Grte improve signal MTN wastewater syst.
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 140P1423R0010
- Agency
- Intermountain Region National Park Service, Department of the Interior
- Responses due
- Set-aside
- Woman-Owned Small Business
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Place of performance
- Signal Mountain Moose, Wyoming 83012, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks offers for construction services to improve the Signal Mountain wastewater system located in Grand Teton National Park, Wyoming. The National Park Service Intermountain Region is procuring rehabilitation and upgrades to the Signal Mountain Lagoon B98 Headworks Building, including replacing the force main, septage receiving structure, mechanical fine screen, surface aerators, outlet structure, and converting a building to an electrical/controls facility. Offerors must meet all requirements and qualifications specified. Evaluation will consider price, technical approach, and past performance. Questions are due by specified dates prior to the proposal submission deadline of May 25, 2023.
This procurement is set aside exclusively for certified Women-Owned Small Businesses. The NAICS code is 237110 - small business size standard of $39.5M. The estimated value is between $1,000,000 to $3,000,000 to be completed within 365 calendar days of the notice to proceed, with work to begin within 10 days at the place of performance in Moose, Wyoming. Offerors must be registered in the System for Award Management and have current online Representations and Certifications. The National Park Service Intermountain Region is the contracting agency.
Notice text
5 versions
Update #5 · Latest ·
Amendment 4 adds a final list of questions and answers and extends the due date. Please note that the NPS contract writing system will experience a blackout period starting 5/19. No additional amendments will be possible after that date.
Amendment 3 extends the due date. Please note that the NPS contract writing system will experience a blackout period starting 5/19. No additional amendments will be possible after that date.
Amendment 2 adds a list of questions and answers.
Amendment 1 adds a list of questions and answers and the site visit sign-in sheet.
GRTE Signal Mountain Water Wastewater System Rehab
PROJECT DESCRIPTION: Grand Teton National Park (GRTE), Signal Mountain Water Wastewater System Rehab and Construction of improvements to the Signal Mountain Lagoon B98 Headworks Building
SITE VISIT: Refer to 52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE 1 (FEB 1995) - RSVP to the contracting officer molly_lynam@nps.gov 24 hours in advance to receive the most up-to-date location and travel information.
SET-ASIDE TYPE: This procurement is being solicited as a total Women-Owned Small Business (WOSB) Program Set-Aside. REMINDER - Pursuant to FAR 52.219-30, offers are solicited only from certified WOSB concerns eligible under the WOSB Program or WOSB concerns with a pending application for certification status in the Dynamic Small Business Search (DSBS).
NAICS CODE: 237110 - small business size standard of $39.5M.
MAGNITUDE: In accordance with FAR 36.204, the project magnitude is estimated to be between $1,000,000 and $3,000,000.
DURATION: The contract performance period is start within 10 days of the NTP and complete within 365 days.
SYSTEM FOR AWARD MANAGEMENT (SAM): The successful offeror must be registered in SAM and have current online Representations and Certifications. Please access http://www.sam.gov to update your records prior to submitting final offer.
INSTRUCTIONS FOR SUBMITTING OFFER: Refer to Section L and M. The contractor agrees that they will follow the specifications provided. Offer shall be submitted via email. A detailed breakdown of the offeror's proposal price (e.g., labor, materials, profit, overhead, and other pricing elements) may be requested by the Contracting Officer during the evaluation and pre-award process to support a fair market value award. The contractor is encouraged to be proactive and prepare details for submission when preparing lump sum offer information.
QUESTIONS: Any questions regarding this solicitation shall be submitted in writing to Molly Lynam, Contract Specialist, at molly_lynam@nps.gov no later than seven (7) business days prior to the offer due date.
Update #4 ·
Amendment 3 extends the due date. Please note that the NPS contract writing system will experience a blackout period starting 5/19. No additional amendments will be possible after that date.
Amendment 2 adds a list of questions and answers.
Amendment 1 adds a list of questions and answers and the site visit sign-in sheet.
GRTE Signal Mountain Water Wastewater System Rehab
PROJECT DESCRIPTION: Grand Teton National Park (GRTE), Signal Mountain Water Wastewater System Rehab and Construction of improvements to the Signal Mountain Lagoon B98 Headworks Building
SITE VISIT: Refer to 52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE 1 (FEB 1995) - RSVP to the contracting officer molly_lynam@nps.gov 24 hours in advance to receive the most up-to-date location and travel information.
SET-ASIDE TYPE: This procurement is being solicited as a total Women-Owned Small Business (WOSB) Program Set-Aside. REMINDER - Pursuant to FAR 52.219-30, offers are solicited only from certified WOSB concerns eligible under the WOSB Program or WOSB concerns with a pending application for certification status in the Dynamic Small Business Search (DSBS).
NAICS CODE: 237110 - small business size standard of $39.5M.
MAGNITUDE: In accordance with FAR 36.204, the project magnitude is estimated to be between $1,000,000 and $3,000,000.
DURATION: The contract performance period is start within 10 days of the NTP and complete within 365 days.
SYSTEM FOR AWARD MANAGEMENT (SAM): The successful offeror must be registered in SAM and have current online Representations and Certifications. Please access http://www.sam.gov to update your records prior to submitting final offer.
INSTRUCTIONS FOR SUBMITTING OFFER: Refer to Section L and M. The contractor agrees that they will follow the specifications provided. Offer shall be submitted via email. A detailed breakdown of the offeror's proposal price (e.g., labor, materials, profit, overhead, and other pricing elements) may be requested by the Contracting Officer during the evaluation and pre-award process to support a fair market value award. The contractor is encouraged to be proactive and prepare details for submission when preparing lump sum offer information.
QUESTIONS: Any questions regarding this solicitation shall be submitted in writing to Molly Lynam, Contract Specialist, at molly_lynam@nps.gov no later than seven (7) business days prior to the offer due date.
Update #3 ·
Amendment 2 adds a list of questions and answers.
Amendment 1 adds a list of questions and answers and the site visit sign-in sheet.
GRTE Signal Mountain Water Wastewater System Rehab
PROJECT DESCRIPTION: Grand Teton National Park (GRTE), Signal Mountain Water Wastewater System Rehab and Construction of improvements to the Signal Mountain Lagoon B98 Headworks Building
SITE VISIT: Refer to 52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE 1 (FEB 1995) - RSVP to the contracting officer molly_lynam@nps.gov 24 hours in advance to receive the most up-to-date location and travel information.
SET-ASIDE TYPE: This procurement is being solicited as a total Women-Owned Small Business (WOSB) Program Set-Aside. REMINDER - Pursuant to FAR 52.219-30, offers are solicited only from certified WOSB concerns eligible under the WOSB Program or WOSB concerns with a pending application for certification status in the Dynamic Small Business Search (DSBS).
NAICS CODE: 237110 - small business size standard of $39.5M.
MAGNITUDE: In accordance with FAR 36.204, the project magnitude is estimated to be between $1,000,000 and $3,000,000.
DURATION: The contract performance period is start within 10 days of the NTP and complete within 365 days.
SYSTEM FOR AWARD MANAGEMENT (SAM): The successful offeror must be registered in SAM and have current online Representations and Certifications. Please access http://www.sam.gov to update your records prior to submitting final offer.
INSTRUCTIONS FOR SUBMITTING OFFER: Refer to Section L and M. The contractor agrees that they will follow the specifications provided. Offer shall be submitted via email. A detailed breakdown of the offeror's proposal price (e.g., labor, materials, profit, overhead, and other pricing elements) may be requested by the Contracting Officer during the evaluation and pre-award process to support a fair market value award. The contractor is encouraged to be proactive and prepare details for submission when preparing lump sum offer information.
QUESTIONS: Any questions regarding this solicitation shall be submitted in writing to Molly Lynam, Contract Specialist, at molly_lynam@nps.gov no later than seven (7) business days prior to the offer due date.
Update #2 ·
Amendment 1 adds a list of questions and answers and the site visit sign-in sheet.
GRTE Signal Mountain Water Wastewater System Rehab
PROJECT DESCRIPTION: Grand Teton National Park (GRTE), Signal Mountain Water Wastewater System Rehab and Construction of improvements to the Signal Mountain Lagoon B98 Headworks Building
SITE VISIT: Refer to 52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE 1 (FEB 1995) - RSVP to the contracting officer molly_lynam@nps.gov 24 hours in advance to receive the most up-to-date location and travel information.
SET-ASIDE TYPE: This procurement is being solicited as a total Women-Owned Small Business (WOSB) Program Set-Aside. REMINDER - Pursuant to FAR 52.219-30, offers are solicited only from certified WOSB concerns eligible under the WOSB Program or WOSB concerns with a pending application for certification status in the Dynamic Small Business Search (DSBS).
NAICS CODE: 237110 - small business size standard of $39.5M.
MAGNITUDE: In accordance with FAR 36.204, the project magnitude is estimated to be between $1,000,000 and $3,000,000.
DURATION: The contract performance period is start within 10 days of the NTP and complete within 365 days.
SYSTEM FOR AWARD MANAGEMENT (SAM): The successful offeror must be registered in SAM and have current online Representations and Certifications. Please access http://www.sam.gov to update your records prior to submitting final offer.
INSTRUCTIONS FOR SUBMITTING OFFER: Refer to Section L and M. The contractor agrees that they will follow the specifications provided. Offer shall be submitted via email. A detailed breakdown of the offeror's proposal price (e.g., labor, materials, profit, overhead, and other pricing elements) may be requested by the Contracting Officer during the evaluation and pre-award process to support a fair market value award. The contractor is encouraged to be proactive and prepare details for submission when preparing lump sum offer information.
QUESTIONS: Any questions regarding this solicitation shall be submitted in writing to Molly Lynam, Contract Specialist, at molly_lynam@nps.gov no later than seven (7) business days prior to the offer due date.
Update #1 ·
GRTE Signal Mountain Water Wastewater System Rehab
PROJECT DESCRIPTION: Grand Teton National Park (GRTE), Signal Mountain Water Wastewater System Rehab and Construction of improvements to the Signal Mountain Lagoon B98 Headworks Building
SITE VISIT: Refer to 52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE 1 (FEB 1995) - RSVP to the contracting officer molly_lynam@nps.gov 24 hours in advance to receive the most up-to-date location and travel information.
SET-ASIDE TYPE: This procurement is being solicited as a total Women-Owned Small Business (WOSB) Program Set-Aside. REMINDER - Pursuant to FAR 52.219-30, offers are solicited only from certified WOSB concerns eligible under the WOSB Program or WOSB concerns with a pending application for certification status in the Dynamic Small Business Search (DSBS).
NAICS CODE: 237110 - small business size standard of $39.5M.
MAGNITUDE: In accordance with FAR 36.204, the project magnitude is estimated to be between $1,000,000 and $3,000,000.
DURATION: The contract performance period is start within 10 days of the NTP and complete within 365 days.
SYSTEM FOR AWARD MANAGEMENT (SAM): The successful offeror must be registered in SAM and have current online Representations and Certifications. Please access http://www.sam.gov to update your records prior to submitting final offer.
INSTRUCTIONS FOR SUBMITTING OFFER: Refer to Section L and M. The contractor agrees that they will follow the specifications provided. Offer shall be submitted via email. A detailed breakdown of the offeror's proposal price (e.g., labor, materials, profit, overhead, and other pricing elements) may be requested by the Contracting Officer during the evaluation and pre-award process to support a fair market value award. The contractor is encouraged to be proactive and prepare details for submission when preparing lump sum offer information.
QUESTIONS: Any questions regarding this solicitation shall be submitted in writing to Molly Lynam, Contract Specialist, at molly_lynam@nps.gov no later than seven (7) business days prior to the offer due date.
Attachments
| File | Type | Posted |
|---|---|---|
| Amendment_4_Questions_and_Answers_0004.pdf | ||
| Sol_140P1423R0010_Amd_0004.pdf | ||
| Sol_140P1423R0010_Amd_0003.pdf | ||
| Sol_140P1423R0010_Amd_0002.pdf | ||
| Amendment_2_Questions_and_Answers_0002.pdf | ||
| Sol_140P1423R0010_Amd_0001.pdf | ||
| Amendment_1_Questions_and_Answers_0001.docx | DOCX document | |
| Site_Visit_Sign_In_0001.jpeg | JPEG file | |
| A06_40610683_GRTE_174170_-_Signal_Mtn_WWTP_-_Final_Drawings_-_01_09_23.pdf | ||
| B03_40610683_Teton_County_Heavy_WY20230003_rev_01062023.pdf | ||
| Construction_Contract_Administration.docx | DOCX document | |
| Sol_140P1423R0010.pdf | ||
| B08_40610683_Attachment_6_General_References.pdf | ||
| B08_40610683_Attachment_8_Past_Performance_Questionnaire.docx | DOCX document | |
| B08_40610683_Attachment_7_Limitation_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| A06_40610683_GRTE_174170_-_Signal_Mtn_WWTP_-_Final_Specs_-_01_09_23.pdf | ||
| B08_40610683_Attachment_5_Project_Experience_Form.docx | DOCX document |
Show all 17
Notice history
| Notice | Type | Posted |
|---|---|---|
| GRTE Signal Mountain Water Wastewater System Rehab | Award Notice | |
| Grte improve signal MTN wastewater syst. | Solicitation | |
| GRTE Signal Mountain Water Wastewater System Rehab | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity