HI STP SR83(1)&(2) hoolapa stream bridge
Awarded Award Notice Posted
- Solicitation number
- DTFH6817R00013
- Agency
- Federal Highway Administration Department of Transportation
- Awarded
- to Kiewit Infrastructure West Co
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- 6982AF18C000042 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- North Shore, Kamehameha Highway (Hi Sr 83) Oahu, Hawaii, United States
Notice details come from SAM.gov. Updated .
Notice text
5 versions
Update #5 · Latest ·
Awarded Vendors: Kiewit Infrastructure West Co.. Contract Award Dollar Amount: $10,607,000.00. Contract Award Date: 2018-09-19.
Update #4 ·
THIS IS THE REQUEST FOR QUALIFICATIONS (RFQ) / SOLICITATION FOR
HI STP SR83 (1 and 2) Hoolapa (Nanahu) Stream Bridge and Kawela Stream Bridge.
THIS TWO-PHASE DESIGN-BUILD PROJECT IS BEING ADVERTISED ON AN UNRESTRICTED (FULL AND OPEN) BASIS.
PROJECT DETAILS: The Hoolapa (Nanahu) Kawela Stream Bridges project is located on the north shore of Oahu in Hawaii along the Kamehameha Hwy (HI SR 83). The project is approximately 4 miles northwest of the town of Laie.
Project Description:
This project is for design and construction of two structures at the Hoolapa (Nanahu) and Kawela Stream crossings.
Line Item Unit Preliminary Quantity
Removal of Bridge EACH 2
Roadway Excavation CUYD 100
Riprap CUYD 1,200
Aggregate Base TON 250
HACP TON 100
Bridge EACH 2
A two-phase design-build selection process is the solicitation approach. The work will take place in an environmentally sensitive area and will require context sensitive design and construction approaches. Environmental clearance and right-of-way acquisitions are expected to be complete prior to the award of a design-build contract. Additional permitting may be required, pending the design-build team approach.
Request for Proposals (short list firms only) is anticipated in December 2017. Award of the Design-Build Contract is anticipated in February of 2018. Estimated total cost is $5 to $10 million.
.
Update #3 ·
Added: Sep 01, 2017 5:56 pm Modified: Sep 26, 2017 2:48 pmTrack Changes
THIS IS THE REQUEST FOR QUALIFICATIONS (RFQ) / SOLICITATION FOR
HI STP SR83 (1 and 2) Hoolapa (Nanahu) Stream Bridge and Kawela Stream Bridge.
THIS TWO-PHASE DESIGN-BUILD PROJECT IS BEING ADVERTISED ON AN UNRESTRICTED (FULL AND OPEN) BASIS.
PROJECT DETAILS: The Hoolapa (Nanahu) Kawela Stream Bridges project is located on the north shore of Oahu in Hawaii along the Kamehameha Hwy (HI SR 83). The project is approximately 4 miles northwest of the town of Laie.
Project Description:
This project is for design and construction of two structures at the Hoolapa (Nanahu) and Kawela Stream crossings.
Line Item Unit Preliminary Quantity
Removal of Bridge EACH 2
Roadway Excavation CUYD 100
Riprap CUYD 1,200
Aggregate Base TON 250
HACP TON 100
Bridge EACH 2
A two-phase design-build selection process is the solicitation approach. The work will take place in an environmentally sensitive area and will require context sensitive design and construction approaches. Environmental clearance and right-of-way acquisitions are expected to be complete prior to the award of a design-build contract. Additional permitting may be required, pending the design-build team approach.
Request for Proposals (short list firms only) is anticipated in December 2017. Award of the Design-Build Contract is anticipated in February of 2018. Estimated total cost is $5 to $10 million.
Update #2 ·
(THIS PRE-SOLICITATION IS IN REFERENCE TO SOURCES SOUGHT POSTING FOR DTFH6817B00013, THE NUMBER HAS CHANGED TO DTFH6817R00013)
HI STP SR83 (1 and 2) Kawela Stream Bridge and Nanahu Stream Bridge
THIS IS NOT AN INVITATION FOR BID NOR REQUEST FOR PROPOSAL - PLANS AND SPECIFICATIONS ARE CURRENTLY NOT AVAILABLE. THIS TWO-PHASE DESIGN-BUILD PROJECT WILL BE ADVERTISED ON AN UNRESTRICTED (FULL AND OPEN) BASIS.
THE TENATIVE ADVERTISEMENT DATE IS MID SEPTEMBER.
PROJECT DETAILS: HI STP SR83 (1 and 2) Hoolapa (Nanahu) Stream Bridge and Kawela Stream Bridge
The Hoolapa (Nanahu) Kawela Stream Bridges project is located on the north shore of Oahu in Hawaii along the Kamehameha Hwy (HI SR 83). The project is approximately 4 miles northwest of the town of Laie.
Project Description:
This project is for design and construction of two structures at the Hoolapa (Nanahu) and Kawela Stream crossings.
Line Item Unit Preliminary Quantity
Removal of Bridge EACH 2
Roadway Excavation CUYD 100
Riprap CUYD 1,200
Aggregate Base TON 250
HACP TON 100
Bridge EACH 2
A two-phase design-build selection process is the expected solicitation approach. The work will take a place in an environmentally sensitive area and will require context sensitive design and construction approaches. Environmental clearance and right-of-way acquisitions are expected to be complete prior to the award of a design-build contract. Additional permitting may be required, pending the design-build team approach.
It is anticipated that a Request for Qualifications will be issued in June, 2017. Request for Proposals (short list firms only) is anticipated in the Fall of 2017. Award of the Design-Build Contract is anticipated in the Fall of 2017. Estimated total cost is $5 to $10 million.
.
Update #1 ·
Added: Sep 01, 2017 5:56 pm
(THIS PRE-SOLICITATION IS IN REFERENCE TO SOURCES SOUGHT POSTING FOR DTFH6817B00013, THE NUMBER HAS CHANGED TO DTFH6817R00013)
HI STP SR83 (1 and 2) Kawela Stream Bridge and Nanahu Stream Bridge
THIS IS NOT AN INVITATION FOR BID NOR REQUEST FOR PROPOSAL - PLANS AND SPECIFICATIONS ARE CURRENTLY NOT AVAILABLE. THIS TWO-PHASE DESIGN-BUILD PROJECT WILL BE ADVERTISED ON AN UNRESTRICTED (FULL AND OPEN) BASIS.
THE TENATIVE ADVERTISEMENT DATE IS MID SEPTEMBER.
PROJECT DETAILS: HI STP SR83 (1 and 2) Hoolapa (Nanahu) Stream Bridge and Kawela Stream Bridge
The Hoolapa (Nanahu) Kawela Stream Bridges project is located on the north shore of Oahu in Hawaii along the Kamehameha Hwy (HI SR 83). The project is approximately 4 miles northwest of the town of Laie.
Project Description:
This project is for design and construction of two structures at the Hoolapa (Nanahu) and Kawela Stream crossings.
Line Item Unit Preliminary Quantity
Removal of Bridge EACH 2
Roadway Excavation CUYD 100
Riprap CUYD 1,200
Aggregate Base TON 250
HACP TON 100
Bridge EACH 2
A two-phase design-build selection process is the expected solicitation approach. The work will take a place in an environmentally sensitive area and will require context sensitive design and construction approaches. Environmental clearance and right-of-way acquisitions are expected to be complete prior to the award of a design-build contract. Additional permitting may be required, pending the design-build team approach.
It is anticipated that a Request for Qualifications will be issued in June, 2017. Request for Proposals (short list firms only) is anticipated in the Fall of 2017. Award of the Design-Build Contract is anticipated in the Fall of 2017. Estimated total cost is $5 to $10 million.
Attachments
| File | Type | Posted |
|---|---|---|
| HI_STP_SR_83_(1)__(2)_DB_RFQ_FINAL.pdf |