RECOVERY ACT - Arkabutla Creek Watershed Project
Award Notice Posted
- Solicitation number
- AG-4423-S-10-0025
- Agency
-
National Resources Conservation Service
Department of Agriculture
- Awarded
- to Arrowhead Enterprises, LLC
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- AG-4423-C-10-0009 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
- Place of performance
- Tate and Panola Counties, Mississippi, United States
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
THIS PROJECT IS FUNDED BY THE AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) OF 2009. The work consists of construction of bank stabilization on seven (7) sites in Arkabutla Creek Watershed, Tate and Panola Counties. The major items of work are: Clearing and Grubbing – 1 lump sum; Protective Cover – 6.0 ac.; Erosion Control Blanket – 335 S.Y.; Excavation, Common – 22,964 C.Y.; Drainfill – 140 C.Y.; Concrete, Class 3000M – 25.2 C.Y.; Corrugated Metal Pipe (CMP), Barrel, 24” Dia. – 64 L.F., 30” Dia. – 82 L.F., 42” Dia. – 84 L.F., 48” Dia. – 292 L.F.; CMP, Riser, 36” Dia. – 9 L.F., 42” Dia. – 10 L.F., 54” Dia. – 18 L.F., 60” Dia. – 9 L.F.; Rock Riprap – 7,630 tons; Pipe Anchor – 1 lump sum; Geotextile – 810 S.Y.; Earthfill, Slurry – 11,363 C.Y.; Earthfill, Slurry, Offsite – 832 C.Y.; Concrete Grout – 105 C.Y.; and Mobilization & Demobilization – 1 lump sum. This work is to be completed within 269 calendar days. Estimated price range for this work is $500,000 to $1,000,000. All responsible sources may submit a bid which shall be considered by the agency. Interested parties may access the invitation for bid on or about August 10, 2010 and download the solicitation files.
Update #2 ·
RECOVERY ACT PROJECT - The work consists of construction of bank stabilization on seven (7) sites in Arkabutla Creek Watershed, Tate and Panola Counties. The major items of work are: Clearing and Grubbing – 1 lump sum; Protective Cover – 6.0 ac.; Erosion Control Blanket – 335 S.Y.; Excavation, Common – 22,964 C.Y.; Drainfill – 140 C.Y.; Concrete, Class 3000M – 25.2 C.Y.; Corrugated Metal Pipe (CMP), Barrel, 24” Dia. – 64 L.F., 30” Dia. – 82 L.F., 42” Dia. – 84 L.F., 48” Dia. – 292 L.F.; CMP, Riser, 36” Dia. – 9 L.F., 42” Dia. – 10 L.F., 54” Dia. – 18 L.F., 60” Dia. – 9 L.F.; Rock Riprap – 7,630 tons; Pipe Anchor – 1 lump sum; Geotextile – 810 S.Y.; Earthfill, Slurry – 11,363 C.Y.; Earthfill, Slurry, Offsite – 832 C.Y.; Concrete Grout – 105 C.Y.; and Mobilization & Demobilization – 1 lump sum. This work is to be completed within 269 calendar days. Estimated price range for this work is $500,000 to $1,000,000. All responsible sources may submit a bid which shall be considered by the agency. Interested parties may access the invitation for bid on or about August 10, 2010 and download the solicitation files.
Update #1 ·
RECOVERY ACT PROJECT - The work consists of construction of bank stabilization on seven (7) sites in Arkabutla Creek Watershed, Tate and Panola Counties. The major items of work are: Clearing and Grubbing 1 lump sum; Protective Cover 6.0 ac.; Erosion Control Blanket 335 S.Y.; Excavation, Common 22,964 C.Y.; Drainfill 140 C.Y.; Concrete, Class 3000M 25.2 C.Y.; Corrugated Metal Pipe (CMP), Barrel, 24 Dia. 64 L.F., 30 Dia. 82 L.F., 42 Dia. 84 L.F., 48 Dia. 292 L.F.; CMP, Riser, 36 Dia. 9 L.F., 42 Dia. 10 L.F., 54 Dia. 18 L.F., 60 Dia. 9 L.F.; Rock Riprap 7,630 tons; Pipe Anchor 1 lump sum; Geotextile 810 S.Y.; Earthfill, Slurry 11,363 C.Y.; Earthfill, Slurry, Offsite 832 C.Y.; Concrete Grout 105 C.Y.; and Mobilization & Demobilization 1 lump sum. This work is to be completed within 100 calendar days. Estimated price range for this work is $500,000 to $1,000,000. All responsible sources may submit a bid which shall be considered by the agency. Interested parties may access the invitation for bid on or about August 10, 2010 and download the solicitation files.
Files
| File | Type | Posted |
|---|---|---|
| Abstract-10-0025.pdf | ||
| Arkabutla Creek Sites Plans.pdf | ||
| Arkabutla Creek Sites Specs.pdf | ||
| davisbaconMS113-heavy(Tate).pdf | ||
| IFB0025-10 RECOVERY.pdf |