About this opportunity
The U.S. Army Corps of Engineers Detroit District is seeking contractors to replace the overhead crane rails at the Main Powerhouse in Sault Sainte Marie, Michigan under solicitation number W911XK20R0019. Contractors must mobilize to the site, perform an initial and final rail alignment survey, remove the existing 30 Ton and 80/20 Ton rails which have significant gaps and misalignments, install new rails aligned to Conveyor Manufacturers Association of America standard 70 using the existing bolt holes, and demobilize once work is complete. The final response deadline for interested contractors is August 31, 2020.
There is no set-aside designation for this procurement. The primary North American Industry Classification System and Product Service Codes are 237990 and R499, covering other heavy and civil engineering construction and construction of other nonresidential structures respectively. No incumbent or current contractors are identified. Key details include replacing approximately 1,000 linear feet each of 30 Ton and 80/20 Ton rails supported by structural I-beams and painted with lead primer at the Main Powerhouse facility in Sault Sainte Marie, Michigan.
Notice text
3 versions
Update #3 · Latest ·
The U.S. Army Corps of Engineers (USACE) Detroit District is seeking contractors that have the capability to provide construction services for replacing the overhead crane rails at the Main Powerhouse in Sault Sainte Marie, MI.
Mobilize to Sault Sainte Marie, MI and provide construction services to replace the 30 Ton and 80/20 Ton crane rails at the Main Powerhouse. Large rail gaps and misalignments exist on both the gatehouse and powerhouse bridge crane rails. These rails rest on structural I-beams. This misalignment has resulted in crane rail damage. The rails are being replaced in order to maintain the bridge crane functionality for the remainder of the crane’s life. The new rails will be aligned to CMAA 70 standards. The contractor will be required to perform an initial survey and a final survey after replacing the rails. The supporting I-beams are not being modified and the existing clip bolt holes are to be reutilized. The rails, rail hardware, and supporting beams are painted with Lead Primer. Demobilize once work is complete.
Note that Amendment 0001 has the number 0003 in Block 2 of the SF30.
Amendment 0002 has the number 0005 in Block 2 of the SF30.
Update #2 ·
The U.S. Army Corps of Engineers (USACE) Detroit District is seeking contractors that have the capability to provide construction services for replacing the overhead crane rails at the Main Powerhouse in Sault Sainte Marie, MI.
Mobilize to Sault Sainte Marie, MI and provide construction services to replace the 30 Ton and 80/20 Ton crane rails at the Main Powerhouse. Large rail gaps and misalignments exist on both the gatehouse and powerhouse bridge crane rails. These rails rest on structural I-beams. This misalignment has resulted in crane rail damage. The rails are being replaced in order to maintain the bridge crane functionality for the remainder of the crane’s life. The new rails will be aligned to CMAA 70 standards. The contractor will be required to perform an initial survey and a final survey after replacing the rails. The supporting I-beams are not being modified and the existing clip bolt holes are to be reutilized. The rails, rail hardware, and supporting beams are painted with Lead Primer. Demobilize once work is complete.
Note that Amendment 0001 has the number 0003 in Block 2 of the SF30.
Update #1 ·
The U.S. Army Corps of Engineers (USACE) Detroit District is seeking contractors that have the capability to provide construction services for replacing the overhead crane rails at the Main Powerhouse in Sault Sainte Marie, MI.
Mobilize to Sault Sainte Marie, MI and provide construction services to replace the 30 Ton and 80/20 Ton crane rails at the Main Powerhouse. Large rail gaps and misalignments exist on both the gatehouse and powerhouse bridge crane rails. These rails rest on structural I-beams. This misalignment has resulted in crane rail damage. The rails are being replaced in order to maintain the bridge crane functionality for the remainder of the crane’s life. The new rails will be aligned to CMAA 70 standards. The contractor will be required to perform an initial survey and a final survey after replacing the rails. The supporting I-beams are not being modified and the existing clip bolt holes are to be reutilized. The rails, rail hardware, and supporting beams are painted with Lead Primer. Demobilize once work is complete.
Attachments
| File | Type | Posted |
|---|---|---|
| W911XK20R0019-0002.pdf | ||
| W911XK20R0019-0001.pdf | ||
| St Marys Powerhouse and Intake Bridge Crane Rail Rehabilitation - RTA Reference....pdf | ||
| Soo Powerhouse and Intake Crane Rail Replacement - RTA Plans.pdf | ||
| Soo Powerhouse and Intake Crane Rail Replacement - RTA Specs.pdf | ||
| W911XK20R0019_29Jul2020(1).pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Replace Powerhouse Crane Rails | Pre-Solicitation | |
| Replace Powerhouse Crane Rails | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity