Aggregate supply and Delivery Shasta-Trinity National Forest
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 127EAY21Q0079
- Agency
-
Forest Service
Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 212319 Other Crushed and Broken Stone Mining and Quarrying
- PSC
- 5610 Mineral Construction Materials, Bulk
- Place of performance
- McCloud, California 96057, United States
Notice details come from SAM.gov. Updated .
Notice text
5 versions
Update #5 · Latest ·
8/20/2021
Amendment 0001
This amendment extends response due to August 25, 2021 at 1300 PT.
This amendment provides clarification to delivery end result for spreading and stockpiling at the two locations. Spreading will be required for Esperanza site and stockpiling at Eddy Creek site.
STATEMENT OF WORK
Shasta-Trinity National Forest
Project Scope
Esperanza Site Location
2100 tons of Class II Aggregate are to be delivered on Esperanza Road at the site location. The vendor will
tailgate spread the rock. The Forest Service and/or partners will be grading and produce the end result needed for
the Esperanza Road. Optional 5000 tons to be delivered in increments of no less than 1000 tons.
Eddy Creek Road Site Location
Optional 1000 tons of Class II Aggregate to be delivered at the site location. For the Eddy Creek Road location,
the stockpile location will be located at the intersection of Forest Road 41N26 (Eddy Creek Road) and N. Old
Stage Road (County Road) as shown on the map.
Update #4 ·
8/20/2021
Amendment 0001
This amendment extends response due to August 25, 2021 at 1300 PT.
This amendment provides clarification to delivery end result for spreading and stockpiling at the two locations. Spreading will be required for Esperanza site and stockpiling at Eddy Creek site.
STATEMENT OF WORK
Shasta-Trinity National Forest
Project Scope
Esperanza Site Location
2100 tons of Class II Aggregate are to be delivered on Esperanza Road at the site location. The vendor will
tailgate spread the rock. The Forest Service and/or partners will be grading and produce the end result needed for
the Esperanza Road. Optional 5000 tons to be delivered in increments of no less than 1000 tons.
Eddy Creek Road Site Location
Optional 1000 tons of Class II Aggregate to be delivered at the site location. For the Eddy Creek Road location,
the stockpile location will be located at the intersection of Forest Roaad 41N26 (Eddy Creek Road) and N. Old
Stage Road (County Road) as shown on the map.
Update #3 ·
8/20/2021
Amendment 0001
This amendment extends response due to August 26, 2021 at 1300 PT.
This amendment provides clarification to delivery end result for spreading and stockpiling at the two locations. Spreading will be required for Esperanza site and stockpiling at Eddy Creek site.
STATEMENT OF WORK
Shasta-Trinity National Forest
Project Scope
Esperanza Site Location
2100 tons of Class II Aggregate are to be delivered on Esperanza Road at the site location. The vendor will
tailgate spread the rock. The Forest Service and/or partners will be grading and produce the end result needed for
the Esperanza Road. Optional 5000 tons to be delivered in increments of no less than 1000 tons.
Eddy Creek Road Site Location
Optional 1000 tons of Class II Aggregate to be delivered at the site location. For the Eddy Creek Road location,
the stockpile location will be located at the intersection of Forest Roaad 41N26 (Eddy Creek Road) and N. Old
Stage Road (County Road) as shown on the map.
Update #2 ·
8/19/21
Q&A
Q1: Does the material need to be tailgate spread? Or is it a stockpile?
A1: The aggregate would be tailgate spread along the road.
STATEMENT OF WORK
Shasta-Trinity National Forest
Project Scope
Esperanza Site Location
2100 tons of Class II Aggregate are to be delivered on Esperanza Road at the site location.
Optional 5000 tons to be delivered in increments of no less than 1000 tons.
Eddy Creek Road Site Location
Optional 1000 tons of Class II Aggregate to be delivered at the site location.
Update #1 ·
STATEMENT OF WORK
Shasta-Trinity National Forest
Project Scope
Esperanza Site Location
2100 tons of Class II Aggregate are to be delivered on Esperanza Road at the site location.
Optional 5000 tons to be delivered in increments of no less than 1000 tons.
Eddy Creek Road Site Location
Optional 1000 tons of Class II Aggregate to be delivered at the site location.
Files
| File | Type | Posted |
|---|---|---|
| 127EAY21Q0079.pdf | ||
| 127EAY21Q0079 SF30.pdf | ||
| QnA Version 1 81921.docx | DOCX document | |
| 127EAY21Q0079.pdf | ||
| Eddy Creek Site Location.pdf | ||
| Esperanza Site Location.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Aggregate supply and Delivery Shasta-Trinity National Forest | Award Notice | |
| This notice | Solicitation | |
| Aggregate supply and Delivery | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity