About this file

Request for Proposals

View the file

Other files for this federal contract opportunity

Other files attached to Maybeso-Hollis Wastewater System Replacement, newest first.
File Type Posted
s_Wastewater_System_ADEC_Permit_Package_3.1.17.pdf PDF
Attach6_EPA_CPG_LandscapingProducts.pdf PDF
Attach2_WastewaterSystem_Drawings.pdf PDF
Attach5_EPA_CPG_ConstructionProducts.pdf PDF
Attach1_Specifications.pdf PDF
Attach3_WageDetermination_AK180001.pdf PDF
Attach4_BioPreferred_Product_Categories.pdf PDF
DRAFT_WastewaterSystem_FullSizeDrawings_3.1.17.pdf PDF
DRAFT_Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

911975

ALASKA REGIONAL OFFICE

709 WEST 9TH STREET

JUNEAU AK 99802

Mari Meiners (USPS)

P.O Box 21628, Juneau, AK 99802 FedEx/UPS/DHL/Hand Delivery:

709 W. 9th St, 5th Floor, Juneau AK 99801

MARI MEINERS 907-586-8746

1x 07/24/2018

12010918R0007

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This solicitation including all attachments

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 305 calendar days and complete it within ________________ ________________ calendar days after receiving

F.1 FAR 52.211-10

08/24/2018

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

ALASKA REGIONAL OFFICE

709 WEST 9TH STREET

JUNEAU AK 99802

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 36

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

12010918R0007

This is a request for proposals for removal of the existing Maybeso-Hollis Wastewater System and installation of a new wastewater system. The project is located in Hollis Alaska on the East side of Prince of Wales Island in Southeast Alaska.

The magnitude of construction is estimated between $250,000 and $500,000.

A pre-proposal conference will be held on Friday, August 3, 2018 at 10:00 a.m. Call in number is 888-844-9904, passcode 6419479#.

Proposals are due no later than 10:00 a.m. on Friday August 24, 2018 to the address listed in section 8 of the SF-1442. The PO Box listed is for US Postal Service delivery, and the street address is for Package Delivery such as FedEx, UPS, DHL, etc. or hand delivery.

FOB: Destination

Maybeso-Hollis Wastewater System Replacement

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

12010918R0007, Maybeso-Hollis Wastewater System Replacement

4 | P a g e

PART I—THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

Item Description Method of Meas.

Qty Unit Unit Price Amount

02 00 00 Construction Survey LSQ 1 LS $ $

03 26 23 Mobilization LSQ 1 LS $ $

26 25 43 Electrical Installation LSQ 1 LS $ $

31 00 00A D-1 Base Course Material AQ 21 Ton $ $

31 00 00B Asphalt AQ 20 SY $ $

31 00 00C Bedding Material AQ 220 Ton $ $

31 00 00D Drain Rock Material AQ 61 Ton $ $

31 00 00E Class II Riprap AQ 14 Ton $ $

31 00 00F Structural Fill AQ 18 Ton $ $

31 00 00G Geotextile Fabric AQ 228 SY $ $

31 10 00 Clearing LSQ 1 LS $ $

31 25 00 Erosion and Pollution Control Plan LSQ 1 LS $ $

33 31 00A Sewer Pipe System LSQ 1 LS $ $

33 31 00B Tank & Manholes LSQ 1 LS $ $

33 31 00C UV Disinfection System LSQ 1 LS $ $

33 31 00D Distribution Box LSQ 1 LS $ $

Total All Items

N/A $

Additional Vendor Information For Administration Contact Name:

Office Phone No:

Cell Phone No:

DUNS No:

SAM Account Expiration Date:

Email:

5 | P a g e

NOTE: Offerors must submit prices for all items included in the price schedule. Mobilization does not include on-site construction activities including the movement of personnel, materials or equipment within the project site.

SECTION C--DESCRIPTION/SPECIFICATIONS

C.1 Scope of Contract This requirement is for the replacement of the existing Maybeso-Hollis wastewater treatment with an on-site system. The existing system was installed to support the U.S. Forest Service (USFS) Maybeso Research Center and the neighboring Hollis School. The work includes site clearing, excavation, electrical work, trenching, installation of a new on-site wastewater system and demolition and removal of the existing system.

C.2 General Conditions and Requirements Safety: Contractor shall submit a written Safety Plan within fourteen (14) calendar days after the Notice to Proceed, but prior to any on-site activities. The Safety Plan shall address safety of the public and contractor personnel, and protection of improvements. The Safety Plan shall comply with and reference all applicable OSHA Construction and Workplace requirements. See FAR 52.236-13 Accident Prevention with Alternate I

(NOV 1991).

Professional Licensing and Certifications: All Electrical and Plumbing work shall be performed or supervised by a journeyman electrician/plumber with a current State of Alaska certificate of fitness. Copies of certificates of fitness will be required prior to the contractor receiving Notice to Proceed.

Electrical Inspection and Building Permits: The Contractor shall arrange for and provide inspection of the electrical installation by an Electrical Administrator licensed in the State of Alaska. The Electrical Administrator shall certify, in writing, that the electrical installation meets all applicable codes. The Contractor is not required to obtain any building permits or inspections other than the Electrical Inspection.

C.3 Project Location This project is located in Hollis Alaska on the East side of Prince of Wales Island in Southeast Alaska. Hollis is located 29 miles from Craig by road and 35 miles West of Ketchikan by water or small plane. The work site is located on Forest Service property next to the “old” ferry terminal.

C.4 Magnitude of Construction The magnitude of the construction is estimated between $250,000 and $500,000.

C.5 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions FPMR Part 101-29 (AUG 1998)

(a) The GSA Index of Federal Specifications, Standards and Commercial Item Description, FPMR Part 101- 29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to--

GSA Federal Supply Service Specifications Section, Suite 8100 470 East L'Enfant Plaza SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978.

(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in

6 | P a g e this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

C.6 AGAR 452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C.7 Submittals All Submittals shall include the following information unless otherwise required in the specification:

1. Date and revision dates.

2. Project name and contract number.

3. Names of Contractor, subcontractor, supplier, and manufacturer.

4. Specifications section number.

5. Field dimensions and relation to adjacent structures.

6. Applicable standards such as ASTM or Federal Specifications.

7. Contractor's stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents. Provide all submittals within 14 calendar days of issuance of the Notice to Proceed unless otherwise required by the specification.

C.8 Product Samples and Submittals The following product samples and/or submittals are required for this project:

Title Referenced by

Specification No Time of Government Approval After Submittal surveyor registration 02 00 00 10 days Final Location 02 00 00 10 days As built survey 02 00 00 10 days Staging Plan 03 26 23 10 days Design mix 03 30 00 10 days Cut sheets hot box 26 05 43 10 days Technical Data Wire 26 05 43 10 days Data sheets Conduit 26 05 43 10 days Cut sheets load center 26 05 43 10 days Technical data grounding cable type

26 05 43 10 days

Cut sheets Geotextile 31 00 00 10 days Slit fence & control measures

31 00 00 10 days

Cut sheets seeding 31 00 00 10 days Errosion and pollution control plan

33 31 00 10 days

Product Data 33 31 00 10 days Tie –in work plan 33 31 00 10 days Marine outfall tie-in work plan

35 53 00 10 days

Cut sheets for ballast 35 53 00 10 days

7 | P a g e

C.9 Shop Drawings The following shop drawings shall be submitted on this project:

Title Referenced by

Specification No Time of Government Approval After Submittal

Detailed installation layout

33 31 00 10 days

C.10 Material Certifications and Testing Reports The following material certifications and/or testing reports shall be submitted on this project:

Title Referenced by

Specification No Time of Government Approval After Submittal

Gradation reports for Aggregate

31 00 00 10 days

SECTION D--PACKAGING AND MARKING

D.1 Project Labeling for Official Correspondence The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication, to include emails, starting upon notice of award.

NOTE: Forest Service solicitation and contract identifiers are new effective 01 Oct 2017. The solicitation number, for this requirement, will include an “R” in the identifier. Solicitation numbers look like this:

12010918R0003. Contracts will have a similar identifier but will have a “C” in place of the “R”. Contract numbers look like this: 12010918C0010.

SECTION E--INSPECTION AND ACCEPTANCE

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

E.1 52.246-12 Inspection of Construction (AUG 1996)

E.2 AGAR 452.246-70 Inspection and Acceptance (FEB 1988) (b) fill in: Worksite Location, Hollis, AK.

E.3 Inspection and Testing Performed by Government The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.

E.4 Conformity with Drawings and Specifications Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

8 | P a g e

SECTION F--DELIVERIES OR PERFORMANCE

F.1 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to

(a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 305 days after award. The time stated for completion shall include final cleanup of the premises.

F.2 52.242-14 Suspension of Work (APR 1984)

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 AGAR 452.215-73 Post Award Conference (NOV 1996) A post award or pre-work conference with the successful offeror is required. It will be scheduled and held within a reasonable time after award and prior to the issuing of a Notice to Proceed—typically within ten (10) days. The conference will be held at the Juneau Forestry Sciences Laboratory, 11175 Auke Lake Way, Juneau AK 99801. The Contractor is required to attend in person.

G.2 Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP)

a. Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform (IPP). "Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is: https://www.ipp.gov. The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fms.treas.gov or phone (866) 973-3131.

b. Final Payment. The final invoice must be accompanied by a release of claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically accepted from the operation of the release. Final payment will not be approved without a properly executed Contract Release, Form 6300-16.

c. In addition, when submitting the invoice, the Contractor shall submit payrolls, subcontractor payment information and a spreadsheet detailing the payment breakdown in accordance with the Pay Items in the Schedule of Items, Section B.1 (either electronically in IPP, hard copy, or via fax) to the Contracting Officer (see FAR 52.232-5 Payments Under Fixed Price Construction Contracts).

https://www.ipp.gov/ mailto:IPPCustomerSupport@fms.treas.gov

9 | P a g e

G.3 Contract Administration

a. This contract will be administered by the Contracting Officer located at:

Alaska Region, Acquisition Management Attn: Mari Meiners

709 W 9th Street Juneau AK 99802-1628

b. All matters related to the performance of this contract shall be coordinated through the Contracting Officer.

G.4 Designation of Contracting Officer’s Representative

a. The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

b. The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

c. On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

G.5 Contractor’s Designated Representative It is required that the Contractor have a designated representative available on the project during the entire project and that the representative be able to speak and understand English. When designating a representative, the Contractor shall furnish a copy of the designation in writing to the Contracting Officer.

Such designation shall clearly indicate the name and limitations (if any) of authority of the representative. If the Contractor intends to designate a representative prior to the pre-work meeting, the representative is strongly encouraged to attend that meeting.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 Potential Safety Hazards

(a) Data and information furnished or referred to below is for the Contractor's information. The

Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite. See also FAR 52.236-13 Accident Prevention.

(b) The following checked activities have been identified by the Government as potential safety hazards.

10 | P a g e

[ ] Confined space entry.

[x] Temporary excavation/deep trenching/slope stability.

[x] Tree falling.

[ ] Fall hazard from work heights exceeding six feet.

[ ] Blasting.

[ ] Traffic control on high-volume and/or high-speed and/or limited visibility roads.

[x] Heavy equipment operation.

[ ] Tree climbing and/or tower climbing.

[ ] Fire hazards.

[ ] Hazardous materials handling.

[x] Electrical hazard.

[ ] Hydraulic and/or pneumatic and/or other high pressure hazards.

[ ] Mechanical hazards such as pulleys, springs, etc.

[ ] Other __________________________________

H.2 Industrial Camps Forest Service regulations for Use of Campgrounds prohibit occupancy of developed recreation sites for other than primarily recreation purposes. No industrial camping will be authorized at these sites.

A special use permit is required on National Forest land for industrial camps. These permits are to be obtained by the Contractor through the Contracting Officer. Such permission, if granted, will be without charge to the Contractor but may include use restrictions.

One self-contained camp unit will be allowed at each staging area and equipment or supply dump for use by a watchman.

H.3 Salvage Rights No Contractor salvage rights exist under the contract unless specifically provided elsewhere herein.

H.4 Special Equipment Cleaning Requirements All earth moving equipment (loaders, excavators, dump trucks, etc.) moved to the job site shall be cleaned of weeds and their seeds prior to each entrance onto the National Forest lands. Cleaning shall consist of the removal of all dirt, grease, debris, and materials that may harbor noxious weeds and their seeds. This may require the use of a pressure hose.

Equipment shall be made available for visual inspection by the Forest Service prior to entering Forest Service lands. The Contractor shall advise of a proposed date for mobilization. Inspections will take place at mutually agreeable en-route locations in advance of entry onto National Forest lands.

Special care shall be taken to assure removal of the following noxious weeds and their seeds:

spotted knapweed (Centaurea maculosa) diffuse knapweed (C. diffusa) yellow starthistle (C. solstitialis) gorse (Ulex europaeus) rush skeletonweed (Chondrilla juncea) tansy ragwort (Senecio jecobaea) purple loosestrife (Lythrum salicaria) distaff thistle (Carthamus lanatus) scotch broom (Cytisus scoparius)

The Contractor shall take special care under this contract to prevent contamination of water at the work sites with any petroleum residues from mechanical equipment operations. This shall include daily inspection and cleaning as appropriate.

11 | P a g e

H.5 Protection of Cultural Resources (the following is in addition to AGAR Clause 452.236-73 Archaeological or Historic Sites (Nov 1996) Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1979 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by Forest Service. Forest Service may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object which is or may be entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified. Discovery of such areas or objects by either party shall be promptly reported to the other party.

Contractor shall protect all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destruction, obliteration, removal or damage during Contractor's Operations. In accordance with 36 CFR 296.14(c), Contractor shall bear costs of restoration, provided that such payment shall not relieve Contractor from civil or criminal remedies otherwise provided by law.

Wheeled or track-laying equipment shall not be operated within such areas except on roads. Unless agreed otherwise, trees will not be felled into such areas.

H.6 Landscape Preservation (the following is in addition to AGAR Clause 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) incorporated by reference in section I).

(a) The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. The Contractor shall confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states. If a spill of petroleum product should occur in water, the Contractor shall take immediate action to clean up or contain the spill, then immediately notify the Engineer and the Division of Oil Spill Prevention and Response, telephone 1-907- 465-5340 and then immediately notify the Contracting Officer.

Contractor shall have a SPILL RESPONSE KIT on the project whenever equipment is operating. The spill kit shall be sufficient to absorb 34 gallons of oil, designed to float on the surface, while absorbing oil and repelling water. The KIT shall meet or exceed the physical properties of “New Pig Products Spill Kit #408”.

Oil absorbing mats are required under all stationary equipment, or equipment being serviced within the Forest Boundary to prevent leaking or spilled petroleum base products from contaminating soil and water resources.

Such material will be furnished by Contactor and approved by Contracting Officer.

Servicing of all equipment shall be done only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

12 | P a g e

Equipment shall be furnished on a fully operational basis, of modern design and in good operating condition with no fuel or oil leaks. Repairs and move-in/move-out are the Contractor’s responsibility. All equipment shall be power washed and shall be clean prior to entering Forest Service Land.

(c) No objectionable material shall be allowed to enter any stream, river, lake, or other body of water.

Material which falls in these areas shall be retrieved and disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the project limits shall be repaired as directed by the Contracting Officer.

(d) The Contractor shall not operate equipment or otherwise disturb the natural vegetation and soil beyond the areas flagged on the ground or beyond two feet from edge of walkways, top of cuts, or toe of fills.

(e) The Contractor will make every reasonable attempt to preserve the scenic and natural environment along this construction project.

(f) Prior to the start of construction the Contractor shall submit to the Engineer for approval a schedule and plan for temporary pollution control measures for the following phases of work: None

H.7 Value Engineering Value engineering change proposals which change the service or function of a facility or produce irreconcilable conflicts with management objectives will not be considered.

The following work is excluded from consideration under the Value Engineering clause: None

H.8 Control of Material A Rights In and Use of Materials: The Contractor may use on the project suitable stone, gravel, or sand encountered in the excavation.

B Excavation: Unclassified.

C Material Sources:

1. Native timber material used in construction shall not be taken within sight of any road or trail. Stumps resulting from tree cutting shall be no more than six (6) inches in height. All debris resulting from preparation of the native timber for use, shall be scattered not more than four (4) inches in depth and out of meadows, stream courses, lakes and ponds.

2. Rocks and mineral soil excavated within the normal excavation shall be conserved and used as needed.

D Storage and Stockpiling of Materials: Materials shall be stored to assure the preservation of quality and fitness for the work. Stored materials shall be located to facilitate their prompt inspection. Sites on Forest Service administered land, approved by the Forest Service, may be used for storage purposes and for the placing of Contractor's plant equipment. All storage sites provided by the Forest Service shall be restored at the Contractor's expense. Contractor shall be responsible for making arrangements for storage on other than Forest Service administered lands.

E Earthwork Tolerances: Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground.

"Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

13 | P a g e

H.9 Construction Stakes, Lines and Grades

(a) The Contractor shall do all further surveying, staking, and engineering to establish the horizontal and vertical control necessary to result in having the finished work comply with the lines and grades shown on the Drawings or stated in the specifications. This work is incidental to the pay items.

(b) If any construction control points have been destroyed or displaced, or are erroneous, the Contractor shall promptly notify the Engineer. If these points are destroyed or displaced due to Contractor's negligence or operation, the cost for replacing them will be charged to the Contractor.

(c) In case of any construction changes, the Contractor shall cooperate with the Engineer and facilitate the prompt reestablishment of the field control for the adjusted work.

H.10 Prosecution of Work

(a) Construction activity shall be limited to the hours between 7:00 a.m. and 6:00 p.m., Monday through Friday, unless other hours are approved in writing by the COR. The Contractor shall conduct activities so that interference with the public shall be kept at a minimum. The project site shall be open to public access and free of hazards on weekends. Any activities requiring closure to the public shall be scheduled with the COR at least 7 days in advance.

(b) The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.

(c) The use of mechanized equipment such as power saws, power rock drills, motorcycles, and bicycles, is prohibited within the wilderness.

H.11 Protection of Improvements Unless otherwise agreed to in writing, Contractor shall remove the existing traffic signs within the work area and reinstall to their approximate existing locations.

H.12 Sanitation Requirements Unless substitute measures or equipment are authorized in writing by the Contracting Officer, protection of air and water quality will include the use of approved chemical toilets by all persons engaged in road construction or in removing timber under this contract while they are within the boundaries of the Forest.

Such facilities shall be furnished by Contractor in quantities and at locations approved by the Engineer. No habitation or overnight dwelling by employees of Contractor will be permitted on National Forest land without advance written approval from the Contracting Officer.

H.13 Final Cleanup Contractor shall remove and dispose all of its own trash and refuse from the contract area. Material to be removed includes, but is not limited to: tin cans, aluminum foil, glass, paper, garbage, used engine oil, oil filters, oil cans, grease cartridges, etc. This Cleanup is a subsidiary item for which no special payment will be made. All debris shall be disposed off of National Forest Land and in accordance with State and Local disposal requirements.

H.14 Methods of Measurement One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:

14 | P a g e

(a) Designed Quantities (DQ). These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project.

Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

(1) As a result of changes in the work authorized by the Contracting Officer.

(2) As a result of the Contracting Officer determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

(3) As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

(b) Staked Quantities (SQ). These quantities are determined from staked measurements prior to construction.

(c) Actual Quantities (AQ). These quantities are determined from measurement of completed work.

(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract including necessary materials, equipment, and labor to complete the job. They will not be measured.

H.15 Emergency Control (the following is in addition to AGAR Clause 452.236-77 Emergency Response (NOV 1996) incorporated by reference in Section I.).

(a) Immediately extinguish without expense to the Government all fires on or in the vicinity of the project which are caused by the Contractor's employees, whether set directly or indirectly as a result of construction operations, with or without direction by the Forest Service. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government resulting from fires set or caused by Contractor's employees or resulting from construction operations.

(b) Contractor's Responsibility for Controlling Other Emergencies - When requested by the Contracting

Officer, allow the Forest Service to temporarily use employees and equipment for emergency control work. Payment will be made at not less than the current area rate established by the Forest Service.

(c) Fire fighting equipment will be required during the fire season from May 10 to August 31, and during any other period of fire danger designated by the Contracting Officer.

Furnish rust-free fire tools to equip all workers employed in Contractor's operations at each separate work site. Maintain tools in serviceable condition and keep tools in one or more weather-tight fire tools boxes.

Paint fire tools boxes red, mark "tools for Fire Only" with letters at least 3” high, and keep sealed. Post a list of the contents inside each fire tool box so as to be visible when opened.

Kind of Tool No. of People Working in Area 1-4 5-9 10-15 16-20 Axe, d.b chopping, 32-inch min. handle 1 1 2 3

15 | P a g e

Shovels, L.H. R.P., No. 0 or larger 1 3 6 7 Pulaski, 32-inch min. handle 2 3 7 10 File, 10-inch mill bastard 1 1 1 2 Pumps, backpack cans, 5-gal filled with water

1 2 2 3

Equip each internal combustion engine with a spark arrester qualified and rated USDA-Forest Service, Standard 5100-1, unless it is:

(a) Equipped with a turbine-driven exhaust supercharger such as the turbocharger. There shall be no exhaust bypass.

(b) A multi-position engine, such as on a chain saw, which is equipped with screen arrester, as described in the Forest Service Spark Arrester guide.

A spark arrester, which does not meet the requirements in this guide may be approved upon submission of acceptable proof that the arrester is at least 80 percent efficient in retention, attrition, or destruction of carbon particles. Such arrester may be required to meet higher standards as improvements in design and efficiency are discovered.

(c) A passenger-carrying vehicle or light truck intended primarily for use on roads, and equipped with a factory designed muffler and exhaust system.

(d) A heavy duty truck, such as a dump or log truck, or other vehicle used for commercial hauling, used only on roads and equipped with a factory designed muffler and with a vertical stack exhaust system extending above the cab.

Properly install and constantly maintain in serviceable condition all exhaust equipment described in this Subsection, including spark arresters and mufflers.

Equip each unit of mobile or stationary power equipment, including trucks, with one shovel, and at least one fire extinguisher meeting one of the following specifications:

1. 2-1/2 pound size or larger dry chemical type.

2. 4-pound size or larger carbon dioxide type.

Test or check each extinguisher for proper functioning prior to the beginning of fire precautionary period.

Provide each gasoline power saw with one chemical-pressurized fire extinguisher of not less than 8-ounce capacity by weight. Maintain the extinguisher in good working order at all times.

Do not burn camp refuse, brush, slash, or debris such as that resulting from clearing around camps or on rights-of-way, without the written approval of the Contracting Officer. Submit written requests for burning to the Contracting Officer at least 48 hours in advance of intended burning. The Contracting Officer will approve routine camp refuse disposal incineration in the camp development proposal.

H.16 Notification of Work Schedule At the pre-work meeting provide a proposed schedule of work showing dates of major work items. Also incorporated into this contract is FAR 52.236-15, Schedules for Construction Contracts.

16 | P a g e

H.17 Required Permitting The contractor is responsible for obtaining all required permits including the NPDES Stormwater Permit for the site prior to beginning construction activities. The Forest Service has a draft package prepared that will be provided to the successful contractor after award and upon request. The contractor may not begin work on the project until all permits have been obtained and the CO issues the contractor a Notice to Proceed.

H.18 Product Substitution Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

A. When submitted within 30 days after contract award, the Contracting Officer will consider formal requests for substitution of products, equipment and methods, in place of those specified. Requests submitted after 30 days will be considered only in case of product unavailability or other conditions beyond the control of Contractor. Requests shall provide the information and be in the format as specified in paragraph B below.

B. Submit separate request for each substitution. Support each request with:

1. Complete data substantiating compliance of proposed substitution with requirements stated in contract documents:

a. Product identification, including manufacturer's name and address.

b. Manufacturer's literature; identify:

1) Product description

2) Reference standards

3) Performance and test data

c. Samples, as applicable

d. Name and address of similar projects on which product has been used, and date of each installation.

e. Comparative data of item to be deleted by proposed substitution. Include drawings to same (or larger) scale as pertinent portion of contract documents and marked to show how differences will be accommodated.

f. Show complete system/assembly as revised to accommodate proposed alternate for difference in performance, size, configuration, connections, service, accessibility, or any other significant characteristics.

g. Show complete layout of system except that which is identical to contract documents unless unchanged portion must be shown to indicate clearances, etc.

h. Include complete detail drawings of supports for all substitute equipment and complete load calculations for adequacy of support prepared and signed by a registered structural engineer.

1. Itemized comparison of the proposed substitution with product specified; list significant variations.

2. Data relating to changes in construction schedule.

3. Any effect of substitution on separate contracts.

17 | P a g e

4. List of changes required in other work or products.

5. Accurate cost data comparing proposed substitution with product specified.

6. Proposed amount of change to the contract.

7. Designation of required license fees or royalties.

8. Designation of availability of maintenance services, sources of replacement materials.

C. Substitutions will NOT be considered for acceptance when:

1. They are merely indicated or implied on shop drawings or product data submittals without a formal request from Contractor.

2. They are requested directly by a subcontractor or supplier.

3. Acceptance will require substantial revision of contract documents.

4. Substitution has not been requested in accordance with this and related clauses.

D. Substitute products shall not be ordered or installed without written acceptance of the Contracting Officer.

E. Contracting Officer will determine acceptability of proposed substitutions.

F. Number of Substitution Submittals: Only one proposed alternative will be considered for each item. Provide specified item if substitution proposal is rejected.

Contractor’s Representation & Responsibility

A. In making formal request for substitution the Contractor represents he/she:

1. Have investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.

2. Will provide same warranties and bond for substitute as for originally specified product.

3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.

4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.

5. Cost data is complete and includes related costs under the contract, but not:

a. Costs under separate contracts.

b. Contracting Officer costs for redesign or revision of contract documents.

B. The Contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.

C. The Contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.

18 | P a g e

H.19 Traffic Control The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

The Contractor shall furnish, erect, maintain, and remove when notified any project identification signs shown on the drawings

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-13 Contractor Code of Business Ethics and Conduct (OCT 2015) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2016) 52.204-13 System for Award Management Maintenance (OCT 2016) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records – Negotiation (OCT 2010) 52.215-8 Order of Precedence – Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (NOV 2016)

19 | P a g e

52.219-14 Limitations on Subcontracting (JAN 2017) 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2014) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Equal Opportunity for Workers With Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (Mar 2015) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Establishing a Minimum Wage for Contractors (DEC 2015) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(SEP 2013)

52.223-3 Hazardous Material and Material Safety Data (JAN 1997) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-9 Estimate of percentage of Recovered Material Content for EPA-Designated Products (May 2008)

(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”

“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall—

(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of postconsumer material content; and

(2) Submit this estimate to _____________________ [Contracting Officer complete in accordance with agency procedures].

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

(MAY 2008)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-9 Buy American Act-Construction Materials (MAY 2014)