumbling Creek Culvert project are scheduled to be uploaded July 25.
PROJECT DESCRIPTION: Project consists of removing the existing 24" culverts at two different sites (three culvert per site including rock headwalls and wingwalls) and replacing them with the following: Site #1 aluminum structural plate open-bottom arch culvert 13'-0" X 4'-1" X 27'-0"; Site #2 aluminum structural plate open-bottom arch culvert 14'-0" X 4'-8" X 27'-0" including, for both sites, aluminum headwalls, wingwalls, all appurtenances and concrete footings, also the constructions of rock headwalls and wingwalls to match rock work of existing culverts in the area.
PROJECT LOCATION: The project sites are along FSR 22 in Fannin County Georgia. (Google search: Forest Service Road 22-2 Epworth GA) Site #1 is located on FSR-22 over No Name Creek approximately 4 miles north from intersection with Old Ga Highway 2. Site #2 is located over Walnut Creek approximately 5.2 miles north from Old Ga Highway 2.
ESTIMATE COST RANGE: between $150,000 and $300,000.
OTHER INFORMATION: A pre-bid conference and site showing is scheduled tentatively for August 7, 2013. Details will be in the solicitation.
SOLICITATION DOCUMENTS, SPECIFICATIONS AND DRAWINGS: The solicitation, AG-435H-S-13-0022 and related documents will be issued via FedBizOpps and will be available for downloading on or about July 25, 2013 at the website address: http://www.fedbizopps.gov/
Update #1 ·
Added: Jul 10, 2013 1:05 pm
PROJECT DESCRIPTION: Project consists of removing the existing 24" culverts at two different sites (three culvert per site including rock headwalls and wingwalls) and replacing them with the following: Site #1 aluminum structural plate open-bottom arch culvert 13'-0" X 4'-1" X 27'-0"; Site #2 aluminum structural plate open-bottom arch culvert 14'-0" X 4'-8" X 27'-0" including, for both sites, aluminum headwalls, wingwalls, all appurtenances and concrete footings, also the constructions of rock headwalls and wingwalls to match rock work of existing culverts in the area.
PROJECT LOCATION: The project sites are along FSR 22 in Fannin County Georgia. (Google search: Forest Service Road 22-2 Epworth GA) Site #1 is located on FSR-22 over No Name Creek approximately 4 miles north from intersection with Old Ga Highway 2. Site #2 is located over Walnut Creek approximately 5.2 miles north from Old Ga Highway 2.
ESTIMATE COST RANGE: between $150,000 and $300,000.
OTHER INFORMATION: A pre-bid conference and site showing is scheduled tentatively for August 7, 2013. Details will be in the solicitation.
SOLICITATION DOCUMENTS, SPECIFICATIONS AND DRAWINGS: The solicitation, AG-435H-S-13-0022 and related documents will be issued via FedBizOpps and will be available for downloading on or about July 25, 2013 at the website address: http://www.fedbizopps.gov/
Attachments
| File | Type | Posted |
|---|---|---|
| Amdt_1_Tumbling_Ck.pdf | ||
| attendees_tumbling_creek_culvert_showing.pdf | ||
| AG-435H-S-13-0022.pdf | ||
| SupSpecs FS-22 culverts replacement.pdf | ||
| Technical Proposal Format.docx | DOCX document | |
| FS-22 culverts replacement dwg.pdf | ||
| Wage Determination GA1.pdf | ||
| Bid Bond_SF 24.pdf | ||
| Janitorial Floor Maintenance Plan.pdf | ||
| Task Frequency and Inspection.pdf | ||
| SF1449 form.pdf | ||
| Relevant Experience Input Form.docx | DOCX document | |
| SCA WageDet 05-2133 Rev12.pdf | ||
| AG-435H-S-13-0022.pdf |
Show all 14
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity