NV_FLAP_200(1)_Q&A.pdf
PDF 258 KB Posted
- Attached to
- NV FLAP 200(1), Beaver Dam Road Federal contract opportunity
- Solicitation number
- 6982AF19B00007
About this file
Question and Answer
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Beaver_Dam_Road_bid_tabs.pdf | ||
| Beaver_Dam_Bid_Opening_Summary.pdf | ||
| FP14.pdf | ||
| Plans_Beaver_Dam_Road_100_Percent_1.pdf | ||
| Beaver_Dam_Road_Geotechnical_Report_-_Final.pdf | ||
| 6982AF19B000007.pdf | ||
| Beaver_Dam_Road_Hydraulics_Report_100__Stamped.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for NV FLAP 200(1), Beaver Dam Road
March 29, 2019
Questions Answers 1 SCR’s Section 153.02 Contractor Quality Control has deleted
(a)(1) Full-time, on-site QCM, but (a)(2) states a part-time QCM is required. Please define the amount of time per week a part-time QCM is going to be expected to spend. We want to meet the expectation of the Project Engineer/COTR.
Under Section 153.02 (a) (1) The Full-Time, on -site QCM has no other responsibilities other than managing quality control.
Under the Section 153 (a) (2) The Part - Time, on-site QCM has the same responsibilities as the full time QCM, but it is understood on smaller projects they can have other responsibilities as well.