NV FLAP 200(1), Beaver Dam Road

Awarded Award Notice Posted

Solicitation number
6982AF19B00007
Agency
Federal Highway Administration Department of Transportation
Awarded
to Trade West Construction, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
6982AF19C000017 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Beaver Dam State Park Lincoln County, Nevada 89008, United States

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

Awarded Vendors: Trade West Construction, Inc.. Contract Award Dollar Amount: 1827176.85. Contract Award Date: 2019-05-02.

Update #1 ·

The proposed project is to rehabilitate a 2.2-mile segment of Beaver Dam Road within Beaver Dam State Park. The project is located approximately 33 miles east of Caliente in Lincoln County, Nevada 89008. The roadway will be resurfaced with 6 inches of compacted gravel base course on top of the existing gravel roadway with minor widening to establish a 14-foot roadway width. Drainage improvements will include culvert replacements and low water crossing structures. The roadway may be closed to the public during construction. Coordination with the property owner, located at the south end of Beaver Dam Road will be necessary to provide access as needed. There are environmental restrictions on tree and brush removal.
Lincoln County Road Department maintains Beaver Dam Road under a road maintenance agreement with Bureau of Land Management (BLM). BLM land has been transferred to Nevada State parks under Lincoln County Land Bill.
Principal work activities include Surveying & Staking, Erosion Control Items, Roadway Aggregate (27,574 Sq. Yds.), Asphalt Paving (315 tons), Corrugated Metal Pipe Culverts (140 Lin Ft), Precast Concrete Box Culverts (87 Lin Ft), Concrete Low Water Crossing, and Temporary Traffic control.
It is anticipated this project will be advertised in early 2019 and be under construction in the Summer of 2019. The project has an estimated completion date of October 2019.
The estimated cost for the project is between $1 - 2 million.
.

Attachments

Files attached to this notice, newest first
File Type Posted
Beaver_Dam_Road_bid_tabs.pdf PDF
Beaver_Dam_Bid_Opening_Summary.pdf PDF
NV_FLAP_200(1)_Q&A.pdf PDF
6982AF19B000007.pdf PDF
Beaver_Dam_Road_Hydraulics_Report_100__Stamped.pdf PDF
FP14.pdf PDF
Plans_Beaver_Dam_Road_100_Percent_1.pdf PDF
Beaver_Dam_Road_Geotechnical_Report_-_Final.pdf PDF