Install Glycol Condensing Loop

Closed Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
15B40119B00000004
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
238220 Plumbing, Heating, and Air-Conditioning Contractors
PSC
Not on record
Place of performance
71 Van Buren Street Chicago, Illinois 60605, United States

Notice details come from SAM.gov. Updated .

Notice text

THIS IS A SOURCES SOUGHT NOTICE. THIS NOTICE IS ISSUED FOR MARKET RESEARCH PURPOSES
ONLY. THIS IS NOT A SOLICITATION OR INVITATION FOR OFFERORS TO SUBMIT BIDS. A SYNOPIS OF PROPOSED CONTRACT ACTION MAY BE POSTED AT A LATER DATE WHICH WILL PROVIDE INSTRUCTIONS FOR BIDDERS TO RESPOND TO THIS OPPORTUNITY.
Please only respond to this sources sought notice if you are interested in submitting a bid and capable of
performing the work required to complete the project. The Federal Bureau of Prisons (BOP) anticipates the need for a firm-fixed-price contract for a project entitled Install Glycol Condensing Loop at the Metropolitan Correctional Center (MCC) Chicago, Illinois. MCC Chicago is a federal correctional facility located at 71 Van Buren Street, Chicago, Illinois 60605.

1. The following brief synopsis should not be considered inclusive of work required to complete the project. The project consists of repairing structural damage. The contractor will be required to provide all labor, materials, equipment, testing etc. necessary to: Furnish and provide installation of two (2) fully piped, valved, wired and controlled air-over evaporative coolers on roof of seven story Federal Parking Garage. Units to be operated in a tandem and piped as per the manufacturer's recommendation. The evaporative coolers will be Baltimore Aircoil Company (BAC), Model NXF-0603N-CS2TT-J6 Nexus Modular Hybrid Cooler with all available additional freeze protection equipment or brand name equivalent.
2. Install 3 phase power feed to Cooling Tower. From breezeway to roof of parking garage (140 feet field verify) Utilize available power in breezeway with transformer to match voltage requirement of new towers.
3. Install 2" type L Copper water make up feed line from laundry thru breezeway to 7th floor (roof of parking garage) to new cooling tower. (160 feet field verify).
4. Install 4" cast pipe over flow drain for cooling tower and connect to existing garage drain system located on 6th floor of parking garage (50 feet field verify)
5. Install Loop system (supply & return) from roof of parking garage down 7 stories (140 feet, field verify) to breezeway located at ground level. Where they will meet with the circulating pumps. Supply and Return Pipe will be mechanical rolled groove 5" steel schedule 40.
6. Furnish and install two (2) new Bell and Gosset Model: 1510-4EB base mounted circulating pumps with variable Frequency Drive and premium efficiency motors with shaft grounding rings, inertia pads, suction diffusers and check valves or brand name equivalent.
7. Installation of a full sized 5" rolitrol type centrifugal air/dirt separator or brand name equivalent.
8. Installation of a glycol feed unit with a 25gal resin storage tank and 1hp centrifugal feed pump. All required controls and power and needed for operation. Unit to be located within the laundry area and piped into the system.
9. Install electrical connections to pumps from existing power supply in breezeway 3-phase, 60hz, 480 volt (25 feet, field verify).
a. Variable frequency drives shall be enclosed in an outdoor enclosure, ventilated and heated as needed for year-round operation.
b. Variable frequency drives to be Bacnet MS/TP ready.
10. Furnish and provide installation of a fabricated pump enclosure to protect the motors and pump assemblies from weather. Housing must be ventilation as required for proper motor ventilation.
11. From the new circulating pumps the loop system will penetrate the bravo stair well and run up the stairwell to the 26th floor (260 feet, field verify) in mechanical rolled groove 4" steel pipe schedule 40. At the highest point on the 26th floor the supply and return pipe runs will interconnect with a circuit setter bypass.
12. Piping Loop (supply and return) will be installed in the Bravo stairwell and will run thru center of open stairwell. Fall protection fencing must be removed and re installed (modification to fencing is acceptable).
13. On the new 4'' Pipe run, each individual floor (1st thru 26th floor) will have a mechanical rolled groove 2" steel pipe schedule 40 takeoff on supply and return and a mechanical rolled groove 3'' steel pipe schedule 40 take off to feed all water cooled units in the basement.
14. New glycol towers to be provided with integral Bacnet MS/TP communication hardware, integral display and fully field configurable.
15. Connection into the existing facility temperature control network and integration into both glycol towers.
a. Configure to properly display the system operation.
b. Existing facility temperature control is based on Tridium Niagara N4 framework.
16. Furnish an engineered and fabricated control panel to operate the glycol circulation pumps.
17. Furnish and provide all I/O controllers required to control the glycol circulation pumps.
a. Controllers to be Johnson Controls Inc. FX-PCA3611 primary I/O controller. With FX-PCX4611 expansion module, or brand name equivalent.
b. A dual pressure transducer shall be installed near the end of the lower level fluid branch and tied into the controllers to maintain differential pressure set point.
c. Pumps to operate as a lead and lag operation, pumps shall rotate the lead position on a weekly basis and rotate in the event of a pump failure.
d. An in-line Onicon or brand name equivalent flow meter shall be installed and integrated into the temperature control system.
18. The Glycol Condensing Loop will be connected to 24 existing remote AC units throughout the high rise institution. The loop system will have 10 future connection points for adding additional units in the future.
19. Off new Glycol Loop tie into existing water cooled units
a. Unit 25 (2 Units) approximately 230 linear feet (field verify) of 1'' steel schedule 40 or type L pipe supply and return
b. Unit 8 (2 Units) approximately 230 linear feet (field verify) of 1'' steel schedule 40 or type L copper pipe supply and return.
c. Unit 7 (2 Units) approximately 230 linear feet (field verify) of 1'' steel schedule 40 or type L copper pipe supply and return
d. Unit 6 (1 Unit) approximately 140 linear feet (field verify) of 1'' steel schedule 40 or type L copper pipe supply and return
e. Unit 4 (2 Units) approximately 230 linear feet (field verify) of 1'' steel schedule 40 or type L copper pipe supply and return
Basement (5 Units) approximately 1450 linear feet (field verify) of 3' steel schedule 40 or type L copper pipe supply and return.


The performance period for the project will be 279 calendar days from issuance of the notice to proceed.


Pursuant to Federal Acquisition Regulation (FAR) 36.204, the estimated magnitude of the project lies between
$500,000 and $1,000,000. (NOTE: This range is one of 8 available ranges from FAR 36.204 and is not meant to imply that the project has necessarily been estimated/budgeted to the maximum of this selected range. It merely conveys that the estimate/budget lies somewhere within that range.)


The North American Industrial Classification System (NAICS) code applicable to this requirement is 238220 with a corresponding small business size standard of $15 million.


Interested parties must be registered in the System for Award Management (SAM) at www.sam.gov.


The BOP is seeking small business contractors for this project. Your business size metrics information entered in you SAM registration must be less than or equal to the small business size standard specified above . Interested small business contractors are requested to respond to this notice by adding their names to the Interested Vendors List for this posting in FedBizOpps.gov (must be logged-in to your account).


The synopsis of proposed contract action will include further instruction for responding to this opportunity.
Interested bidders are advised to continuously monitor FedBizOpps.gov for all future updates.

.

Notice history

Notice Type Posted
Install Glycol Condensing Loop Award Award Notice
Install Glycol Condensing Loop Latest solicitation Solicitation
This notice Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity