Astoria Housing Phase 2, Astoria, OR
Award Notice Posted
- Solicitation number
- HSCG50-16-R-PFDAH1
- Agency
-
Coast Guard
Department of Homeland Security
- Awarded
- to Integrity Structures, LLC
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- HSCG5017CPAH002 Federal contract award
- NAICS code
- 236210 Industrial Building Construction
- PSC
- Not on record
- Place of performance
- 200 W. Klaskanine Astoria, Oregon 97103, United States
Notice details come from SAM.gov. Updated .
Notice text
4 versions
Update #4 · Latest ·
UPDATED MAY 27, 2016***The Solicitation (Includes Specifications and Drawings) is now anticipated to be released in June 2016 timeframe.***
Update #3 ·
UPDATE***The Solicitation (Includes Specifications and Drawings) is now anticipated to be released in the April 2016 to May 2016 timeframe.***
Update #2 ·
***The Solicitation (Includes Specifications and Drawings) is now anticipated to be released on or before March 31, 2016.***
This project previously identified as "Design-Bid-Build" is changed to "Design-Build".
Update #1 ·
USCG Facilities Design & Construction Center issues this Pre-Solicitation Notice of a Solicitation (Design-Bid-Build) that is anticipated to be released between December 2015 and January 2016, to design and construct the new housing maintenance building including all supporting utilities, paved road access, sidewalks and landscaping, at USCG Sector Columbia River, Astoria, Oregon 97103. The Solicitation is anticipated to include Four Option Items, which include the design and construction of new housing units including all supporting utilities; design and construct the paved road, sidewalks and all utilities to the cul-de-sac at the end of the road, grade all building pads and hill sides for future installations of units, provide conduit paths for electrical and cable, relocation of existing 10" HDPE water line installed during in existing Phase 1 to the new roadway location and elevations, and design and construct a site storm water system capable of meeting the storm water demands for the site through the construction of option item units. Solicitation packages (INCLUDES SPECIFICATIONS AND DRAWINGS) is anticipated to be released between December 2015 and January 2016, at which time it will be posted on FEDBIZ OPPS. The estimated price for this project is between $6M - $12M. This is anticipated to be a Total Small Business Set-Aside.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Astoria family housing phase 2, astoria, or | Award Notice | |
| This notice | Award Notice |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity