Maybeso-Hollis Wastewater System Replacement

Awarded Award Notice Posted

Solicitation number
12010918R0007
Agency
Region 10 - Alaska Region Forest Service, Department of Agriculture
Awarded
to Ketchikan Ready-Mix & Quarry, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
12010918C0031 Federal contract award
NAICS code
237110 Water and Sewer Line and Related Structures Construction
PSC
Not on record
Place of performance
Maybeso Research Center Hollis, Alaska, United States

Notice details come from SAM.gov. Updated .

Notice text

7 versions

Update #7 · Latest ·

Awarded Vendors: Ketchikan REady Mix & Quarry, Inc.. Contract Award Dollar Amount: $338,190. Contract Award Date: 2018-08-30.

Update #6 ·

UPDATE 8/7/2018: This update provides a secondary point of contact for quesions, submission of proposals, and delivery of bid guarantee. E-mails should be sent to both the primary and secondary points of contact. The mailing address is the same for both individuals.
This update also posts the draft Alaska Department of Environmental Conservation Permit package. The successful contractor will be responsible for obtaining the permit including all associated fees.
*************************
UPDATE: Request for Proposals has been issued with this update.
*************************
This requirement is for the replacement of the exisitng wastewater treatment system at the US Forest Service Maybeso Research Center in Hollis Alaska. Work includes site clearing, excavation, electrical work, trenching, demo and disposal of the existing system and installation of a new on-site wastewater system.
The project is located on Forest Service property next to the "old" ferry terminal in Hollis Alaska.
Draft project drawings and draft specifications are provided with this presolicitation notice for awareness. The Forest Service does not expect these documents to change between issuance of this notice and posting of the final RFP.
The government anticipates setting this requirement aside as a Total Small Business Set Aside. The final set aside will be noted when the RFP is posted..

Update #5 ·

Added: Jun 20, 2018 9:19 pm Modified: Aug 07, 2018 12:23 pmTrack Changes UPDATE 8/7/2018:  This update provides a secondary point of contact for quesions, submission of proposals, and delivery of bid guarantee.  E-mails should be sent to both the primary and secondary points of contact.  The mailing address is the same for both individuals.

This update also posts the draft Alaska Department of Environmental Conservation Permit package.  The successful contractor will be responsible for obtaining the permit including all associated fees.

*************************

UPDATE:  Request for Proposals has been issued with this update.

*************************

This requirement is for the replacement of the exisitng wastewater treatment system at the US Forest Service Maybeso Research Center in Hollis Alaska.  Work includes site clearing, excavation, electrical work, trenching, demo and disposal of the existing system and installation of a new on-site wastewater system.

The project is located on Forest Service property next to the "old" ferry terminal in Hollis Alaska.

Draft project drawings and draft specifications are provided with this presolicitation notice for awareness.  The Forest Service does not expect these documents to change between issuance of this notice and posting of the final RFP.

The government anticipates setting this requirement aside as a Total Small Business Set Aside.  The final set aside will be noted when the RFP is posted.

Update #4 ·

UPDATE: Request for Proposals has been issued with this update.
*************************
This requirement is for the replacement of the exisitng wastewater treatment system at the US Forest Service Maybeso Research Center in Hollis Alaska. Work includes site clearing, excavation, electrical work, trenching, demo and disposal of the existing system and installation of a new on-site wastewater system.
The project is located on Forest Service property next to the "old" ferry terminal in Hollis Alaska.
Draft project drawings and draft specifications are provided with this presolicitation notice for awareness. The Forest Service does not expect these documents to change between issuance of this notice and posting of the final RFP.
The government anticipates setting this requirement aside as a Total Small Business Set Aside. The final set aside will be noted when the RFP is posted..

Update #3 ·

Added: Jun 20, 2018 9:19 pm Modified: Jul 25, 2018 7:47 pmTrack Changes UPDATE:  Request for Proposals has been issued with this update.

*************************

This requirement is for the replacement of the exisitng wastewater treatment system at the US Forest Service Maybeso Research Center in Hollis Alaska.  Work includes site clearing, excavation, electrical work, trenching, demo and disposal of the existing system and installation of a new on-site wastewater system.

The project is located on Forest Service property next to the "old" ferry terminal in Hollis Alaska.

Draft project drawings and draft specifications are provided with this presolicitation notice for awareness.  The Forest Service does not expect these documents to change between issuance of this notice and posting of the final RFP.

The government anticipates setting this requirement aside as a Total Small Business Set Aside.  The final set aside will be noted when the RFP is posted.

Update #2 ·

This requirement is for the replacement of the exisitng wastewater treatment system at the US Forest Service Maybeso Research Center in Hollis Alaska. Work includes site clearing, excavation, electrical work, trenching, demo and disposal of the existing system and installation of a new on-site wastewater system.
The project is located on Forest Service property next to the "old" ferry terminal in Hollis Alaska.
Draft project drawings and draft specifications are provided with this presolicitation notice for awareness. The Forest Service does not expect these documents to change between issuance of this notice and posting of the final RFP.
The government anticipates setting this requirement aside as a Total Small Business Set Aside. The final set aside will be noted when the RFP is posted..

Update #1 ·

Added: Jun 20, 2018 9:19 pm This requirement is for the replacement of the exisitng wastewater treatment system at the US Forest Service Maybeso Research Center in Hollis Alaska.  Work includes site clearing, excavation, electrical work, trenching, demo and disposal of the existing system and installation of a new on-site wastewater system.

The project is located on Forest Service property next to the "old" ferry terminal in Hollis Alaska.

Draft project drawings and draft specifications are provided with this presolicitation notice for awareness.  The Forest Service does not expect these documents to change between issuance of this notice and posting of the final RFP.

The government anticipates setting this requirement aside as a Total Small Business Set Aside.  The final set aside will be noted when the RFP is posted.