Fiber Optic Repair

Award Notice Posted

Solicitation number
W912GY16T0014
Agency
Awarded
to AMG Fiber Optic Technologies Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W912GY16P0016 Federal contract award
NAICS code
238210 Electrical Contractors and Other Wiring Installation Contractors
PSC
Not on record
Place of performance
Sierra Army Depot Herlong, California 96113, United States

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

-Contractor to test, repair, verify and determine good or damaged fiber optics cables.
-Contractor will install ST connectors on main 24 strand fiber feed between two buildings for a total of 48
terminations.
-Contractor will install a splice in a manhole that feeds 8outlying buildings which have 6 strand to each building for a total of 48 splices in the manhole. The other end of the cable will be terminated with ST connectors for a total of 48 terminations.
-Contractor will bore underneath a road and install two 4 inch conduit approximately 90 feet long under the road. The conduits will be no less than 36 inch, and no more than 48 inch deep. Contractor will install approximately 300 feet of 24 strand single mode fiber. One end to be spliced to existing fiber and the other end to be terminated with ST connectors for a total of 24 splices and 24 terminations. Government will supply the fiber optic cable.
-All fiber connections will have no more than .05 db loss per connection.
-Contractor will provide all ST connectors and splice cases.
-Contractor will splice 200 pair copper cable in two different places for a total of 400 splices..

Update #1 ·

-Contractor to test, repair, verify and determine good or damaged fiber optics cables.
-Contractor will install ST connectors on main 24 strand fiber feed between two buildings for a total of 48
terminations.
-Contractor will install a splice in a manhole that feeds 8outlying buildings which have 6 strand to each building for a total of 48 splices in the manhole. The other end of the cable will be terminated with ST connectors for a total of 48 terminations.
-Contractor will bore underneath a road and install two 4 inch conduit approximately 90 feet long under the road. The conduits will be no less than 36 inch, and no more than 48 inch deep. Contractor will install approximately 300 feet of 24 strand single mode fiber. One end to be spliced to existing fiber and the other end to be terminated with ST connectors for a total of 24 splices and 24 terminations. Government will supply the fiber optic cable.
-All fiber connections will have no more than .05 db loss per connection.
-Contractor will provide all ST connectors and splice cases.
-Contractor will splice 200 pair copper cable in two different places for a total of 400 splices.

Files

File Type Posted
W912GY-16-T-0014.pdf PDF

On GovTribe