CA FTNP SEKI 10(12 Generals Highway

Awarded Award Notice Posted

Solicitation number
6982AF18B000033
Agency
Federal Highway Administration Department of Transportation
Awarded
to Steve Manning Construction Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
6982AF19C000016 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Sequoia and Kings Canyon National Park and the Sequoia National Forest, California 96362, United States

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

Awarded Vendors: Steve Manning Construction, Inc.. Contract Award Dollar Amount: $23,796,966.40. Contract Award Date: 2019-04-19.

Update #3 ·

This project consists of roadway resurfacing, restoration, and rehabilitation of approximately 18.2 miles of roadway within Sequoia and Kings Canyon National Park and the Sequoia National Forest, Tulare County, California, including the Generals Highway from 1 mile east of the State Route 180 intersection to the Little Baldy Saddle. Work also includes rehabilitation/reconstruction of multiple parking areas, and drainage improvements, including culvert cleaning, lining and replacement. The terrain is mountainous with the elevation for the work ranging between 6,400 and 7,600 feet.


Construction is anticipated from April 2019 to October 2020.


Principle work items include:


46,000 tons of asphalt concrete pavement, gyratory mix,


74,000 linear feet of concrete curb,


17,000 tons of aggregate base,


18.2 miles of full depth reclamation,


17,000 square yards of asphalt paved ditch,


40 each stone masonry headwalls,


900 cubic yards of riprap,


800 linear feet of lining pipe culverts, and


1,200 linear feet of metal pipe culverts.


All of the work is occurring in natural resource sensitive areas. Construction phasing, temporary traffic control, and timely completion of construction will be crucial to minimize disruptions to park visitors throughout construction and achieve customer satisfaction.
Estimated dollar amount including Options is between $15,000,000 and $25,000,000.

.

Update #2 ·

This project consists of roadway resurfacing, restoration, and rehabilitation of approximately 18.2 miles of roadway within Sequoia and Kings Canyon National Park and the Sequoia National Forest, Tulare County, California, including the Generals Highway from 1 mile east of the State Route 180 intersection to the Little Baldy Saddle. Work also includes rehabilitation/reconstruction of multiple parking areas, and drainage improvements, including culvert cleaning, lining and replacement. The terrain is mountainous with the elevation for the work ranging between 6,400 and 7,600 feet.


The anticipated advertisement date is February 2019 with construction anticipated from April 2019 to October 2020.


Principle work items include:


46,000 tons of asphalt concrete pavement, gyratory mix,


74,000 linear feet of concrete curb,


17,000 tons of aggregate base,


18.2 miles of full depth reclamation,


17,000 square yards of asphalt paved ditch,


40 each stone masonry headwalls,


900 cubic yards of riprap,


800 linear feet of lining pipe culverts, and


1,200 linear feet of metal pipe culverts.


All of the work is occurring in natural resource sensitive areas. Construction phasing, temporary traffic control, and timely completion of construction will be crucial to minimize disruptions to park visitors throughout construction and achieve customer satisfaction.
Estimated dollar amount including Options is between $15,000,000 and $25,000,000.

.

Update #1 ·

THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE

This project consists of roadway resurfacing, restoration, and rehabilitation of approximately 18.2 miles of roadway within Sequoia and Kings Canyon National Park and the Sequoia National Forest, Tulare County, California, including the Generals Highway from 1 mile east of the State Route 180 intersection to the Little Baldy Saddle. Work also includes rehabilitation/reconstruction of multiple parking areas, and drainage improvements, including culvert cleaning, lining and replacement. The terrain is mountainous with the elevation for the work ranging between 6,400 and 7,600 feet.


The anticipated advertisement date is February 2019 with construction anticipated from April 2019 to October 2020.


Principle work items include:


46,000 tons of asphalt concrete pavement, gyratory mix,


74,000 linear feet of concrete curb,


17,000 tons of aggregate base,


18.2 miles of full depth reclamation,


17,000 square yards of asphalt paved ditch,


40 each stone masonry headwalls,


900 cubic yards of riprap,


800 linear feet of lining pipe culverts, and


1,200 linear feet of metal pipe culverts.


All of the work is occurring in natural resource sensitive areas. Construction phasing, temporary traffic control, and timely completion of construction will be crucial to minimize disruptions to park visitors throughout construction and achieve customer satisfaction.
Estimated dollar amount including Options is between $15,000,000 and $25,000,000.

.

Attachments

Files attached to this notice, newest first
File Type Posted
Bid_Tabulation.pdf PDF
Bid_Opening_CA_FTNP_SEKI_10(12).pdf PDF
A002.pdf PDF
QnA_3.7.19__(002).pdf PDF
SF30.pdf PDF
SEKI10(12)_Cross_Sections_Final.pdf PDF
QnA_3.1.19_.docx DOCX document
CA_FTNP_SEKI_10(12)_Generals_Highway_Pavements_Report_2017_-_Signed.pdf PDF
IFB-6982AF18B000033.pdf PDF
Restroom_&_Paint_JOFOC.pdf PDF
FP-14.pdf PDF
Plan_Sheets.pdf PDF
Show all 12

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity