NV_FLAP_200(1)_Q&A.pdf

PDF 258 KB Posted

Attached to
NV FLAP 200(1), Beaver Dam Road Federal contract opportunity
Solicitation number
6982AF19B00007
Issued by
Department of Transportation Federal Highway Administration

About this file

Question and Answer

View the file

Other files for this federal contract opportunity

Other files attached to NV FLAP 200(1), Beaver Dam Road, newest first.
File Type Posted
Beaver_Dam_Road_bid_tabs.pdf PDF
Beaver_Dam_Bid_Opening_Summary.pdf PDF
FP14.pdf PDF
Plans_Beaver_Dam_Road_100_Percent_1.pdf PDF
Beaver_Dam_Road_Geotechnical_Report_-_Final.pdf PDF
6982AF19B000007.pdf PDF
Beaver_Dam_Road_Hydraulics_Report_100__Stamped.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for NV FLAP 200(1), Beaver Dam Road

March 29, 2019

Questions Answers 1 SCR’s Section 153.02 Contractor Quality Control has deleted

(a)(1) Full-time, on-site QCM, but (a)(2) states a part-time QCM is required. Please define the amount of time per week a part-time QCM is going to be expected to spend. We want to meet the expectation of the Project Engineer/COTR.

Under Section 153.02 (a) (1) The Full-Time, on -site QCM has no other responsibilities other than managing quality control.

Under the Section 153 (a) (2) The Part - Time, on-site QCM has the same responsibilities as the full time QCM, but it is understood on smaller projects they can have other responsibilities as well.