Nez Perce-Clearwater NFs - Van Buren Creek AOP Culvert Replacement

Award Notice Posted

Solicitation number
AG-0343-C-16-0048
Agency
Awarded
to Stone Ridge Construction, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
AG-0343-C-16-0042 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record
Place of performance
Nez Perce-Clearwater NFs Grangeville Office 104 Airport Road Grangeville, Idaho 83530, United States

Notice details come from SAM.gov. Updated .

Notice text

6 versions

Update #6 · Latest ·

Contract was awarded on 6/24/2016 for Base Items only.

Update #5 ·

Description of Work:

Van Buren Creek AOP Culvert Replacement NFSR 2002 MP 5.98


The project consists of the removal of an existing culvert and replacing it with a new 19'-0" span by 6'-4" rise steel structural plate arch culvert. Improvements consist of but are not limited to: clearing and shaping the roadway to the project site for contractor access, structure excavation, excavation and reshaping of the channel, installation of precast footings, placement of riprap, foundation fill, installation of a structural steel plate arch culvert, structural backfill, excavation and embankment of the roadway approaches, and gravel surfacing.


Project Location:

The project is located on the Salmon River Ranger District of the Nez Perce-Clearwater National Forests, approximately 33 miles northeast of Riggins in Idaho County, Idaho (Section 33, Township 26 north, Range 3 east). A vicinity map has been uploaded to FBO as an attachment to this notice.

Price Range: The Government's estimate for the project is between $100,000 and $250,000.


Performance Deadlines: Work on the project site shall commence no earlier than July 1, 2016 and be completed no later than September 15, 2016. All in-stream work must take place between July 15 and August 30, 2016.


Solicitation shall be issued on May 20th with contract award anticipated approximately June 22th. Original bid bonds are required. The project has been set-aside for small businesses.


Solicitation was amended on 6/14/2016.  Response deadline was not extended.  Offerors must acknowledge amendment.

Solicitation was amended 6/17/16 to correct a clear mistake in the Schedule of Items.  Response deadline was not extended.  Offerors shall acknowledge the amendment.

Based on offeror inquiries, response deadline was extended via Amendment 3 to June 21, 2016 at 4:00 PM local time.

Update #4 ·

Description of Work:

Van Buren Creek AOP Culvert Replacement NFSR 2002 MP 5.98


The project consists of the removal of an existing culvert and replacing it with a new 19'-0" span by 6'-4" rise steel structural plate arch culvert. Improvements consist of but are not limited to: clearing and shaping the roadway to the project site for contractor access, structure excavation, excavation and reshaping of the channel, installation of precast footings, placement of riprap, foundation fill, installation of a structural steel plate arch culvert, structural backfill, excavation and embankment of the roadway approaches, and gravel surfacing.


Project Location:

The project is located on the Salmon River Ranger District of the Nez Perce-Clearwater National Forests, approximately 33 miles northeast of Riggins in Idaho County, Idaho (Section 33, Township 26 north, Range 3 east). A vicinity map has been uploaded to FBO as an attachment to this notice.

Price Range: The Government's estimate for the project is between $100,000 and $250,000.


Performance Deadlines: Work on the project site shall commence no earlier than July 1, 2016 and be completed no later than September 15, 2016. All in-stream work must take place between July 15 and August 30, 2016.


Solicitation shall be issued on May 20th with contract award anticipated approximately June 22th. Original bid bonds are required. The project has been set-aside for small businesses.


Solicitation was amended on 6/14/2016.  Response deadline was not extended.  Offerors must acknowledge amendment.

Solicitation was amended 6/17/16 to correct a clear mistake in the Schedule of Items.  Response deadline was not extended.  Offerors shall acknowledge the amendment.

Update #3 ·

Description of Work:

Van Buren Creek AOP Culvert Replacement NFSR 2002 MP 5.98


The project consists of the removal of an existing culvert and replacing it with a new 19'-0" span by 6'-4" rise steel structural plate arch culvert. Improvements consist of but are not limited to: clearing and shaping the roadway to the project site for contractor access, structure excavation, excavation and reshaping of the channel, installation of precast footings, placement of riprap, foundation fill, installation of a structural steel plate arch culvert, structural backfill, excavation and embankment of the roadway approaches, and gravel surfacing.


Project Location:

The project is located on the Salmon River Ranger District of the Nez Perce-Clearwater National Forests, approximately 33 miles northeast of Riggins in Idaho County, Idaho (Section 33, Township 26 north, Range 3 east). A vicinity map has been uploaded to FBO as an attachment to this notice.

Price Range: The Government's estimate for the project is between $100,000 and $250,000.


Performance Deadlines: Work on the project site shall commence no earlier than July 1, 2016 and be completed no later than September 15, 2016. All in-stream work must take place between July 15 and August 30, 2016.


Solicitation shall be issued on May 20th with contract award anticipated approximately June 22th. Original bid bonds are required. The project has been set-aside for small businesses.


Solicitation was amended on 6/14/2016.  Response deadline was not extended.  Offerors must acknowledge amendment.

Update #2 ·

Description of Work:

Van Buren Creek AOP Culvert Replacement NFSR 2002 MP 5.98


The project consists of the removal of an existing culvert and replacing it with a new 19'-0" span by 6'-4" rise steel structural plate arch culvert. Improvements consist of but are not limited to: clearing and shaping the roadway to the project site for contractor access, structure excavation, excavation and reshaping of the channel, installation of precast footings, placement of riprap, foundation fill, installation of a structural steel plate arch culvert, structural backfill, excavation and embankment of the roadway approaches, and gravel surfacing.


Project Location:

The project is located on the Salmon River Ranger District of the Nez Perce-Clearwater National Forests, approximately 33 miles northeast of Riggins in Idaho County, Idaho (Section 33, Township 26 north, Range 3 east). A vicinity map has been uploaded to FBO as an attachment to this notice.

Price Range: The Government's estimate for the project is between $100,000 and $250,000.


Performance Deadlines: Work on the project site shall commence no earlier than July 1, 2016 and be completed no later than September 15, 2016. All in-stream work must take place between July 15 and August 30, 2016.


Solicitation shall be issued on May 20th with contract award anticipated approximately June 22th. Original bid bonds are required. The project has been set-aside for small businesses.


 

Update #1 ·

Description of Work:

Van Buren Creek AOP Culvert Replacement NFSR 2002 MP 5.98


The project consists of the removal of an existing culvert and replacing it with a new 19'-0" span by 6'-4" rise steel structural plate arch culvert. Improvements consist of but are not limited to: clearing and shaping the roadway to the project site for contractor access, structure excavation, excavation and reshaping of the channel, installation of precast footings, placement of riprap, foundation fill, installation of a structural steel plate arch culvert, structural backfill, excavation and embankment of the roadway approaches, and gravel surfacing.


Project Location:

The project is located on the Salmon River Ranger District of the Nez Perce-Clearwater National Forests, approximately 33 miles northeast of Riggins in Idaho County, Idaho (Section 33, Township 26 north, Range 3 east). A vicinity map has been uploaded to FBO as an attachment to this notice.

Price Range: The Government's estimate for the project is between $100,000 and $250,000.


Performance Deadlines: Work on the project site shall commence no earlier than July 1, 2016 and be completed no later than September 15, 2016. All in-stream work must take place between July 15 and August 30, 2016.


Solicitation shall be issued in mid-May with contract award anticipated approximately June 20th. Original bid bonds are required. The project has been set-aside for small businesses.


 

Files

File Type Posted
Amend3.doc DOC document
Amend2.doc DOC document
VanBurenAmendment1Pg2thru7.docx DOCX document
Amend1Page1VanBuren.doc DOC document
SignedVanBurenConPlans.pdf PDF
Van_Buren-FSSS.docx DOCX document
VanBurenCONRFP.docx DOCX document
Van_Buren_Vicinity_Map.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity