FA461018R0013
XUMU 11-1240B; Replace HVAC, Bldg. 7011
Proposal Requests for Information (RFIs)
1- In Computer Room Air Conditioning (CRAC), we are used to seeing computer cables on the ground with elevated floor (crawl space is used as ducting for the air conditioning), few cables run above ground and the ceiling is very low (to minimize the energy loss). Since the cables in the computer room at Building 7011 are located above ground on a steel paneled grid hanging from a tall ceiling (making it very energy inefficient and requires a lot to cool the computers) and also there are literally millions of cables there, please provide:
A clear access plan/drawing/details to the HVAC ducting above the cables for removal and reinstallation.
HVAC contractor may not be qualified to move the cables to access the ducting. From the site walk, we gather, understandably, manager for the facility is extremely meticulous and requires copious response to manger’s specifications on the project. Given this, it is even more important, a thorough plan be provided for the removal and reinstallation of the ducting in the computer room.
Response: The contractor is required to develop the access plan. Previous contracts which required access above the grid used a scaffolding company to develop a scaffolding plan for access. The plan will need to be coordinated and reviewed by the Government to ensure it does not impede the mission. Depending on the location and time frame of scaffolding installation, access to certain sections of the grid will not be authorized until mission restrictions are lifted.
2- What are different elevations in the computer room, i.e., cable ceiling grid elevation (x-feet above ground elevation) and the building ceiling elevation (clear and roof elevation)? Please provide a profile of the room.
Response: The contractor that is awarded the contract is responsible to investigate and confirm all the measurements on the field during the design phase, the design drawings provided are for reference.
3- Specifications state that, this is a Design-Build project, however, a design is provided for most of the project, except, contractor is required to verify whether the current design is per the latest codes and requires updating the design, if there are any changes? This is very confusing and put an undue responsibility on the contractor. For a Design-Build project, specifications clearly provide details as to what is to be included in the incremental design and anticipated deliverable design documents, i.e., what is to be delivered at 35%, 65%, 95%, and as 100% or an alternate percentages. Please provide:
a. A clear specification as to exactly what requires to be designed in this project?
b. What we require to update?
c. Provide a list of submittals required for the project as a design-build project.
Response: a) The Statement of Work identifies the revisions to the concept design which the Contractor will be required to complete. b) The Contractor will be required to update the design as identified in the Statement of Work and ensure that the design complies with all codes and regulations to include UFC and UFGS requirements. c) The Statement of Work identifies the required design and project management submittals. All material submittals will be required to be identified by the Contractor as part of the design.
4- Item # 2 of Statement of Work (SOW) requires demolition of a 500KVA transformer and installation of a 750KVA. Drawing E-101, Note 7 requires removal and relocation of 45KVA transformer. Note 9 sheet E-201 indicates relocate 45KVA transformer. Please clarify exactly what is required regarding transformers related work?
Response: The contractor awarded the contract is required to remove the existing 500KVA transformer and furnish a new 750 KVA transformer. There is also a 45 kVA transformer that needs to be replaced and relocated. The existing location of the 45 kVA transformer is on E-101, note 7, and the proposed new location of the new 45 kVA transformer is shown on page E 201, note 9.
5- Drawing M-201 indicates Alternate Bid. However, there is no description of an Alternate Bid scope in the SOW or a CLIN is provided for the alternate bid. Please clarify.
Response: Disregard alternate bid comments, the contractor will submit the updated design without this comments.
6- Structural drawing S-2, Detail 5 refers to wall infill. Please indicate where does this detail apply? No architectural elevation drawings are provided. Please provide them both for inside and outside of the work area. Please provide clear demolition and new installation Architectural drawings.
Response: The contractor that is awarded the contract is responsible to investigate and confirm all the measurements on the field during the design phase, the design drawings provided are for reference.
7- Provide as many photos as you can for the systems that requires to be removed and for reinstallation of new systems, and also photos that depicts a better understanding of the access limitations for equipment removal/reinstallation in the Computer Room.
Response: Due to the security of the building, photos will not be posted on FBO.gov. Photos are available upon written (email) request to the Contracting Officer and new contract specialist, Meghann Applebay, meghann.applebay@us.af.mil. Due to delays in responding to questions, any previous requests submitted for photos will need to be resubmitted.
8- When will the next door project complete? Also, given all the improvements/fence located next to the outside facilities installation, clearly provide contractor staging area, access and working area for the crane and trucks that will bring large equipment.
Response: The project in the adjacent building is expected to be ongoing when this project is awarded, however, its perimeter fence line may be able to be adjusted to accommodate work and staging restrictions for this project. All the staging areas will be identified during the 2.3.2 Site Survey / Charrette and will need to be approved during the AF Form 103 processing.
9- Does any of the work requires HAZMAT (lead based paint, mold or asbestos) handling or abatement in order to complete the project scope?
Response: During the 65% design the contractor needs to submit:
c. Environmental Surveys: The Contractor shall provide the environmental surveys and include abatement specifications if asbestos, lead-based paint, PCBs, or underground storage tanks (USTs) are affected by work pertaining to any project.
mailto:meghann.applebay@us.af.mil
10- What are the working hours and can we work 10-hour, 4 days per week work week?
Response: No
11- How will the escorting of our workers happen? Are we forced to work only either inside or outside of the building at a given time?
Response: Escorts are authorized to escort up to 10 personnel each and required to maintain a line of sight with all escorted personnel. As a result of the line of sight requirement, workers will be required to stay within view of an escort. As an example, if an escort is overseeing 10 personnel and one of the personnel needs to get an item from their truck or use the restroom the escort will be required to take all individuals to the truck or restroom.
12- How many escorts will be on-site during the work?
Response: The Government anticipates providing two escorts for each work day on site. If the Contractor does not believe this to be sufficient based upon their work plan, they need to specifically identify in their proposal the quantity of escorts and number of days they feel are required.
13- How much time do we need to allocate for each worker to clear the security requirements at
Building 7011, prior to start working each day?
Response: The government anticipates the group of workers will take 10-15minutes to clear security. All personnel associated with this project will have to be sponsored via the Visitor Center to gain access to the base; prior to entering they will need to be vetted by the Visitor Center. The project will also have to have some cleared personnel who has the authority to escort vendors into the work area. Will allot of the work occur within the buildings perimeter; if so, we may need to designate a clear zone for equipment and personnel to work. The timing it will all be dependent if workers follow security protocol.
14- What are the other restrictions based on the escort requirement? i.e., if a worker goes to restroom, and the escort is with that person, do rest of the workers stop working and stay with the escort?
Response: See question 11. Workers may possibly be required to stop work and stay with escort. The answer is dependent upon how many workers are present, the location(s) work is being performed, and the number of escorts available.
15- How much time do we need to allocate to bring the large equipment (crane/trucks) to enter
Building 7011 premises, after they enter the base to deliver large equipment?
Response: The coordination to bring large equipment should begging at least one week in advance with bldg.
facility manager to clear all the security requirement. All service vehicles have to go through search at the Lompoc Gate; this process takes a while due to the large amount of vendors trying to gain access to the base. As you can guess, access during the hours of 6 – 9 am are the most congested. Access to the 7000 Complex itself should be fairly easy just provide Calvin Daniels (Certified Security Consultant) with the dates and he will coordinate with the associated personnel. Also, if you could pre-fill the 1109 visitor form for each individual day of operation this would help to; a large amount of time is spent at the ECF filling this form out on the spot.
16. During the job walk and on the demolition plans the Control Panels for AC-2 & AC-3 were not located in an obvious location(s), nor are they located on the demolition plans. Can you provide the location(s) on the demolition plan? They also appeared to be using pneumatic controls. Is this true?
Response: The Contractor shall investigate, design and build (D/B) a solution to bring the below issues up to code compliance and to meet all base, federal and user requirements. The work shall be based on, but not limited to, the concept design provided. The Contractor shall:
1. Verify and update attached design to accommodate building renovations and upgrades completed and in progress since the design was completed and updated design standards identified in paragraph 2.3 below.
17. Will this Data Center project be a separate Controls System from the rest of the building as well as the rest of the 7000 buildings? At this time they are Alerton controls but the new concept design call for a new workstation, software & laptop and a new control system shall be proposed.
Response: New control system shall be proposed
18. It appears in the concept drawings that AH-4 is to get new DDC controls along with AH-3
(previously HV-3 & HV-4). Is this the case? Please clarify.
Response: Yes M-406 shows the controls for AH-4 and AH-3.
19. During the job walk, in UPS room #205 there happens to be a control panel enclosure with
Johnson Controls (JCI) within. Are these controls to remain? Are these controls to be integrated into the new DDC controls system? Are they to left in place? Please clarify.
Response: The control panel enclosure is not on the drawings or part of the scope. Does not need to be integrated and be left in place.
20. On the concept plans it appears the room #203 control room is receiving air by the AH-3 unit without any way of controlling the airflow to maintain a creature comfort temperature setpoint.
Adding control dampers and a respective controller would alleviate large temperature swings and ease creature comfort. Is this part of the scope & intent for this project?
Response: The intent on the project is that the UFC requirement are met for all the room that AHU will supply air. All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
21. Is there a particular location in mind for the new PC workstation called out for on the concept plans (M401)?
Response: The location of the new work station can be discus with user during the 2.3.2 Site Survey / Charrette The Contractor shall avail themselves for a design “Charrette” on the day of or the day after the Kickoff Meeting / Site Survey. The design “Charrette” will allow the Government and/or Contractor to discuss any specific concerns not previously addressed. The Contractor shall document decisions and meeting minutes and provide with the 35% Design below.
22. Is the new DDC controls system to be available from an offsite network or Virtual network?
The reason for asking is that there what appears to be a wireless transmitter located in the boiler room #202 that appears to be connected to the existing Alerton DDC controls system.
Response: Yes
23. Will a third party Facility Management System be integrated to the new DDC system?
Response: It will need to integrate to existing DDC system.
24. Are the control valves on AH-3 & AH-4 (CHW & HW) to be replaced? Are there any issues with them at this time that will require the 3-way valves to be replaced?
Response: All the associated equipment to the CHW and HW will be replaced.
25. Will all new DDC controls wiring be required to be in conduit or can it run free air within the Data Center overhead grid? Conduit shall be used in exposed areas below the ceiling grid.
Response: In conduit.
26. Will the DDC controls contractor be allowed to reuse existing, functional, wiring & conduit?
Response: No.
27. Will existing devices not being reused need to be demoed or abandoned in place, where their location is not needed?
Response: We typically do not want abandoned-in-place equipment, if it can be avoided.
28. Are as-built drawings available? If so, can the contractors get a copy of the as-built drawings?
Response: Due to the security of the building, as-built drawings will not be posted on FBO.gov. As-built drawings are available upon written (email) request to the Contracting Officer and new contract specialist, Meghann Applebay, meghann.applebay@us.af.mil. Due to delays in responding to questions, any previous requests submitted for as-built drawings will need to be resubmitted.
29. Will the contractor be permitted to have a lay-down area inside the existing censored security fence?
Response: This depends on when construction is anticipated to start. It is expected that with all the construction going on now, there will be no room for an additional contractor within the fenced-in area in the near future (the next several months).
30. Are there any known hazardous materials? If yes, is there a hazardous materials survey report?
Response: The survey report will be provided by the contractor. During the 65% design the contractor needs to submit:
c. Environmental Surveys: The Contractor shall provide the environmental surveys and include abatement specifications if asbestos, lead-based paint, PCBs, or underground storage tanks (USTs) are affected by work pertaining to any project.
32. Will the daily point of entrance to the project site be through the existing turnstile access point used at the site visit? Or, will an alternate point of entrance such as on the west side of the building be acceptable?
Response: The daily point of entrance will be the one used at the site visit.
33. The conceptual design drawings (Sheets M-402 and M-404) furnished with the RFP bid documents make reference to “plumbing” drawings. However, there are no plumbing drawings furnished with the conceptual design drawings. Are there any conceptual plumbing design drawings available to the contractors?
Response: No, the Contractor shall investigate, design and build (D/B) a solution to bring the below issues up to code compliance and to meet all base, federal and user requirements. The work shall be based on, but not limited to, the concept design provided. The Contractor shall:
1. Verify and update attached design to accommodate building renovations and upgrades completed and in progress since the design was completed and updated design standards identified in paragraph 2.3 below.
34. The RFP clearly states that the Site Superintendent can also act as the Quality Control Manager as long as they meet the qualifications as stated in the RFP. Can the Site Superintendent also act as the Site Safety Health Officer (SSHO)? One person wearing all three hats!
Response: The Statement of Work does not state the Superintendent and Quality Control Manager will be authorized to be the same individual, but states they shall be two separate individuals unless expressly allowed for by the 30CES PM and 30CONS Contracting Officer. No allowance has being made for this project. While the Superintendent and Quality Control Manager shall be separate individuals, the SSHO may be dual hatted as either the Superintendent or Quality Control Manager.
35. Because there were no camera’s allowed at the site visit, would it be possible to have the
Government provide photos. We would like to request the following photos:
a. Reference Mechanical sheet M-101---------Grid ceiling located between grid lines 3 & 4 and D & F.
b. Reference Mechanical sheet M-101---------Existing duct located adjacent to Room #203; grid lines 3 & 4 and C & D.
c. General photo of existing HVAC unit (to be demolished) located in Room 201.
d. Exterior photo of each side of Building #7011 as well as a photo of the substation yard.
Response: Due to the security of the building, photos will not be posted on FBO.gov. Photos are available upon written (email) request to the Contracting Officer and new contract specialist, Meghann Applebay, meghann.applebay@us.af.mil. Due to delays in responding to questions, any previous requests submitted for
36. SOW 2.2.1-2 identifies scope to replace the building transformer. There are two 500 kVA transformers. Are both transformers in scope for replacement?
37. Does ‘MSA’ or ‘MSB’ need to have the full ampacity (900 Amps) to meet the full load amps of the new 750 kVA transformer(s)?
38. What is the bus rating of MSA and MSB?
Response: Current Single Line Diagram indicates that the incoming circuit breakers for MSA and MSB are rated for 800AF; 700AT.
39. The larger transformer may increase the available fault current to exceed all of the 22KAIC ratings of the existing equipment. Is the Contractor responsible for replacing all of the under rated equipment throughout the building?
Response: Maximum available fault current will not exceed 22KAIC. Due to the security of the building, load study will not be posted on FBO.gov. Load study is available upon written (email) request to the Contracting Officer and new contract specialist, Meghann Applebay, meghann.applebay@us.af.mil. Due to delays in responding to questions, any previous requests submitted for the load study will need to be resubmitted.
40. SOW 2.2.1-3 places responsibility on the Contractor to provide all electrical equipment necessary to meet an unknown demand. The General Note 2 on sheet E-004 requires the Contractor to record load on MSA, MSB, and MCCB. This data may require the upgrade of switchboards, MCCs, conduit, conductors, and other electrical equipment. Is the Contractor responsible for providing all of this unforeseen equipment upgrades under the scope of this project?
41. Is the rating on the existing 12kV switch feeding the 500kVA transformers at least 100 Amps?
Response: Yes, each outgoing way from the switch is equipped with 200A bushings.
42. SOW 2.2.1-7 What are the User requirements for temporary and back-up power during equipment replacements and outages?
Response: Temporary Generator for the bldg. load.
43. Is an arc flash study required? If so, is there a current software file (SKM) of the facility and will it be provided?
Response: VAFB can provide a disk of the short circuit analysis study dated June 20, 2012 after award.
44. Are all of the new circuit breakers to be coordinated with the existing circuit breakers? If so, is there a current coordination study to work from?
Response: See response to Item 43 above.
45. What is the available fault current at the 12 kV point of connection?
Response: Due to the security of the building, load study will not be posted on FBO.gov. Load study is available upon written (email) request to the Contracting Officer and new contract specialist, Meghann Applebay, meghann.applebay@us.af.mil. Due to delays in responding to questions, any previous requests submitted for the load study will need to be resubmitted.
46. Sheet E-001 references many California codes. Are all of these applicable? 2013 CEC => 2017
NEC? Title 24? CBC => IBC? Los Angeles Building Code?
Response: The codes in the concept design are codes the concept designer thought would be applicable, however, they may not be accurate or complete. Per Statement of Work paragraph 2.2.11, the Contractor is required to identify and comply with all applicable federal, state and local statutes. If there is conflict between the codes, the most stringent shall take precedence.
47. Will the Government consider the use of fabric ducts (ductsox) for new interior ductwork?
Response: 2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to those outlined in attached specifications
48. The specifications provided for the project do not appear to represent currently active UFGS specification sections. For example, section 23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC has been superseded. Please confirm that the most current UFGS specifications for all divisions should be followed for the design of this project.
Response: 2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to those outlined in attached specifications
49. Based on the HVAC system specified, energy performance that meets UFC 1-200-02 High
Performance Sustainable Building Requirements does not appear to be achievable. Confirm whether compliance with energy performance criteria in UFC 1-200-02 is required or whether HVAC systems should be modified as required to meet the requirements of the UFC.
Response: 2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to
50. Please confirm that building envelope upgrades to meet the requirements of AHRAE 189.1 are not a requirement of this contract.
Response: 2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to
51. The drawings included in the RFP indicate that emergency power is not a requirement. Please confirm that emergency power for HVAC systems is not required.
Response: Permanent backup power is not required for this project.
52. The equipment capacities shown on the drawings appear to include process load from data center equipment. Will loads be made available prior to bidding to confirm equipment sizing, or should bids be based on equipment capacities in the drawings included in the RFP?
Response: No additional information will be provided.
53. It appears that the project includes some physical security requirements, including bars within ductwork. Is compliance with a specific referenced physical security standard required for the project?
Response: 2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to
54. The intent of the project appears to be to provide redundant HVAC capacity for selected areas of the building. During construction, are there requirements for temporary HVAC system redundancy, above and beyond what is currently existing?
Response: Contractor shall install HVAC system as per UFCs and User requirements.
55. Please identify which rooms require temporary HVAC during construction.
Response: Contractor shall provide temporary cooling as per UFCs and User requirements.
56. Please confirm that existing HVAC systems not modified under this contract are not required to be connected to the new BAS system.
57. Please confirm that the new BAS system is stand-alone and will not be required to integrate with a base-wide DDC system.
Response: It will need to integrate to existing DDC system.
58. Are the new HVAC systems required to comply with UFC 4-010-01 Minimum Antiterrorism
Standards for Buildings including emergency shutoff pushbuttons, low-leakage dampers, and air intakes above 10 feet?
Response: Yes, all work will need to comply with all UFC requirements per Statement of Work paragraph 2.2.3(1).
59. Are there any requirements to integrate HVAC controls with existing halon fire suppression systems?
60. Heat pump units shown for the TEMPEST officer and Comm Sec. Officer appear to be noted as Bid Options on M-201. Please provide a list of all Bid Options.
Response: Disregard note.
61. Please confirm the design indoor space temperature and relative humidity requirements.
Response: Typical electronic room temp and humidity is:
Ambient temp 68 - 75 degree F.
Humidity 40%-60%
62. At (E) AC-2 and (E) AC-3, the plans indicate two existing (E) 30x30 Supply Air openings. Are there existing Return Air openings and what are the sizes and locations of those openings?
Response: Contractor shall verify and update attached design to accommodate building renovations and upgrades completed and in progress since the design was completed and updated design standards identified in paragraph
2.3 below.
63. Can any temporary HVAC equipment be stationed in the roadway immediately south of the building?
Response: All the staging areas will be identified during the 2.3.2 Site Survey / Charrette.
64. Please indicate if existing building utilities can be utilized to power temporary HVAC units or if a generator will need to be supplied for that power.
Response: The Contractor will be authorized to tie into existing utilities at their own cost.
65. Are security measures, i.e. bars at wall penetrations, required for temporary HVAC openings?
Response: (1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to
66. Please indicate if compression-type solderless piping connections are allowable for refrigerant and condensate piping < 1.5” i.d. at FC1 and FC2.
Response: 2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to
67. Is the transformer increase requirement due to new mechanical system equipment loads or for another purpose? If for another purpose, please indicate what the purpose is.
Response: Contractor’s responsibility to perform a Load Study addressing existing load and any additional load for new HVAC equipment.
68. Based on the electrical single-line diagram included in the RFP (sheet E-003), there are two
500KVA, 12KV-480V transformers in the existing electrical yard. Please indicate (on sheet E-
003) which transformer is required to be upgraded.
Response: The Contractor shall replace the transformer with serial #PCT 7986-01, see picture DSFF0050
69. The load summaries shown on the RFP drawings (sheet E-004) indicate the demand loads for
MSA and MSB are larger than 500KVA and would therefore indicate a need to replace and upgrade both of the existing 500KVA transformers. Are both existing transformers required to be upgraded?
Response: Only one transformer will be upgraded.
70. Does the primary 12KV feeder need to be replaced?
71. Since the transformer capacity is being upgraded, the secondary feeder and switchboard will also need to be upgraded to a larger capacity. Please confirm this is a project requirement.
Response: Per Statement of Work 2.2.1.3, the contractor is required to install electrical equipment to meet electrical demand requirements.
72. Has the government confirmed there is enough space in the existing electrical yard to house the larger transformer?
Response: This will be part of the Contractor’s responsibility to determine during design.
73. Will the contractor be required to provide temporary power while the transformer is being replaced/upgraded?
Response: Yes, the contractor will be responsible for providing temporary power.
74. Please indicate the specific UFC applicable for this facility regarding backup power.
Response: 2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to
75. Please indicate user requirements regarding permanent and temporary backup power.
Response: No permanent backup power necessary on this project it will be done under another CE project.
Temporary power will be needed for any outage cause by the replacement of transformer.
2.2.3 DESIGN REQUIREMENTS:
(1) All design/construction shall comply with DoD Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS)
(2) All Design/construction shall comply with the VAFB Facilities Excellence Standards
(3) All design/construction shall comply with local, State and Federal standards included but not limited to
76. Is the intent to provide permanent backup power to one or both of the existing 12KV-480V transformers (entire facility) or only to specific equipment? If to specific equipment, provide list of equipment that needs to be provided with permanent backup power.
Response: Permanent backup power will be installed for the 7011 with a different contract.
77. If permanent backup power is a project requirement, then please provide minimum generator system requirements such as fuel type, amount of time the generator needs to supply backup power during a power outage, type of transfer switch, etc.
Response: Permanent backup power is not required on the project.
78. If a permanent backup power is determined to be required, does the generator need to be enclosed by a wall or chain linked fence?
Response: Permanent backup power is not required on the project.
79. Please provide last year’s, electrical peak demand load (in amps or VA) for the two existing
500KVA, 12KV-480V transformers. This information will be needed to perform electrical calculations to confirm existing/new transformers and switchboards are properly sized (or larger ones required) for new HVAC loads.
Response: Contractor’s responsibility to perform a Load Study addressing existing load and any additional load for new HVAC equipment.
80. Please provide copy of all electrical calculations developed by the electrical engineer in conjunction with the RFP electrical drawings.
Response: No electrical calculations available, contractor is responsible to provide them on the new design.
81. Please confirm that temporary cooling equipment can be provided with temporary type normal electrical power and does not need to be provided with backup power systems.
Response: Yes the temporary cooling equipment can be provided with temporary type normal electrical power4 but the Contractor shall install it as per UFCs and User requirements.
82. Indicate if there are any redundant electrical systems required for the new HVAC equipment; if there are, provide requirements.
Response: Primary power has a redundant feeder and will have a back-up generator.
83. Can the Government provide the name of the contractor that recently installed the Halon Fire
Protection System?
Response: A Halon system was not installed. The installed system is FM-200 clean agent system and was installed by Spectrum Services Group.
84. Would the Government entertain the possibility of a second site visit to B-7011?
Response: No, a second site visit will not be conducted
85. Due to the fact that no photos were allowed on the site visit, we respectfully ask the
Government to provide photos of the following:
a. The outdoor electrical yard housing the main substation/pad-mounted transformers and mains service switchboards, and including the exterior wall of Column Line 2 above the electrical yard.
b. The existing 500KVA transformer that is required to be upgraded, including the area surrounding the transformer.
c. Photos of existing MCCA & MCCB
d. Photos of the name plates on AC-2, CU-2, AC-4, ACC-4, the Outdoor Chiller, the AC unit in the Mechanical Room, and the existing boiler.
e. Photos of Interior and exterior wall penetrations for supply air, and return air and SWR ducts at (E) AC2 and (E) AC3
f. Photos of the motor-controllers for existing AH-3, in relation to the passage door(s) and the
AH that is to be replaced.
g. General photos of the overhead cable tray system in the Data Center.
h. the existing pavement & curbing, the screen walls, the existing equipment, and the existing penetrations through the exterior walls for existing equipment.
Response: Due to the security of the building, photos will not be posted on FBO.gov. Photos are available upon written (email) request to the Contracting Officer and new contract specialist, Meghann Applebay, meghann.applebay@us.af.mil. Due to delays in responding to questions, any previous requests submitted for
86. RFP Page 26 references this as a competitive Total Small Business Set-Aside while the SF1442 indicates a set-aside for WOSB. Can you please confirm this is restricted to WOSB firms?
Response: Page 26 was a typographical error. This requirement is set-aside for Woman-Owned Small Businesses.
87. The SF1442 indicates that a Bid Guarantee is not required. Should offeror's submit a letter from their surety demonstrating bonding capacity with the Volume I proposal?
Response: This is not required.
88. The RFP does not provide an outline of what items (e.g., SF1442, Section B Price, Representations and Certifications, Pricing Back-up Documentation, etc.) should be included within Volume I - Executed Contract Documentation and Price Proposal. Can you please provide submission requirements for Volume I?
Response: See Section L of the amendment.
89. RFP page 31 provides a Proposal Adequacy Checklist for completion. Should this checklist be completed and submitted with Volume I as part of the proposal submission?
Response: Not required. The checklist is for contractor use when preparing their proposal.
90. RFP page 39 of 39 indicates the "Price proposal will be evaluated by reviewing the overall proposed price proposed by the Offeror in Section B." However, the Proposal Adequacy Checklist on RFP page 21 seems to imply that pricing back-up documentation should be submitted with the proposal. Can you please clarify the requirements for providing pricing backup documentation with Volume I?
Response: The Proposal Adequacy Checklist is a standard DFARS provision and my contain items/tasks which are not applicable to this solicitation. Evaluations will be conducted in accordance with the criteria established in Section M.
91. The RFP indicates, "Typeface shall not be less than 12 font, with 1” margins on all sides.
Smaller, legible font size, no smaller than 6 point, may be used for charts and tables. Is it acceptable to use a font size smaller than 12 in the header/footer of the proposal response documents?
Response: Yes, headers/footers may be less than 12.