CA FTBR FSTR(2), Folsom South Trail Improvements Ph 2
Closed Pre-Solicitation Posted
This opportunity was awarded. See its 2 award notices in the notice history.
- Solicitation number
- 6982AF20B000012
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Sacramento Ca Usa
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is for construction services for the Folsom South Trail Improvements Phase 2 project located in Sacramento County, California. The Federal Highway Administration will procure construction to complete a pedestrian bridge over Laguna Creek, an open-air shelter house, asphalt patching, micro surfacing, signing, and other miscellaneous work items. Evaluation will consider both technical qualifications and price, with award expected in early June 2020. The anticipated advertisement date is late April 2020, with a bid opening in late May 2020.
The project involves no set-aside designation. Key quantities include 3,550 square yards of micro surfacing, 200 square yards of asphalt patching, and 43 cubic yards of structural concrete. The engineer's estimate is between $1-2 million for the base scope. Optional line items provide for additional micro surfacing, crack sealing, and pavement marking quantities. Construction must be completed between July and September 2020.
Notice text
THIS IS NOT AN INVITATION FOR BID, PLANS AND SPECIFICATIONS ARE CURRENTLY NOT AVAILABLE.
PROJECT NUMBER: CA FTBR FSTR (2)
PROJECT NAME: Folsom Trail Improvements PH II
PROJECT DESCRIPTION:
The Folsom South Trail Improvements project is located in Sacramento County, CA, on Bureau of Reclamation (BOR) property, adjacent to the Folsom South Canal. The trail, initially constructed for use by BOR maintenance vehicles, has been open to the public due to urban development and increasing popularity amongst bicyclists and pedestrians.
The project consists of construction of a pedestrian bridge over Laguna Creek, an open-air shelter house, crack sealing, asphalt patching, micro surfacing, signing, pavement markings, and other miscellaneous items as requested by the BOR.
The BOR will allow full trail closures in work areas as needed. There will be no delays nor closures on public roadways.
SIGNIFICANT QUANTITIES:
Schedule A:
Line Item Unit Estimated Quantity
40901-2000 Micro Surfacing, Type 2 3,550 SQYD
41801-2000 Asphalt Concrete Pavement Patch, Type 2 200 SQYD
55201-0600 Structural Concrete, Class C (AE) 43 CUYD
55504-0000 Pre-Fabricated Steel Bridge ALL LPSM
63301-0000 Sign System 96 EACH
Option X:
Line Item Unit Estimated Quantity
40901-2000 Micro Surfacing, Type 2 72,600 SQYD
41402-2000 Cracks, Cleaning and Sealing 7.3 MILE
63402-0300 Pavement Markings, Type B, Solid 28 MILE
63402-0400 Pavement Markings, Type B, Broken 11 MILE
Option Y:
Line Item Unit Estimated Quantity
40901-2000 Micro Surfacing, Type 2 30,850 SQYD
41402-2000 Cracks, Cleaning and Sealing 4.4 MILE
63402-0300 Pavement Markings, Type B, Solid 12 MILE
63402-0400 Pavement Markings, Type B, Broken 5 MILE
ENGINEER’S ESTIMATE:
Estimated total cost is $1 million to $2 million.
CONSTRUCTION DURATION: Construction is anticipated between July 2020 and September 2020.
ADDITIONAL INFORMATION FOR NOTICE
Anticipated advertisement in late April 2020.
Anticipated bid opening in late May 2020.
Anticipated Award in early June 2020.
Notice history
| Notice | Type | Posted |
|---|---|---|
| AZ FTFS 104(1), Mingus Mountain | Award Notice | |
| CA FTBR FSTR(2), Folsom South Trail Improvements Ph 2 | Award Notice | |
| AZ FTFS 104(1), Mingus Mountain | Solicitation | |
| AZ FTFS 104(1), Mingus Mountain | Pre-Solicitation | |
| CA FTBR FSTR(2), Folsom South Trail Improvements Ph 2 | Solicitation | |
| This notice | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity