- to Oddo Construction Services, LLC
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W911PT17P0235 Federal contract award
- NAICS code
- 238290 Other Building Equipment Contractors
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
CLIN 0001- REMOVE APPROXIMATELY 135 FEET OF THREE CONDUCTOR BUSS BAR, BRIDGE COLLECTOR SHOES AND ALL MOUNTING HARDWARE. INSTALL APPROXIMATELY 135 FEET OF FOUR CONDUCTOR BUSS BAR (3 POWER AND 1 GROUND) AND ALL NEW MOUNTING HARDWARE. MODIFY CRANES (B009 AND B030) COLLECTOR POSTS TO EXCEPT THE 4TH COLLECTOR SHOE. REPLACE ALL COLLECTOR SHOES AND TEST BOTH CRANES FOR PROPER OPERATION.
CLIN 0002 REMOVE WIRE ROPE AND LOWER HOIST BLOCK, DISCONNECT CROSS TROLLEY CONDUCTORS TO CABLE REEL. REMOVED CABLE REEL. DISCONNECT AND REMOVED CROSS TROLLEY COLLECTORS. PROVIDE RIGGING, RENTAL CRANE AND OPERATOR, RIG TROLLEY AND LOWER TO FLOOR.
CLIN 0003 REMOVED APPROXIMATELY 1,460 LINEAR FEET OF RAIL. FURNISH AND INSTALL APPROXIMATELY 1,460 LINEAR FEET OF NEW PRIME CRANE RAIL WITH JOINT BARS, RAIL PAD AND MOUNTING HARDWARE AS REQUIRED. REMOVE USED RAIL FROM SITE. TEST CRANES AFTER INSTALLATION TO ENSURE PROPER OPERATION. THIS WORK CAN ONLY BE ACCOMPLISHED DURING WATERVLIET SHUTDOWN PERIOD 24 -28 JUL 2017. PRICE SHOULD INCLUDE RAILMOUNTING HARDWARE, FREIGHT, RENTAL EQUIPMENT AND ON SITE INSTALLATION.
. Awarded Vendors: ODDO CONSTRUCTION SERVICES LLC. Contract Award Dollar Amount: $148,879.00. Contract Award Date: 2017-07-06.
Update #1 ·
CLIN 0001- REMOVE APPROXIMATELY 135 FEET OF THREE CONDUCTOR BUSS BAR, BRIDGE COLLECTOR SHOES AND ALL MOUNTING HARDWARE. INSTALL APPROXIMATELY 135 FEET OF FOUR CONDUCTOR BUSS BAR (3 POWER AND 1 GROUND) AND ALL NEW MOUNTING HARDWARE. MODIFY CRANES (B009 AND B030) COLLECTOR POSTS TO EXCEPT THE 4TH COLLECTOR SHOE. REPLACE ALL COLLECTOR SHOES AND TEST BOTH CRANES FOR PROPER OPERATION.
CLIN 0002 REMOVE WIRE ROPE AND LOWER HOIST BLOCK, DISCONNECT CROSS TROLLEY CONDUCTORS TO CABLE REEL. REMOVED CABLE REEL. DISCONNECT AND REMOVED CROSS TROLLEY COLLECTORS. PROVIDE RIGGING, RENTAL CRANE AND OPERATOR, RIG TROLLEY AND LOWER TO FLOOR.
CLIN 0003 REMOVED APPROXIMATELY 1,460 LINEAR FEET OF RAIL. FURNISH AND INSTALL APPROXIMATELY 1,460 LINEAR FEET OF NEW PRIME CRANE RAIL WITH JOINT BARS, RAIL PAD AND MOUNTING HARDWARE AS REQUIRED. REMOVE USED RAIL FROM SITE. TEST CRANES AFTER INSTALLATION TO ENSURE PROPER OPERATION. THIS WORK CAN ONLY BE ACCOMPLISHED DURING WATERVLIET SHUTDOWN PERIOD 24 -28 JUL 2017. PRICE SHOULD INCLUDE RAILMOUNTING HARDWARE, FREIGHT, RENTAL EQUIPMENT AND ON SITE INSTALLATION.
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity